The Price-Anderson Act (Act), having the dual purpose of
protecting the public and encouraging the development of the
nuclear energy industry, imposes a $560 million limitation on
liability for nuclear accidents resulting from the operation of
federally licensed private nuclear power plants, requires those
indemnified by the $560 million fund established under the Act to
waive all legal defenses in the event of a substantial nuclear
accident, and further provides that, in the event of a nuclear
accident involving damages in excess of the amount of aggregate
liability, Congress "will take whatever action is deemed necessary
and appropriate to protect the public from the consequences of a
disaster of such magnitude." Appellant Duke Power Co. (Duke), an
investor-owned public utility which is constructing nuclear power
plants in North and South Carolina, and appellant Nuclear
Regulatory Commission (NRC), were sued by appellees (an
environmental organization, a labor union, and a number of
individuals who live near the plants in question) who sought a
declaration that the Act is unconstitutional. After finding,
inter alia, that the "immediate" adverse effects upon
appellees resulting from the operation of the plants included
thermal pollution of lakes in the vicinity, and emission of
non-natural radiation into appellees' environment, and also that
there was a "substantial likelihood" that Duke would not be able to
complete construction and maintain operation of the plants "but
for" the protection provided by the Act, the District Court held
that appellees had standing to challenge the Act's
constitutionality, and that their claim could be properly
adjudicated. The court then went on to hold that the Act violated
the Due Process Clause of the Fifth Amendment because the amount of
recovery is not rationally related to the potential losses, the Act
tends to encourage irresponsibility in matters of safety and
environmental protection, and there is no
quid pro quo for
the liability limitation; and the Act also offended the equal
Page 438 U. S. 60
protection component of the Fifth Amendment by forcing the
victims of nuclear incidents to bear the burden of injury, whereas
society as a whole benefits from the existence and development of
nuclear power.
Held:
1. The District Court had jurisdiction over appellees' complaint
against the NRC under 28 U.S.C. § 1331(a) (1976 ed.), rather than §
1337, the jurisdictional base pleaded. The complaint, fairly read,
raised two basic challenges to the Act, both of which are derived
from the Fifth Amendment. Appellees' cause of action against the
NRC directly under the Constitution is sufficiently substantial to
sustain jurisdiction; the further question of whether such a cause
of action is to be generally recognized need not be decided on this
record. Pp.
438 U. S.
68-72.
2. Appellees have standing to challenge the Act's
constitutionality. That several of the "immediate" adverse effects
of construction of the plants were found to harm appellees is
sufficient to satisfy the "injury in fact" prong of the
constitutional requirement for standing. And the finding as to the
"but for" causal connection between the Act and the construction of
the plants satisfies the second prong of the constitutional test
for standing, that the exercise of the court's remedial powers
would redress the claimed injuries. Pp.
438 U. S.
72-81.
3. The constitutional challenges to the Act are ripe for
adjudication, since all parties would be adversely affected by a
decision to defer definitive resolution of the constitutional
validity
vel non of the Act. To the extent that "issues of
ripeness involve, at least in part, the existence of a live
Case or Controversy,'" Regional Rail Reorganization Act
Cases, 419 U. S. 102,
419 U. S. 138
(1974), the fact that appellees will sustain immediate injury from
the operation of the disputed power plants and that such injury
would be redressed by the relief requested satisfies this
requirement. Pp. 438 U. S.
81-82.
4. The Act does not violate the Due Process Clause of the Fifth
Amendment. Pp.
438 U. S.
82-94.
(a) The record supports the need for the imposition of a
statutory limit on liability to encourage private industry
participation, and hence bears a rational relationship to Congress'
concern for stimulating private industry's involvement in the
production of nuclear electric energy. P.
438 U. S.
84.
(b) Assuming,
arguendo, that the $560 million fund
would not insure full recovery in all conceivable circumstances, it
does not follow that the liability limitation is therefore
irrational and violative of due process. When appraised in light of
the extremely remote possibility of an accident in which liability
would exceed the statutory limit and Congress' commitment to "take
whatever action is deemed necessary and appropriate
Page 438 U. S. 61
to protect the, public from the consequences of" a disaster of
such proportions, the congressional decision to fix a $560 million
ceiling is within permissible limits, and not violative of due
process. Pp.
438 U. S.
84-87.
(c) The District Court's finding that the Act tends to encourage
irresponsibility in matters of safety and environmental protection
cannot withstand careful scrutiny, since nothing in the liability
limitation provision undermines or alters the rigor and integrity
of the process involved in the review of applications for a license
to construct or operate a nuclear power plant, and since, in the
event of a nuclear accident, the utility itself would probably
suffer the largest damages. P.
438 U. S.
87.
(d) The Act provides a reasonably just substitute for the common
law or state tort law remedies it replaces, and nothing more is
required by the Due Process Clause. The congressional assurance of
a $560 million fund for recovery, accompanied by the statutory
commitment to "take whatever action is deemed necessary and
appropriate to protect the public from the consequences of" a
nuclear accident, is a fair and reasonable substitute for the
uncertain recovery of damages of this magnitude from a utility or
component manufacturer whose resources might well be exhausted at
an early stage. And, at the minimum, the statutorily mandated
waiver of defenses establishes at the threshold the right of
injured parties to compensation without proof of fault, and
eliminates the burden of delay and uncertainty that would follow
from the need to litigate the question of liability after an
accident. Pp.
438 U. S.
87-93.
(e) There is no equal protection violation, since the general
rationality of the Act's liability limitation, particularly with
reference to the congressional purpose of encouraging private
participation in the exploitation of nuclear energy, is ample
justification for the difference in treatment between those injured
in nuclear accidents and those whose injuries are derived from
other causes. Pp.
438 U. S.
93-94.
5. The Act does not withdraw the Tucker Act remedy, 28 U.S.C. §
1491, and thus appellees' challenge under the Just Compensation
Clause must fail. The further question of whether a taking claim
could be established under the Fifth Amendment is a matter
appropriately left for another day. P.
438 U. S. 94 n.
39.
431 F.
Supp. 203, reversed and remanded.
BURGER, C.J., delivered the opinion of the Court, in which
BRENNAN, WHITE, MARSHALL, BLACKMUN, and POWELL, JJ., joined.
STEWART, J., filed an opinion concurring in the result,
post, p.
438 U. S. 94.
REHNQUIST, J., filed an opinion concurring in the judgment, in
which STEVENS, J., joined,
post, p.
438 U. S. 95.
STEVENS, J., filed an opinion concurring in the judgment,
post, p.
438 U. S.
102.
Page 438 U. S. 62
MR. CHIEF JUSTICE BURGER delivered the opinion of the Court.
These appeals present the question of whether Congress may,
consistent with the Constitution, impose a limitation on
Page 438 U. S. 63
liability for nuclear accidents resulting from the operation of
private nuclear power plants licensed by the Federal
Government.
When Congress passed the Atomic Energy Act of 1946, it
contemplated that the development of nuclear power would be a
Government monopoly.
See Act of Aug. 1, 1946, ch. 724, 60
Stat. 755. Within a decade, however, Congress concluded that the
national interest would be best served if the Government encouraged
the private sector to become involved in the development of atomic
energy for peaceful purposes under a program of federal regulation
and licensing.
See H.R.Rep. No. 2181, 83d Cong., 2d Sess.,
1-11 (1954). The Atomic Energy Act of 1954, Act of Aug. 30, 1954,
ch. 1073, 68 Stat. 919, as amended, 42 U.S.C. §§ 2011-2281 (1970
ed. and Supp. V), implemented this policy decision, providing for
licensing of private construction, ownership, and operation of
commercial nuclear power reactors for energy production under
strict supervision by the Atomic Energy Commission (AEC). [
Footnote 1]
See Power Reactor
Development Co. v. Electrical Workers, 367 U.
S. 396 (1961),
rev'g and remanding 108
U.S.App.D.C. 97, 280 F.2d 645 (1960).
Private industry responded to the Atomic Energy Act of 1954 with
the development of an experimental power plant constructed under
the auspices of a consortium of interested companies. It soon
became apparent that profits from the private exploitation of
atomic energy were uncertain, and the accompanying risks
substantial.
See Green, Nuclear Power:
Page 438 U. S. 64
Risk, Liability,.and Indemnity, 71 Mich.L.Rev. 479-481 (1973)
(Green). Although the AEC offered incentives to encourage
investment, there remained in the path of the private nuclear power
industry various problems -- the risk of potentially vast liability
in the event of a nuclear accident of a sizable magnitude being the
major obstacle. Notwithstanding comprehensive testing and study,
the uniqueness of this form of energy production made it impossible
totally to rule out the risk of a major nuclear accident resulting
in extensive damage. Private industry and the AEC were confident
that such a disaster would not occur, but the very uniqueness of
nuclear power meant that the possibility remained, and the
potential liability dwarfed the ability of the industry and private
insurance companies to absorb the risk.
See Hearings
before the Joint Committee on Atomic Energy on Government Indemnity
for Private Licensees and AEC Contractors Against Reactor Hazards,
84th Cong., 2d Sess., 122-124 (1956). Thus, while repeatedly
stressing that the risk of a major nuclear accident was extremely
remote, spokesmen for the private sector informed Congress that
they would be forced to withdraw from the field if their liability
were not limited by appropriate legislation.
Id. at 9,
109-110, 115, 120, 136-137, 148, 181, 195, and 240.
Congress responded in 1957 by passing the Price-Anderson Act, 71
Stat. 576, 42 U.S.C. § 2210 (1970 ed. and Supp. V). The Act had the
dual purpose of "protect[ing] the public and . . . encourag[ing]
the development of the atomic energy industry." 42 U.S.C. §
2012(i). In its original form, the Act limited the aggregate
liability for a single nuclear incident [
Footnote 2] to $500 million plus the amount of
liability insurance
Page 438 U. S. 65
available on the private market -- some $60 million in 1957. The
nuclear industry was required to purchase the maximum available
amount of privately underwritten public liability insurance, and
the Act provided that, if damages from a nuclear disaster exceeded
the amount of that private insurance coverage, the Federal
Government would indemnify the licensee and other "persons
indemnified" [
Footnote 3] in an
amount not to exceed $500 million. Thus, the actual ceiling on
liability was the amount of private insurance coverage plus the
Government's indemnification obligation, which totaled $560
million.
Since its enactment, the Act has been twice amended, the first
occasion being on the eve of its expiration in 1966. [
Footnote 4] These amendments extended the
basic liability limitation provisions for another 10 years, and
added a provision which had the effect of requiring those
indemnified under the Act to waive all legal defenses in the event
of a substantial nuclear accident. [
Footnote 5] This provision was based on a congressional
concern that state tort law dealing with liability for nuclear
incidents was generally unsettled, and that some way of insuring a
common standard of responsibility for all jurisdictions -- strict
liability -- was needed. A waiver of defenses was thought to be the
preferable approach, since it entailed less
Page 438 U. S. 66
interference with state tort law than would the enactment of a
federal statute prescribing strict liability. [
Footnote 6]
See S.Rep. No. 1605, 89th
Cong., 2d Sess., 6-10 (1966).
In 1975, Congress again extended the Act's coverage until 1987,
and continued the $560 million limitation on liability. However, a
new provision was added requiring, in the event of a nuclear
incident, each of the 60 or more reactor owners to contribute
between $2 and $5 million toward the cost of compensating victims.
[
Footnote 7] 42 U.S.C. §
2210(b) (1970 ed., Supp. V). Since the liability ceiling remained
at the same level, the effect of the "deferred premium" provision
was to reduce the Federal Government's contribution to the
liability pool. [
Footnote 8] In
its amendments to the Act in 1975, Congress also explicitly
provided that,
"in the event of a nuclear incident involving damages in excess
of [the] amount of aggregate liability, the Congress will
thoroughly review the particular incident and will take whatever
action is deemed necessary and appropriate to protect the public
from the consequences of a
Page 438 U. S. 67
disaster of such magnitude. . . ."
42 U.S.C. § 2210(e) (1970 ed., Supp. V).
Under the Price-Anderson Act as it presently stands, liability
in the event of a nuclear incident causing damages of $560 million
or more would be spread as follows: $315 million would be paid from
contributions by the licensees of the 63 private operating nuclear
power plants; $140 million would come from private insurance (the
maximum now available); the remainder of $105 million would be
borne by the Federal Government. [
Footnote 9]
B
Appellant in No. 77-262, Duke Power Co., is an investor-owned
public utility which is constructing one nuclear power plant in
North Carolina and one in South Carolina. Duke Power, along with
the NRC, was sued by appellees, two organizations -- Carolina
Environmental Study Group and the Catawba Central Labor Union --
and 40 individuals who live within close proximity to the planned
facilities. The action was commenced in 1973, and sought, among
other relief, a declaration that the Price-Anderson Act is
unconstitutional. [
Footnote
10]
After the parties had engaged in extensive discovery, the
District Court held an evidentiary hearing on the questions of
whether the issues were ripe for adjudication and whether
Page 438 U. S. 68
appellees had standing to challenge the constitutionality of the
Act. That court determined that appellees had standing, and that
their claim could properly be adjudicated. The District Court went
on to hold that the Price-Anderson Act was unconstitutional in two
respects: (a) it violated the Due Process Clause of the Fifth
Amendment because it allowed injuries to occur without assuring
adequate compensation to the victims; (b) the Act offended the
equal protection component of the Fifth Amendment by forcing the
victims of nuclear incidents to bear the burden of injury, whereas
society as a whole benefits from the existence and development of
nuclear power.
We noted probable jurisdiction [
Footnote 11] in these appeals, 434 U.S. 937 (1977), and
we now reverse.
II
As a threshold matter, we must address the question of whether
the District Court had subject matter jurisdiction over appellees'
claims, despite the fact that none of the parties raised this
issue, and the District Court did not consider it.
See Liberty
Mutual Ins. Co. v. Wetzel, 424 U. S. 737,
424 U. S. 740
(1976). Appellees' complaint alleges jurisdiction under 28 U.S.C. §
1337 (1976 ed.), which provides for original jurisdiction in the
district courts over
"any civil action or proceeding arising under any Act of
Congress regulating commerce or protecting trade and commerce
against restraints and monopolies."
Our reading of the pleadings, [
Footnote 12] however, indicates that
Page 438 U. S. 69
appellees' claims do not "arise under" the Price-Anderson Act as
that statutory language has been interpreted in prior decisions.
See Peyton v. Railway Express Agency, 316 U.
S. 350,
316 U. S. 353
(142).
Specifically, as we read the complaint, appellees are making two
basic challenges to the Act -- both of which find their moorings in
the Fifth Amendment. First, appellees contend that the Due Process
Clause protects them against arbitrary governmental action
adversely affecting their property rights, and that the
Price-Anderson Act -- which both creates the source of the
underlying injury and limits the recovery therefor -- constitutes
such arbitrary action. And second, they are contending that, in the
event of a nuclear accident, their property would be "taken"
without any assurance of just compensation. The Price-Anderson Act
is the instrument of the taking, since on this record, without it,
there would be no power plants and no possibility of an accident.
Implicit in the complaint is also the assumption that there exists
a cause of action directly under the Constitution to vindicate
appellees' federal rights through a suit against the NRC, the
executive agency charged with enforcement and administration of the
allegedly unconstitutional statute. [
Footnote 13] Appellees' right to relief
Page 438 U. S. 70
thus depends not on the interpretation or construction of the
Price-Anderson Act itself, but instead "upon the construction or
application of the Constitution,"
Smith v. Kansas City Title
& Trust Co., 255 U. S. 10,
255 U. S. 199
(1921). Hence, if there exists jurisdiction to hear appellees'
claims at all, it must be derived from 28 U.S.C. § 1331(a) (1976
ed.), the general federal question statute, rather than from § 1337
-- the jurisdictional base pleaded. [
Footnote 14]
For purposes of determining whether jurisdiction exists under §
1331(a) to resolve appellees' claims, it is not necessary to decide
whether appellees' alleged cause of action against the NRC based
directly on the Constitution is, in fact, a cause of action "on
which [appellees] could actually recover."
Bell v. Hood,
327 U. S. 678,
327 U. S. 682
(1946). Instead, the test is whether "
the cause of action
alleged is so patently without merit as to justify . . .
the court's dismissal for want of jurisdiction.'" Hagans v.
Lavine, 415 U. S. 528,
415 U. S.
542-543 (1974), quoting Bell v. Hood, supra, at
327 U. S. 683.
(Emphasis added.) See also Oneida Indian Nation v. County of
Oneida, 414 U. S. 661,
414 U. S. 666
(1974) (test is whether right claimed is "so insubstantial,
implausible, foreclosed by prior decisions of this
Page 438 U. S. 71
Court, or otherwise completely devoid of merit as not to involve
a federal controversy"). In light of prior decisions, for example,
Bivens v. Six Unknown Fed. Narcotics Agents, 403 U.
S. 388 (1971), and
Hagans v. Lavine, supra, as
well as the general admonition that, "where federally protected
rights have been invaded . . . , courts will be alert to adjust
their remedies so as to grant the necessary relief,"
Bell v.
Hood, supra at
327 U. S. 684,
we conclude that appellees' allegations are sufficient to sustain
jurisdiction under § 1331(a). [
Footnote 15]
The further question of whether appellees' cause of action under
the Constitution is one generally to be recognized need not be
decided here. The question does not directly implicate our
jurisdiction,
see Bell v. Hood, supra, was not raised in
the court below, was not briefed, and was not addressed during oral
argument. As we noted last Term in a similar context, questions of
this sort should not be resolved on such an inadequate record;
leaving them unresolved is no bar to full consideration of the
merits.
See Mt. Healthy Cty Bd. of Educ. v. Doyle,
429 U. S. 274,
429 U. S.
278-279 (1977). It is enough for present purposes that
the claimed cause of action to vindicate appellees'
Page 438 U. S. 72
constitutional rights is sufficiently substantial and colorable
to sustain jurisdiction under § 1331(a). [
Footnote 16]
III
The District Judge held four days of hearings on the questions
of standing and ripeness; his factual findings form the basis for
our analysis of these issues.
A
The essence of the standing inquiry is whether the parties
seeking to invoke the court's jurisdiction have
"alleged such a personal stake in the outcome of the controversy
as to assure that concrete adverseness which sharpens the
presentation of issues upon which the court so largely depends for
illumination of difficult constitutional questions."
Baker v. Carr, 369 U. S. 186,
369 U. S. 204
(1962). As refined by subsequent reformulation, this requirement of
a "personal stake" has come to be understood to require not only a
"distinct and palpable injury," to the plaintiff,
Warth v.
Seldin, 422 U. S. 490,
422 U. S. 501
(1975), but also a "fairly traceable" causal connection between the
claimed injury and the challenged conduct.
Arlington Heights v.
Metropolitan Housing Dev. Corp., 429 U.
S. 252,
429 U. S. 261
(1977).
See also Simon v. Eastern Ky. Welfare Rights Org.,
426 U. S. 26,
426 U. S. 41-42
(1976);
Linda R.S. v. Richard D., 410 U.
S. 614,
410 U. S. 617
(1973). Application of these constitutional standards to the
factual findings of the District Court persuades us that the Art.
III requisites for standing are satisfied by appellees. We turn
first to consider the kinds of injuries the District Court found
the appellees suffered. It discerned two categories of effects
which resulted from the operation of nuclear
Page 438 U. S. 73
power plants in potentially dangerous proximity to appellees'
living and working environment. The immediate effects included: (a)
the production of small quantities of non-natural radiation which
would invade the air and water; (b) a "sharp increase" in the
temperature of two lakes presently used for recreational purposes
resulting from the use of the lake waters to produce steam and to
cool the reactor; (c) interference with the normal use of the
waters of the Catawba River; (d) threatened reduction in property
values of land neighboring the power plants; (e) "objectively
reasonable" present fear and apprehension regarding the "effect of
the increased radioactivity in air, land and water upon [appellees]
and their property, and the genetic effects upon their
descendants"; and (f) the continual threat of "an accident
resulting in uncontrolled release of large or even small quantities
of radioactive material" with no assurance of adequate compensation
for the resultant damage.
431 F.
Supp. 203, 209. Into a second category of potential effects
were placed the damages "which may result from a core melt or other
major accident in the operation of a reactor. . . ."
Id.
at 209. [
Footnote 17]
For purposes of the present inquiry, we need not determine
whether all the putative injuries identified by the District Court,
particularly those based on the possibility of a nuclear accident
and the present apprehension generated by this future uncertainty,
are sufficiently concrete to satisfy constitutional requirements.
Compare O'Shea v. Littleton, 414 U.
S. 488 (1974),
with United States v. SCRAP,
412 U. S. 669
(1973).
See also Conservation Society of Southern Vermont v.
AEC, Civ. Action No.19-72 (DC Apr. 17, 1975). It is enough
that several of the "immediate" adverse effects were found to harm
appellees. Certainly the environmental and aesthetic consequences
of the thermal pollution of the two lakes in the vicinity of the
disputed power plants is the type
Page 438 U. S. 74
of harmful effect which has been deemed adequate in prior cases
to satisfy the "injury in fact" standard.
See United States v.
SCRAP, supra. Cf. Sierra Club v. Morton, 405 U.
S. 727,
405 U. S. 734
(1972). [
Footnote 18] And
the emission of non-natural radiation into appellees' environment
would also seem a direct and present injury, given our generalized
concern about exposure to radiation and the apprehension flowing
from the uncertainty about the health and genetic consequences of
even small emissions like those concededly emitted by nuclear power
plants. [
Footnote 19]
The more difficult step in the standing inquiry is establishing
that these injuries "fairly can be traced to the challenged action
of the defendant,"
Simon v. Eastern Ky. Welfare Rights Org.,
supra at
426 U. S. 41,
or, put otherwise, that the exercise of the Court's remedial powers
would redress the claimed injuries. 426 U.S. at
426 U. S. 43.
The District Court discerned a "but for" causal connection between
the Price-Anderson Act, which appellees challenged as
unconstitutional, "and the construction of the nuclear plants which
the [appellees] view as a threat to them." 431 F. Supp. at 219.
Particularizing that causal link to the facts of the instant case,
the District Court concluded that
"there is a substantial likelihood that Duke would not be able
to complete the construction and maintain the operation of the
McGuire and Catawba Nuclear Plants
Page 438 U. S. 75
but for the protection provided by the Price-Anderson Act."
Id. at 220.
These findings, which, if accepted, would likely satisfy the
second prong of the constitutional test for standing as elaborated
in
Simon, [
Footnote
20] are challenged on two grounds. First, it is argued that the
evidence presented at the hearing, contrary to the conclusion
reached by the District Court, indicated that the McGuire and
Catawba nuclear plants would be completed and operated without the
Price-Anderson Act's limitation on liability. And second, it is
contended that the Price-Anderson Act is not, in some essential
sense, the "but for" cause of the disputed nuclear power plants and
resultant adverse effects, since, if the Act had not been passed,
Congress may well have chosen to pursue the nuclear program as a
Government monopoly, as it had from 1946 until 1954. We reject both
of these arguments.
The District Court's finding of a "substantial likelihood" that
the McGuire and Catawba nuclear plants would be neither completed
nor operated absent the Price-Anderson Act rested in major part on
the testimony of corporate officials before the Joint Committee on
Atomic Energy (JCAE) in 1956-1957, when the Price-Anderson Act was
first considered, and again in 1975, when a second renewal was
discussed. During the 1956-1957 hearings, industry spokesmen for
the utilities and the producers of the various component parts of
the power plants expressed a categorical unwillingness to
participate in the development of nuclear power absent guarantees
of a limitation on their liability. 431 F. Supp. at 215.
See
also
Page 438 U. S. 76
Green 486, 490-491. [
Footnote
21] By 1975, the tenor of the testimony had changed only
slightly. While large utilities and producers were somewhat more
equivocal about whether a failure to renew Price-Anderson would
entail their leaving the industry, the smaller producers of
component parts and architects and engineers -- all of whom are
essential to the building of the reactors and generating plants --
considered renewal of the Act as the critical variable in
determining their continued involvement with nuclear power. 431 F.
Supp. at 216-217. Duke Power itself, in its letter to the Committee
urging extension of the Act, cited recent experiences with
suppliers and contractors who were requiring the inclusion of
cancellation clauses in their contracts to take effect if the
liability limitation provisions were eliminated.
Id. at
217. And the Report of the JCAE, in discussing the need for renewal
of the Act, stated:
"Nuclear power plants now in the planning and design phases
would not receive construction permits until about 1977-1978. Thus,
there is uncertainty as to whether these plants would receive
protection in the form of Government indemnity. Reactor
manufacturers and architect-engineers are already requiring escape
clauses in their contracts to permit cancellation in the event some
form of protection from unlimited potential liability is not
provided. Action is required soon to prevent disruption in utility
plans for nuclear power."
H.R.Rep. No. 9648, p. 7 (1975)
Nor was the testimony at the hearing in this case, evaluation of
which is the primary responsibility of the trial judge, at odds
with the impression drawn from the legislative history. The
testimony of Executive Vice President Lee of Duke Power
Page 438 U. S. 77
simply echoed the views presented by Duke and others to Congress
in 1975, that is, although some of the utilities themselves might
be confident enough with respect to safety factors to proceed with
nuclear power absent a liability limitation, the suppliers of
critical parts and the utility shareholders could reasonably be
expected to take a more cautious view. [
Footnote 22] Appellees presented expert testimony
essentially to the same effect. Considering the documentary
evidence and the testimony in the record, we cannot say we are left
with "the definite and firm conviction that" the finding by the
trial court of a substantial likelihood that the McGuire and
Catawba nuclear power plants would be neither completed nor
operated absent the Price-Anderson Act is clearly erroneous; and,
hence, we are bound to accept it.
United States v. United
States Gypsum Co., 333 U. S. 364,
333 U. S. 395
(1948).
The second attack on the District Court's finding of a causal
link warrants only brief attention. Essentially, the argument is,
as we understand it, that Price-Anderson is not a "but for" cause
of the injuries appellees claim, since, if Price-Anderson had not
been passed, the Government would have undertaken development of
nuclear power on its own, and the same injuries would likely have
accrued to appellees from such Government-operated plants as from
privately operated ones. Whatever the ultimate accuracy of this
speculation, it is not responsive to the simple proposition that
private power companies now do, in fact, operate the nuclear
powered generating plants injuring
Page 438 U. S. 78
appellees, and that their participation would not have occurred
but for the enactment and implementation of the Price-Anderson Act.
Nothing in our prior cases requires a party seeking to invoke
federal jurisdiction to negate the kind of speculative and
hypothetical possibilities suggested in order to demonstrate the
likely effectiveness of judicial relief.
B
It is further contended that, in addition to proof of injury and
of a causal link between such injury and the challenged conduct,
appellees must demonstrate a connection between the injuries they
claim and the constitutional rights being asserted. This nexus
requirement is said to find its origin in
Flast v. Cohen,
392 U. S. 83
(1968), where the general question of taxpayer standing was
considered:
"The nexus demanded of federal taxpayers has two aspects to it.
First, the taxpayer must establish a logical link between that
status and the type of legislative enactment attacked. . . .
Secondly, the taxpayer must establish a nexus between that status
and the precise nature of the constitutional infringement
alleged."
Id. at
392 U. S. 102.
See also United States v. Richardson, 418 U.
S. 166,
418 U. S.
174-175 (1974). Since the environmental and health
injuries claimed by appellees are not directly related to the
constitutional attack on the Price-Anderson Act, such injuries, the
argument continues, cannot supply a predicate for standing.
[
Footnote 23] We decline to
accept this argument.
The major difficulty with the argument is that it implicitly
assumes that the nexus requirement formulated in the context of
taxpayer suits has general applicability in suits of all other
types brought in the federal courts. No cases have been cited
Page 438 U. S. 79
outside the context of taxpayer suits where we have demanded
this type of subject matter nexus between the right asserted and
the injury alleged, and we are aware of none. [
Footnote 24] Instead, in
Schlesinger v.
Reservists Comm. to Stop the War, 418 U.
S. 208,
418 U. S. 225
n. 15 (1974), we explicitly rejected such a broad compass for the
Flast nexus requirement:
"Looking 'to the substantive issues' which
Flast stated
to be both 'appropriate and necessary' in relation to taxpayer
standing was for the express purpose of determining 'whether there
is a logical nexus between the [taxpayer] status asserted and the
claim sought to be adjudicated.' 392 U.S. at
392 U. S.
102. This step is not appropriate on a claim of citizen
standing, since the
Flast nexus test is not applicable
where the taxing and spending power is not challenged. . . ."
We continue to be of the same view, and cannot accept the
contention that, outside the context of taxpayers' suits, a
litigant must demonstrate something more than injury in fact and a
substantial likelihood that the judicial relief requested will
prevent or redress the claimed injury to satisfy the "case or
controversy" requirement of Art. III. [
Footnote 25]
Page 438 U. S. 80
Our prior cases have, however, acknowledged "other limits on the
class of persons who may invoke the courts' decisional and remedial
powers,"
Warth v. Seldin, 422 U.S. at
422 U. S. 499,
which derive from general prudential concerns "about the proper --
and properly limited -- role of the courts in a democratic
society."
Id. at
422 U. S. 498.
See also Schlesinger v. Reservists Comm. to Stop the War,
supra at
418 U. S.
221-227. Thus, we have declined to grant standing where
the harm asserted amounts only to a generalized grievance shared by
a large number of citizens in a substantially equal measure.
See United States v. Richardson, supra. We have also
narrowly limited the circumstances in which one party will be given
standing to assert the legal rights of another.
"[E]ven when the plaintiff has alleged injury sufficient to meet
the 'case or controversy' requirement, this Court has held that the
plaintiff generally must assert his own legal rights and interests,
and cannot rest his claim to relief on the legal rights or
interests of third parties."
Warth v. Seldin, supra at
422 U. S. 499.
See also United States v. Raines, 362 U. S.
17 (1960). This limitation on third-party standing
arguably suggests a connection between the claimed injury and the
right asserted bearing some resemblance to the nexus requirement
now urged upon us.
There are good and sufficient reasons for this prudential
limitation on standing when rights of third parties are implicated
-- the avoidance of the adjudication of rights which those not
before the Court may not wish to assert, and the assurance that the
most effective advocate of the rights at issue is present to
champion them.
See Singleton v. Wulff, 428 U.
S. 106,
428 U. S.
113-114 (1976). We do not, however, find these reasons a
satisfactory predicate for applying this limitation or a similar
nexus requirement to all cases as a matter of course. Where a party
champions his own rights, and where the injury alleged is a
concrete and particularized one which will be
Page 438 U. S. 81
prevented or redressed by the relief requested, the basic
practical and prudential concerns underlying the standing doctrine
are generally satisfied when the constitutional requisites are met.
See, e.g., Arlington Heights v. Metropolitan Housing Dev.
Corp., 429 U. S. 252
(1977).
We conclude that appellees have standing to challenge the
constitutionality of the Price-Anderson Act. [
Footnote 26]
C
The question of the ripeness of the constitutional challenges
raised by appellees need not long detain us. To the extent that
"issues of ripeness involve, at least in part, the existence of a
live
Case or Controversy,'" Regional Rail Reorganization
Act Cases, 419 U.S. at 419 U. S. 138,
our conclusion that appellees will sustain immediate injury from
the operation of the disputed power plants and that such injury
would be redressed by the relief requested would appear to satisfy
this requirement.
The prudential considerations embodied in the ripeness doctrine
also argue strongly for a prompt resolution of the claims
presented. Although it is true that no nuclear accident has yet
occurred, and that such an occurrence would eliminate much of the
existing scientific uncertainty surrounding this
Page 438 U. S. 82
subject, it would not, in our view, significantly advance our
ability to deal with the legal issues presented, nor aid us in
their resolution. However, delayed resolution of these issues would
foreclose any relief from the present injury suffered by appellees
-- relief that would be forthcoming if they were to prevail in
their various challenges to the Act. Similarly, delayed resolution
would frustrate one of the key purposes of the Price-Anderson Act
-- the elimination of doubts concerning the scope of private
liability in the event of major nuclear accident. In short, all
parties would be adversely affected by a decision to defer
definitive resolution of the constitutional validity
vel
non of the Price-Anderson Act. Since we are persuaded that "we
will be in no better position later than we are now" to decide this
question,
Id. at
419 U. S.
143-145, we hold that it is presently ripe for
adjudication.
IV
The District Court held that the Price-Anderson Act contravened
the Due Process Clause because "[t]he amount of recovery is not
rationally related to the potential losses"; because "[t]he Act
tends to encourage irresponsibility in matters of safety and
environmental protection . . ."; and, finally, because "[t]here is
no
quid pro quo" for the liability limitations. 431 F.
Supp. at 222-223. An equal protection violation was also found
because the Act "places the cost of [nuclear power] on an
arbitrarily chosen segment of society, those injured by nuclear
catastrophe."
Id. at 225. Application of the relevant
constitutional principles forces the conclusion that these holdings
of the District Court cannot be sustained.
A
Our due process analysis properly begins with a discussion of
the appropriate standard of review. Appellants, portraying the
liability limitation provision as a legislative balancing of
economic interests, urge that the Price-Anderson Act be
Page 438 U. S. 83
accorded the traditional presumption of constitutionality
generally accorded economic regulations, and that it be upheld
absent proof of arbitrariness or irrationality on the part of
Congress.
See Ferguson v. Skrupa, 372 U.
S. 726,
372 U. S.
731-732 (1963);
Usery v. Turner Elkhorn Mining
Co., 428 U. S. 1,
428 U. S. 15
(1976). Appellees, however, urge a more elevated standard of review
on the ground that the interests jeopardized by the Price-Anderson
Act "are far more important than those in the economic due process
and business-oriented cases," where the traditional rationality
standard has been invoked. Brief for Appellees 36. An intermediate
standard like that applied in cases such as
Craig v.
Boren, 429 U. S. 190
(1976) (equal protection challenge to statute requiring that males
be older than females in order to purchase beer) or
United
States Trust Co. of New York v. New Jersey, 431 U. S.
1 (1977) (Contract Clause challenge to repeal of
statutory covenant providing security for bondholders) is thus
recommended for our use here.
As we read the Act and its legislative history, it is clear that
Congress' purpose was to remove the economic impediments in order
to stimulate the private development of electric energy by nuclear
power, while simultaneously providing the public compensation in
the event of a catastrophic nuclear incident.
See, e.g.,
S.Rep. No. ,6, 85th Cong., 1st Sess., 15 (1957). The liability
limitation provision thus emerges as a classic example of an
economic regulation -- a legislative effort to structure and
accommodate "the burdens and benefits of economic life."
Usery
v. Turner Elkhorn Mining Co., supra at
428 U. S. 15.
"It is by now well established that [such] legislative Acts . .
. come to the Court with a presumption of constitutionality, and
that the burden is on one complaining of a due process violation to
establish that the legislature has acted in an arbitrary and
irrational way."
Ibid. That the accommodation struck may have profound
and far-reaching consequences, contrary to appellees' suggestion,
provides all the
Page 438 U. S. 84
more reason for this Court to defer to the congressional
judgment unless it is demonstrably arbitrary or irrational.
[
Footnote 27]
B
When examined in light of this standard of review, the
Price-Anderson Act, in our view, passes constitutional muster. The
record before us fully supports the need for the imposition of a
statutory limit on liability to encourage private industry
participation, and hence bears a rational relationship to Congress'
concern for stimulating the involvement of private enterprise in
the production of electric energy through the use of atomic power;
nor do we understand appellees or the District Court to be of a
different view. Rather, their challenge is to the alleged
arbitrariness of the particular figure of $560 million, which is
the statutory ceiling on liability. The District Court aptly
summarized its position:
"The amount of recovery is not rationally related to the
potential losses. Abundant evidence in the record shows that,
although major catastrophe in any particular place is not certain,
and may not be extremely likely, nevertheless, in the territory
where these plants are located, damage to life and property for
this and future generations could well be many, many times the
limit which the law places on liability."
431 F. Supp. at 222.
Assuming,
arguendo, that the $560 million fund would
not insure full recovery in all conceivable circumstances [
Footnote 28] -- and
Page 438 U. S. 85
the hard truth is that no one can ever know -- it does not by
any means follow that the liability limitation is therefore
irrational and violative of due process. The legislative history
clearly indicates that the $560 million figure was not arrived at
on the supposition that it alone would necessarily be sufficient to
guarantee full compensation in the event of a nuclear incident.
Instead, it was conceived of as a "starting point," or a working
hypothesis. [
Footnote 29]
The reasonableness of the statute's assumed ceiling on liability
was predicated on two corollary considerations -- expert appraisals
of the exceedingly small risk of a nuclear incident involving
claims in excess of $560 million and the recognition that, in the
event of such an incident, Congress would likely enact
extraordinary relief provisions to provide additional relief, in
accord with prior practice.
"[T]his limitation does not, as a practical matter, detract from
the public protection afforded by this legislation. In the first
place, the likelihood of an accident occurring
Page 438 U. S. 86
which would result in claims exceeding the sum of the financial
protection required and the governmental indemnity is exceedingly
remote, albeit theoretically possible. Perhaps more important, in
the event of a national disaster of this magnitude, it is obvious
that Congress would have to review the problem and take appropriate
action. The history of other natural or man-made disasters, such as
the Texas City incident, bears this out. The limitation of
liability serves primarily as a device for facilitating further
congressional review of such a situation, rather than as an
ultimate bar to further relief of the public."
H.R.Rep. No. 883, 89th Cong., 1st Sess., 7 (1965).
See
also S.Rep. No. 296,
supra at 21; H.R.Rep. No.
94-648, pp. 12, 15 (1975).
Given our conclusion that, in general, limiting liability is an
acceptable method for Congress to utilize in encouraging the
private development of electric energy by atomic power, candor
requires acknowledgment that whatever ceiling figure is selected
will, of necessity, be arbitrary in the sense that any choice of a
figure based on imponderables like those at issue here can always
be so characterized. This is not, however, the kind of
arbitrariness which flaws otherwise constitutional action. When
appraised in terms of both the extremely remote possibility of an
accident where liability would exceed the limitation [
Footnote 30] and Congress' now
statutory commitment to "take whatever action is deemed necessary
and appropriate to protect the public from the consequences of" any
such disaster, 42 U.S.C. § 2210(e) (1970 ed., Supp. V), [
Footnote 31] we hold the
Page 438 U. S. 87
congressional decision to fix a $560 million ceiling, at this
stage in the private development and production of electric energy
by nuclear power, to be within permissible limits, and not
violative of due process.
This District Court's further conclusion that the Price-Anderson
Act "tends to encourage irresponsibility . . . on the part of
builders and owners" of the nuclear power plants, 431 F. Supp. at
222, simply cannot withstand careful scrutiny. We recently outlined
the multitude of detailed steps involved in the review of any
application for a license to construct or to operate a nuclear
power plant,
Vermont Yankee Nuclear Power Corp. v. NRDC,
435 U. S. 519,
435 U. S.
526-527, and n. 5 (1978); nothing in the liability
limitation provision undermines or alters in any respect the rigor
and integrity of that process. Moreover, in the event of a nuclear
accident, the utility itself would suffer perhaps the largest
damages. While obviously not to be compared with the loss of human
life and injury to health, the risk of financial loss and possible
bankruptcy to the utility is, in itself, no small incentive to
avoid the kind of irresponsible and cavalier conduct implicitly
attributed to licensees by the District Court.
The remaining due process objection to the liability limitation
provision is that it fails to provide those injured by a
Page 438 U. S. 88
nuclear accident with a satisfactory
quid pro quo for
the common law rights of recovery which the Act abrogates.
Initially, it is not at all clear that the Due Process Clause, in
fact, requires that a legislatively enacted compensation scheme
either duplicate the recovery at common law or provide a reasonable
substitute remedy. [
Footnote
32] However, we need not resolve this question here, since the
Price-Anderson Act does, in our view, provide a reasonably just
substitute for the common law or state tort law remedies it
replaces.
Cf. New York Central R. Co. v. White,
243 U. S. 188
(1917);
Crowell v. Benson, 285 U. S.
22 (1932). [
Footnote
33]
Page 438 U. S. 89
The legislative history of the liability limitation provisions
and the accompanying compensation mechanism reflects Congress'
determination that reliance on state tort law remedies and state
court procedures was an unsatisfactory approach to assuring public
compensation for nuclear accidents, while at the same time
providing the necessary incentives for private development of
nuclear-produced energy. The remarks of Chairman Anders of the NRC
before the Joint Committee on Atomic Energy during the 1975
hearings on the need for renewal of the Price-Anderson Act are
illustrative of this concern, and of the expectation that the Act
would provide a more efficient and certain vehicle for assuring
compensation in the unlikely event of a nuclear incident:
"The primary defect of this alternative [nonrenewal of the Act],
however, is its failure to afford the public either a secure source
of funds or a firm basis for legal liability with respect to new
plants. While, in theory, no legal limit would be placed on
liability, as a practical matter, the public would be less assured
of obtaining compensation than under Price-Anderson. Establishing
liability would depend in each case on state tort law and
procedures, and these might or might not provide for no-fault
liability, let alone the multiple other protections now embodied in
Price-Anderson. The present assurance of prompt and equitable
compensation under a pre-structured and nationally applicable
protective system would give way to uncertainties, variations and
potentially lengthy delays in recovery. It should be emphasized,
moreover, that it is collecting a judgment, not filing a
Page 438 U. S. 90
lawsuit, that counts. Even if defenses are waived under state
law, a defendant with theoretically 'unlimited' liability may be
unable to pay a judgment once obtained. When the defendant's assets
are exhausted by earlier judgments, subsequent claimants would be
left with uncollectible awards. The prospect of inequitable
distribution would produce a race to the courthouse door, in
contrast to the present system of assured orderly and equitable
compensation."
Hearings on H.R. 8631 before Joint Committee on Atomic Energy,
94th Cong., 1st Sess., 69 (1975)
Appellees, like the District Court, differ with this appraisal
on several grounds. They argue,
inter alia, that recovery
under the Act would not be greater than without it, that the waiver
of defenses required by the Act, 42 U.S.C. § 2210(n) (1970 ed.,
Supp. V), is an idle gesture, since those involved in the
development of nuclear energy would likely be held strictly liable
under common law principles; [
Footnote 34] that the claim administration procedure
under the Act delays, rather than expedites, individual recovery;
and, finally, that recovery of even limited compensation is
uncertain, since the liability ceiling does not vary with the
number of persons injured or amount of property damaged. The
extension of short state statutes of limitations and the provision
of omnibus [
Footnote 35]
coverage do not save the Act, in their view, since such provisions
could equally well be included in a fairer plan which would assure
greater compensation.
We disagree. We view the congressional assurance of a $560
million fund for recovery, accompanied by an express statutory
commitment, to "take whatever action is deemed necessary
Page 438 U. S. 91
and appropriate to protect the public from the consequences of"
a nuclear accident, 42 U.S.C. § 210(e) (1970 ed., Supp. V), to be a
fair and reasonable substitute for the uncertain recovery of
damages of this magnitude from a utility or component manufacturer,
whose resources might well be exhausted at an early stage. The
record in this case raises serious questions about the ability of a
utility or component manufacturer to satisfy a judgment approaching
$560 million -- the amount guaranteed under the Price-Anderson Act.
[
Footnote 36] Nor are we
persuaded that the mandatory waiver of defenses required by the Act
is of no benefit to potential claimants. Since there has never
been, to our knowledge, a case arising out of a nuclear incident
like those covered by the Price-Anderson Act, any discussion of the
standard of liability that state courts will apply is necessarily
speculative. At the minimum, the statutorily mandated waiver of
defenses establishes at the threshold the right of injured parties
to compensation without proof of fault, and eliminates the burden
of delay and uncertainty which would follow from the need to
litigate the question of liability after an accident. Further, even
if strict liability were routinely applied, the common law doctrine
is subject to exceptions for acts of God or of third parties
[
Footnote 37] -- two of the
very factors which appellees emphasized in the District Court
in
Page 438 U. S. 92
the course of arguing that the risks of a nuclear accident are
greater than generally admitted. All of these considerations belie
the suggestion that the Act leaves the potential victims of a
nuclear disaster in a more disadvantageous position than they would
be in if left to their common law remedies -- not known in modern
times for either their speed or economy.
Appellees' remaining objections can be briefly treated. The
claim administration procedures under the Act provide that, in the
event of an accident with potential liability exceeding the $560
million ceiling, no more than 15% of the limit can be distributed
pending court approval of a plan of distribution taking into
account the need to assure compensation for "possible latent injury
claims which may not be discovered until a later time." 42 U.S.C. §
2210(
o)(3) (1970 ed., Supp. V). Although some delay might
follow from compliance with this statutory procedure, we doubt that
it would approach that resulting from routine litigation of the
large number of claims caused by a catastrophic accident. [
Footnote 38] Moreover, the statutory
scheme insures the equitable distribution of benefits to all who
suffer injury -- both immediate and latent; under the common law
route, the proverbial race to the courthouse would, instead,
determine who had "first crack" at the diminishing resources of the
tortfeasor, and fairness could well be sacrificed in the process.
The remaining contention that recovery is uncertain because of the
aggregate, rather than individualized, nature of the liability
ceiling is but a thinly disguised version of the contention that
the $560 million figure is inadequate, which we have already
rejected.
In the course of adjudicating a similar challenge to the
Page 438 U. S. 93
Workmen's Compensation Act in
New York Central R. Co. v.
White, 243 U.S. at
243 U. S. 201,
the Court observed that the Due Process Clause of the Fourteenth
Amendment was not violated simply because an injured party would
not be able to recover as much under the Act as before its
enactment.
"[H]e is entitled to moderate compensation in all cases of
injury, and has a certain and speedy remedy without the difficulty
and expense of establishing negligence or proving the amount of the
damages."
The logic of
New York Central would seem to apply with
renewed force in the context of this challenge to the
Price-Anderson Act. The Price-Anderson Act not only provides a
reasonable, prompt, and equitable mechanism for compensating
victims of a catastrophic nuclear incident, it also guarantees a
level of net compensation generally exceeding that recoverable in
private litigation. Moreover, the Act contains an explicit
congressional commitment to take further action to aid victims of a
nuclear accident in the event that the $560 million ceiling on
liability is exceeded. This panoply of remedies and guarantees is,
at the least, a reasonably just substitute for the common law
rights replaced by the Price-Anderson Act. Nothing more is required
by the Due Process Clause.
Although the District Court also found the Price-Anderson Act to
contravene the "equal protection provision that is included within
the Due Process Clause of the Fifth Amendment," 431 F. Supp. at
224-225, appellees have not relied on this ground, since the equal
protection arguments largely track and duplicate those made in
support of the due process claim. In any event, we conclude that
there is no equal protection violation. The general rationality of
the Price-Anderson Act liability limitations -- particularly with
reference to the important congressional purpose of encouraging
private participation in the exploitation of nuclear energy -- is
ample justification for the difference in treatment between those
injured in nuclear accidents and those whose injuries are derived
from other
Page 438 U. S. 94
causes. Speculation regarding other arrangements that might be
used to spread the risk of liability in ways different from the
Price-Anderson Act is, of course, not pertinent to the equal
protection analysis.
See Mourning v. Family Publications
Service, Inc., 411 U. S. 356,
411 U. S. 378
(1973). [
Footnote 39]
Accordingly, the decision of the District Court is reversed, and
the cases are remanded for proceedings consistent with this
opinion.
Reversed and remanded.
* Together with No. 77-375,
United States Nuclear Regulatory
Commission et al. v. Carolina Environmental Study Group, Inc., et
al., also on appeal from the same court.
[
Footnote 1]
Under the terms of the Energy Reorganization Act of 1974, 42
U.S.C. § 5801
et seq. (1970 ed., Supp. V), the Nuclear
Regulatory Commission (NRC) has now replaced the AEC as the
licensing and regulatory authority.
[
Footnote 2]
A "nuclear incident" is defined as
"any occurrence . . . within the United States causing, within
or outside the United States, bodily injury, sickness, disease, or
death, or loss of or damage to property, or loss of use of
property, arising out of or resulting from the radioactive, toxic,
explosive, or other hazardous properties of source, special
nuclear, or byproduct material. . . ."
42 U.S. . § 2014(q).
[
Footnote 3]
"The term 'person indemnified' means (1) with respect to a
nuclear incident occurring within the United States . . . the
person with whom an indemnity agreement is executed and any other
person who may be liable for public liability. . . ."
42 U.S.C. § 2014(t).
[
Footnote 4]
By the terms of the Act as originally passed, it was only
applicable to licenses issued between August 30, 1954, and August
1, 1967. § 4, 71 Stat. 576, as amended, 42 U.S.C. § 2210(c).
[
Footnote 5]
The waiver provision is incorporated in the indemnity agreement.
The defenses of negligence, contributory negligence, charitable or
governmental immunity, and assumption of risk all are waived in the
event of an extraordinary nuclear occurrence, as are, to a limited
degree, defenses based on certain short state statutes of
limitations. 80 Stat. 891, 42 U.S.C. § 2210(n)(1).
See
also 10 CFR §§ 140.81 to 140.85, 140.91 to 140.92 (1977).
[
Footnote 6]
The Act was also amended in 1966 to provide for the transfer of
all claims arising out of a nuclear incident to a single federal
district court. 42 U.S.C. § 2210(n)(2). If the court finds that
liability may exceed the liability limitation of the Act, immediate
payments to injured parties are limited to 15% of the liability
limitation until the court approves a plan of distribution to
insure equitable treatment of all parties. § 2210(
o) (1970
ed. and Supp. V).
[
Footnote 7]
The NRC, which was empowered by the 1975 amendments to choose a
figure in the $2-$5 million range, has set the assessment at $5
million. 42 Fed.Reg. 46 (1977).
[
Footnote 8]
As the number of reactors increases, the $5 million deferred
premium, in itself, will yield a fund exceeding the present
liability ceiling. For example, it is predicted that, by 1985,
there will be a maximum of 138 reactors operating,
see
Executive Office of the President, The National Energy Plan 71
(1977), which would produce $690 million in addition to whatever
insurance is available from the private insurance market. Under the
Act, the liability ceiling automatically increases to a level equal
to the amount of primary and secondary (deferred premium) insurance
coverage when the amount of such coverage exceeds the $560 million
figure. 42 U.S.C. § 2210(e) (1970 ed., Supp. V).
[
Footnote 9]
Appellees' expert witness on insurance testified in the District
Court that homeowners were unable to purchase insurance against
nuclear catastrophes because
"the nuclear industry has essentially absorbed the entire
capacity of the private insurance markets in their need for
property and liability insurance."
App. 293-294.
[
Footnote 10]
The complaint also sought review of the AEC's decision to grant
a construction permit for one of the plants. During the pendency of
this action, however, the United States Court of Appeals for the
District of Columbia Circuit decided that the AEC had properly
issued the permits.
Carolina Environmental Study Group v.
United States, 166 U.S.App.D.C. 416, 510 F.2d 796 (1975).
Accordingly, the District Court dismissed all counts of the
complaint except those relating to the Price-Anderson Act's
constitutionality.
[
Footnote 11]
Our jurisdiction was invoked under 28 U.S.C. § 1252 (1976 ed.),
which provides for a direct appeal to this Court from any decision
invalidating an Act of Congress in any suit to which the United
States, its agencies, officers, or employees are parties.
[
Footnote 12]
The complaint provides in relevant part:
"19. Since the Price-Anderson Act provides victims of a nuclear
disaster no benefit, while at the same time limiting their right to
recover for their losses to approximately 2 1/2% of such losses,
the operation of the $500 million limitation would, in the event of
a nuclear disaster, deprive the persons injured by such a disaster
of property rights without due process of law in violation of the
Fifth Amendment to the Constitution of the United States."
App. 32.
[
Footnote 13]
MR JUSTICE REHNQUIST would read the complaint, insofar as it
alleges a denial of due process, as stating a claim only against
Duke Power under North Carolina law. Under such a construction of
the complaint, the question of the constitutionality of the
Price-Anderson Act would emerge only in anticipation of a defense
to appellees' state law claims, and thus would not support federal
jurisdiction under the "well pleaded" complaint rule regardless of
the jurisdictional statute relied upon.
See Louisville &
Nashville R. Co. v. Mottley, 211 U. S. 149
(1908). We conclude that the complaint is more fairly read as
stating a claim against the NRC directly under the Due Process
Clause of the Fifth Amendment.
See n 12,
supra. On this view, the "well
pleaded" complaint rule poses no bar to the assertion of
jurisdiction. Appellees' claim under the Due Process Clause is an
essential ingredient of a well pleaded complaint asserting a right
under the Constitution, and is not simply a claim made in
anticipation of a defense to be raised in an action having its
origin in state law.
See also n 26,
infra.
[
Footnote 14]
Previously, § 1331(a) required a minimum amount in controversy
in all suits, but a 1976 amendment eliminated the jurisdictional
amount requirement in actions "brought against the United States,
any agency thereof, or any officer or employee thereof in his
official capacity." Pub.L. 94-574 § 2, 90 Stat. 2721. Thus, this
action, at least as against the NRC, would seem clearly permitted
by § 1331(a) without specification of an amount in controversy.
See Andrus v. Charlestone Stone Products Co., 436 U.
S. 604,
436 U. S. 608
n. 6 (1978). Appellees' failure to assert § 1331(a) as a basis for
jurisdiction in their complaint is not fatal, since the facts
alleged are sufficient to support such jurisdiction.
See
436 U.S. at
436 U. S. 608
n. 6.
[
Footnote 15]
MR. JUSTICE REHNQUIST suggests that appellees' "taking" claim
will not support jurisdiction under § 1331(a), but instead that
such a claim can be adjudicated only in the Court of Claims under
the Tucker Act, 28 U.S.C. § 1491 (1976 ed.). We disagree. Appellees
are not seeking compensation for a taking, a claim properly brought
in the Court of Claims, but are now requesting a declaratory
judgment that, since the Price-Anderson Act does not provide
advance assurance of adequate compensation in the event of a
taking, it is unconstitutional. As such, appellees' claim tracks
quite closely that of the petitioners in the
Regional Rail
Reorganization Act Cases, 419 U. S. 102
(1974), which were brought under § 1331 as well as the Declaratory
Judgment Act.
See App. in
Regional Rail Reorganization
Act Cases, O.T. 1974, Nos. 74-165, 74-166, 74-167, 74-168, p.
161. While the Declaratory Judgment Act does not expand our
jurisdiction, it expands the scope of available remedies. Here, it
allows individuals threatened with a taking to seek a declaration
of the constitutionality of the disputed governmental action before
potentially uncompensable damages are sustained.
[
Footnote 16]
We need not resolve the question of whether Duke Power is a
proper party, since jurisdiction over appellees' claims against the
NRC is established, and Duke's presence or absence makes no
material difference to either our consideration of the merits of
the controversy or our authority to award the requested relief.
[
Footnote 17]
For a detailed explanation of the nature and consequences of a
core melt,
see 431 F. Supp. at 206-207.
[
Footnote 18]
"We do not question that this type of harm may amount to an
'injury in fact' sufficient to lay the basis for standing. . . .
Aesthetic and environmental wellbeing, like economic wellbeing, are
important ingredients of the quality of life in our society. . .
."
Sierra Club v. Morton, 405 U.S. at
405 U. S.
734.
[
Footnote 19]
It is argued that the District Court's findings on the question
of injury in fact upon which we rely are clearly erroneous, and
should not be accepted as a predicate for standing.
"A finding is 'clearly erroneous' when, although there is
evidence to support it, the reviewing court, on the entire
evidence, is left with the definite and firm conviction that a
mistake has been committed."
United States v. United States Gypsum Co., 333 U.
S. 364,
333 U. S. 395
(1948). Application of this standard to the factual findings of the
District Court does not persuade us that they should not be
accepted.
[
Footnote 20]
Our recent cases have required no more than a showing that there
is a "substantial likelihood" that the relief requested will
redress the injury claimed to satisfy the second prong of the
constitutional standing requirement.
See Arlington Heights v.
Metropolitan Housing Dev. Corp., 429 U.
S. 252,
429 U. S. 262
(1977), quoting
Simon v. Eastern Ky. Welfare Rights Org.,
426 U. S. 26,
426 U. S. 38
(1976) ("MHDC has shown an injury to itself that is
likely to
be redressed by a favorable decision'"). See also Warth v.
Seldin, 422 U. S. 490,
422 U. S. 504,
422 U. S.
506-507 (1975).
[
Footnote 21]
Nor was the situation different in 1965-1966, when the first
10-year renewal of Price-Anderson was considered.
See
H.R.Rep. No. 883, 89th Cong., 1st Sess., 9 (1965).
See
generally Green 493.
[
Footnote 22]
"From what I know about nuclear power, it would be my
recommendation that Duke proceed even in the absence of
Price-Anderson. However, from the point of view of how others
perceive nuclear power, there is some question about whether it
would be a practical undertaking in the absence of the Act. . . . I
have already been advised by several firms that the existence of
Price-Anderson is required for them to be a supplier to our nuclear
program. . . . If Price-Anderson did not exist, I would therefore
have to evaluate the extent to which its absence caused
disappearance of suppliers from the marketplace in arriving at my
recommendation."
App. 3636.
[
Footnote 23]
The only injury that would possess the required subject matter
nexus to the due process challenge is the injury that would result
from a nuclear accident causing damages in excess of the liability
limitation provisions of the Price-Anderson Act.
[
Footnote 24]
In
Linda R.S. v. Richard D., 410 U.
S. 614 (1973), a nontaxpayer suit, reference was made to
Flast's nexus requirement in the course of denying
appellant's standing to challenge the nonenforcement of Texas'
desertion and nonsupport statute. Upon careful reading, however, it
is clear that standing was denied not because of the absence of a
subject matter nexus between the injury asserted and the
constitutional claim, but instead because of the unlikelihood that
the relief requested would redress appellant's claimed injury.
Id. at
410 U. S. 618.
This case thus provides no qualitative support for the broader
application of
Flast's principles which appellants appear
to advocate.
Cf. Scott, Standing in the Supreme Court -- A
Functional Analysis, 86 Harv.L.Rev. 645, 660-662 (1973).
[
Footnote 25]
Both at the time of its formulation,
see Flast v.
Cohen, 392 U.S. at
392 U. S. 120,
392 U. S.
130-131 (Harlan J., dissenting), and more recently,
see United States v. Richardson, 418 U.
S. 166,
418 U. S. 181,
418 U. S. 196
n. 18 (1974) (POWELL, J., concurring), there have been questions as
to whether the nexus requirement, even in the context of taxpayers'
suits, is constitutionally mandated, or is instead simply a
prudential limitation.
[
Footnote 26]
MR. JUSTICE REHNQUIST undertakes to sever the action of the NRC
in executing indemnity agreements under the Act from the Act's
alleged constitutional infirmities -- particularly the liability
limitation provisions. Careful examination of the statutory
mechanism indicates that such a separation simply cannot be
sustained. The execution of the indemnification agreements by the
NRC triggers the statutory ceiling on liability, which, in terms,
applies only to "persons indemnified."
See 42 U.S.C. §
2210(e) (1970 ed., Supp. V). Thus, absent the execution of such
agreements between the NRC and the licensees, the liability
limitation provisions of the Act, to which appellees object, would
simply not come into play. This fact, coupled with the District
Court's finding that "but for" the liability limitation provisions,
there is a substantial likelihood that the contemplated plants
would not be built or operated, is sufficient to establish the
justiciability of appellees' claim against the Commission.
See
Simon v. Eastern Ky. Welfare Rights Org., 426 U.S. at
426 U. S.
44-46.
[
Footnote 27]
Appellees, in apparent reliance on our recent decision in
National League of Cities v. Usery, 426 U.
S. 833 (1976), argue that, because the Price-Anderson
Act encroaches on substantial state government interests, an
augmented standard of review under the Due Process Clause is
warranted. Nothing in
National League of Cities or in our
prior due process cases provides any support for this claim.
[
Footnote 28]
As the various studies considered by the District Court
indicate, there is considerable uncertainty as to the amount of
damages which would result from a catastrophic nuclear accident.
See 431 F. Supp. at 210-214. The Reactor Safety Study
published by the NRC in 1975 suggested that there was a 1 in 20,000
chance (per reactor year) of an accident causing property damage
approaching $100 million and having only minor health effects. By
contrast, when the odds were reduced to the range of 1 in 1 billion
(per reactor year), the level of damages approached $14 billion;
and 3,300 early fatalities and 45,000 early illnesses were
predicted. NRC, Reactor Safety Study, An Assessment of Accident
Risks in U.S. Commercial Nuclear Power Plants 83-85 (Wash-1400,
Oct.1975). For a thorough criticism of the Reactor Safety Study,
see EPA, Reactor Safety Study (Wash-1400): A Review of the
Final Report (June, 1976).
[
Footnote 29]
"What we were thinking about was the magnitude of protection,
and we set an arbitrary figure, because it seemed to be practical
at that time and because we didn't think an accident would happen .
. . , but yet we recognize that it could happen.
We wanted to
have a base to work from."
Hearings before the Joint Committee on Atomic Energy on Possible
Modification or Extension of the Price-Anderson Insurance And
Indemnity Act of 1957 In Order for Proper Planning of Nuclear Power
Plants to Continue Without Delay, 93d Cong.2d Sess., 68 (1974)
(remarks of Rep. Holifield) (emphasis added).
[
Footnote 30]
Congress' conclusion that "the probabilities of a nuclear
incident are much lower, and the likely consequences much less
severe, than has been thought previously" was a key factor in the
decision not to increase the $560 million liability ceiling in
1975. S.Rep. No. 94-454, p. 12 (1975).
[
Footnote 31]
In the past Congress has provided emergency assistance for
victims of catastrophic accidents even in the absence of a prior
statutory commitment to do so. For example, in 1955, Congress
passed the Texas City Explosion Relief Act, 69 Stat. 707, to
provide relief for victims of the explosion of ammonium nitrate
fertilizer in 1947. Congress took this action despite the decision
in
Dalehite v. United States, 346 U. S.
15 (1953), holding the United States free from any
liability under the Federal Tort Claims Act for the damages
incurred and injuries suffered. More recently, Congress enacted
legislation to provide relief for victims of the flood resulting
from the collapse of the Teton Dam in Idaho. Pub.L. 94-400, 90
Stat. 1211. Under the Act, the Secretary of the Interior was
authorized to provide full compensation for any deaths, personal
injuries, or property damage caused by the failure of the dam.
Ibid.
The Price-Anderson Act is, of course, a significant improvement
on these prior relief efforts, because it provides an advance
guarantee of recovery up to $560 million plus an express commitment
by Congress to take whatever further steps are necessary to aid the
victims of a nuclear incident.
[
Footnote 32]
Our cases have clearly established that "[a] person has no
property, no vested interest, in any rule of the common law."
Second Employers' Liability Cases, 223 U. S.
1,
223 U. S. 50
(1912), quoting
Munn v. Illinois, 94 U. S.
113,
94 U. S. 134
(1877). The
"Constitution does not forbid the creation of new rights, or the
abolition of old ones recognized by the common law, to attain a
permissible legislative object,"
Silver v. Silver, 280 U. S. 117,
280 U. S. 122
(1929), despite the fact that "otherwise settled expectations" may
be upset thereby.
Usery v. Turner Elkhorn Mining Co.,
428 U. S. 1,
428 U. S. 16
(1976).
See also Arizona Employers' Liability Cases,
250 U. S. 400,
250 U. S.
419-422 (1919). Indeed, statutes limiting liability are
relatively commonplace, and have consistently been enforced by the
courts.
See, e.g., Silver v. Silver, supra, (automobile
guest statute);
Providence & New York S.S. Co. v. Hill Mfg.
Co., 109 U. S. 578
(1883) (limitation of vessel owner's liability);
Indemnity Ins.
Co. of North America v. Pan American Airways, 58 F. Supp.
338 (SDNY 1944) (Warsaw Convention limitation on recovery for
injuries suffered during international air travel).
Cf.
Thomason v. Sanchez, 539 F.2d 955 (CA3 1976) (Federal Driver's
Act).
[
Footnote 33]
We reject at the outset appellees' contention that the
Price-Anderson Act differs from other statutes limiting liability
because the Act itself is the "but for" cause of the tort for which
liability is limited. Put otherwise, the argument is that no
quid pro quo can be provided by the Act, since, without
it, there would be no nuclear power plants, and no possibility of
accidents or injuries. As we understand the argument, it proceeds
from the premise that, prior to the enactment of the Price-Anderson
Act, appellees had some right, cognizable under the Due Process
Clause, to be free of nuclear power or to take advantage of the
state of uncertainty which inhibited the private development of
nuclear power. This premise we cannot accept. Appellees' only
relevant right prior to the enactment of the Price-Anderson Act was
to utilize their existing common law and state law remedies to
vindicate any particular harm visited on them from whatever
sources. After the Act was passed, that right, at least with regard
to nuclear accidents, was replaced by the compensation mechanism of
the statute, and it is only the terms of that substitution which
are pertinent to the
quid pro quo inquiry which appellees
insist the Due Process Clause requires.
[
Footnote 34]
See Rylands v. Fletcher, L.R. 3 E. & I. App. 330
(H.L. 1868).
See generally W. Prosser, Law of Torts § 79,
p. 516 (4th ed. 1871); Cavers, Improving Financial Protection of
the Public Against the Hazards of Nuclear Power, 77 Harv.L.Rev.
644, 649 (1964).
[
Footnote 35]
See n 3,
supra.
[
Footnote 36]
The expert testimony before the District Court indicated that
Duke Power, one of the largest utilities in the country, could not
be expected to accumulate more than $200 million for damages claims
without reaching the point of insolvency. App. 393-397. This
amount, even when coupled with the amount of available private
insurance, would be less than the $560 million provided by the Act.
Moreover, if the liability were of sufficient magnitude to force
the utility or component manufacturer into bankruptcy or
reorganization, recovery would likely be further reduced and
delayed.
See Joint Committee on Atomic Energy, Issues of
Financial Protection in Nuclear Activities in Selected Materials on
Atomic Energy Indemnity and Insurance Legislation, 93d Cong., 2d
Sess., 110 (Comm.Print 1974).
[
Footnote 37]
See Prosser,
supra, n 34, at 520-521.
[
Footnote 38]
The Act explicitly provides for "payments to, or for the aid of,
claimants for the purpose of providing immediate assistance
following a nuclear incident." 42 U.S.C. § 2210(m). Unlike the
normal tort recovery situation, these emergency payments are made
prior to the determination of injury and the setting of damages,
and are not conditioned on the execution of any release by the
victim.
Ibid.
[
Footnote 39]
Appellees also contend that the Price-Anderson Act effects an
unconstitutional "taking," because, in the event of a catastrophic
nuclear accident, their property would be destroyed without any
assurance of just compensation. We find it unnecessary to resolve
the claim that such an accident would constitute a "taking" as that
term has been construed in our precedents, since on our reading the
Price-Anderson Act does not withdraw the existing Tucker Act
remedy, 28 U.S.C. § 1491 (1976 ed.).
See Regional Rail
Reorganization Act Cases, 419 U.S. at
419 U. S.
125-136. Appellees concede that, if the Tucker Act
remedy would be available in the event of a nuclear disaster, then
their constitutional challenge to the Price-Anderson Act under the
Just Compensation Clause must fail. Brief for Appellees 71 n. 56.
The further question of whether a taking claim could be established
under the Fifth Amendment is a matter appropriately left for
another day.
MR. JUSTICE STEWART, concurring in the result.
With some difficulty I can accept the proposition that federal
subject matter jurisdiction under 28 U.S.C. § 1331 (1976 ed.)
exists here, at least with respect to the suit against the Nuclear
Regulatory Commission, the agency responsible for the
administration of the Price-Anderson Act. The claim under federal
law is to be found in the allegation that the Act, if enforced,
will deprive the appellees of certain property rights, in violation
of the Due Process Clause of the Fifth Amendment. One of those
property rights, and perhaps the sole cognizable one, is a
state-created right to recover full compensation for tort injuries.
The Act impinges on that right by limiting recovery in major
accidents.
Page 438 U. S. 95
But there never has been such an accident, and it is sheer
speculation that one will ever occur. For this reason, I think
there is no present justiciable controversy, and that the appellees
were without standing to initiate this litigation
On the issue of standing, the Court relies on the "present"
injuries of increased water temperatures and low-level radiation
emissions. Even assuming that, but for the Act, the plant would not
exist, and therefore neither would its effects on the environment,
I cannot believe that it follows that the appellees have standing
to attack the constitutionality of the Act. Apart from a "but for"
connection in the loosest sense of that concept, there is no
relationship at all between the injury alleged for standing
purposes and the injury alleged for federal subject matter
jurisdiction.
Surely a plaintiff does not have standing simply because his
challenge, if successful, will remove the injury relied on for
standing purposes only because it will put the defendant out of
existence. Surely there must be some direct relationship between
the plaintiff's federal claim and the injury relied on for
standing.
Cf. Arlington Heights v. Metropolitan Housing Dev.
Corp., 429 U. S. 252,
429 U. S. 261;
United States v. SCRAP, 412 U. S. 669,
412 U. S.
687-690;
Linda R.S. v. Richard D., 410 U.
S. 614,
410 U. S.
617-618. An interest in the local water temperature does
not, in short, give these appellees standing to bring a suit under
28 U.S.C. § 1331 (1976 ed.) to challenge the constitutionality of a
law limiting liability in an unrelated and as-yet-to-occur major
nuclear accident.
For these reasons, I would remand these cases to the District
Court with instructions to dismiss the complaint.
MR JUSTICE REHNQUIST, with whom MR. JUSTICE STEVENS joins,
concurring in the judgment.
I can understand the Court's willingness to reach the merits of
this case, and thereby remove the doubt which has been cast over
this important federal statute. In so doing, however, it ignores
established limitations on district court jurisdiction
Page 438 U. S. 96
as carefully defined in our statutes and cases. Because I
believe the preservation of these limitations is, in the long run,
more important to this Court's jurisprudence than the resolution of
any particular case or controversy, however important, I too would
reverse the judgment of the District Court, but would do so with
instructions to dismiss the complaint for want of jurisdiction.
Cf. Montana-Dakota Utilities Co. v. Northwestern Public Service
Co., 341 U. S. 246,
341 U. S.
249-250 (1951). Giving the conclusory allegations of
appellees' complaint the most liberal possible reading, they
purport to establish only two grounds for the declaratory relief
requested. First, they contend that the Price-Anderson Act deprives
them of their property without due process of law in that it
irrationally limits the tort recovery otherwise available in the
North Carolina courts. [
Footnote
2/1] Second, they contend that the Act works an
unconstitutional taking of their property for public use without
just compensation. They purport to base District Court jurisdiction
upon 28 U.S.C. § 1337 (1976 ed.), which covers
"any civil action or proceeding arising under any Act of
Congress regulating commerce or protecting trade and commerce
against restraints and monopolies."
I
It is apparent that appellees' first asserted basis for relief
does not state a claim "arising under" the Price-Anderson Act.
Their complaint alleges that the operation of the two power plants
will cause immediate injury to property within their vicinity. App.
32, � 21. The District Court explicitly found that these
injuries
"give rise to an immediate right of action for redress. Under
the law of North Carolina, a right of action arises as soon as a
wrongful act has created 'any injury, however
Page 438 U. S. 97
slight,' to the plaintiff."
431 F.
Supp. 203, 221 (WDNC 1977) (citations omitted). This right of
action provided by state, not federal, law is the property of which
the appellees contend the Act deprives them without due process.
Thus, the constitutionality of the Act becomes relevant only if the
appellant Duke Power Co. were to invoke the Act as a defense to
appellees' suit for recovery under their North Carolina right of
action.
It has long been established that the mere anticipation of a
possible federal defense to a state cause of action is not
sufficient to invoke the federal question jurisdiction of the
district courts. In
Louisville & Nashville R. Co. v.
Mottley, 211 U. S. 149
(1908), the plaintiffs sought to compel the specific performance of
a contract by which the railroad had granted them free passes for
life. Although their contract was not predicated upon federal law,
the plaintiffs contended that federal question jurisdiction was
established by the presence of an Act of Congress forbidding
railroads to issue free passes. This Court held that the District
Court did not have jurisdiction to consider whether the Act was
inapplicable or unconstitutional:
"It is the settled interpretation of these words ['arising
under'], as used in this statute, conferring jurisdiction, that a
suit arises under the Constitution and laws of the United States
only when the plaintiff's statement of his own cause of action
shows that it is based upon those laws or that Constitution. It is
not enough that the plaintiff alleges some anticipated defense to
his cause of action and asserts that the defense is invalidated by
some provision of the Constitution of the United States. Although
such allegations show that, very likely, in the course of the
litigation, a question under the Constitution would arise, they do
not show that the suit, that is, the plaintiff's original cause of
action, arises under the Constitution."
Id. at
211 U. S.
152.
Page 438 U. S. 98
Just as the underlying claim in
Mottley arose under
Kentucky contract law, the underlying claim in this case arises
under North Carolina tort law. This Court has construed the
"arising under" language of 28 U.S.C. § 1337 (1976 ed.) just as it
has the similar language of 28 U.S.C. § 1331 (1976 ed.).
Peyton
v. Railway Express Agency, Inc., 316 U.
S. 350,
316 U. S. 353
(1942).
Nor does the fact that appellees seek only declaratory relief
under the Declaratory Judgment Act, 28 U.S.C. § 2201 (1976 ed.),
support a different result. This Court has held that the well
pleaded complaint rule applied in
Mottley is fully
applicable in cases seeking only declaratory relief, because the
Declaratory Judgment Act merely expands the remedies available in
the district courts, without expanding their jurisdiction.
"It would turn into the federal courts a vast current of
litigation indubitably arising under State law, in the sense that
the right to be vindicated was State-created, if a suit for a
declaration of rights could be brought into the federal courts
merely because an anticipated defense derived from federal
law."
Skelly Oil Co. v. Phillips Petroleum Co., 339 U.
S. 667,
339 U. S. 673
(1950).
See also Phillips Petroleum Co. v. Texaco, Inc.,
415 U. S. 125
(1974); C. Wright, A. Miller, & E. Cooper, Federal Practice and
Procedure § 3566, pp. 43738 (1975). [
Footnote 2/2]
Page 438 U. S. 99
Appellees do not. contend that the Price-Anderson Act itself
grants to them personal rights which may be vindicated in a federal
proceeding. Since the only property rights they assert arise under
North Carolina law, the District Court had no jurisdiction to
consider whether the setting up of an Act of Congress as a defense
against those rights would deny them due process of law under the
Fifth Amendment.
Indeed, the Court does not even contend that there is an
independent statutory source of jurisdiction over Duke.
Ante at
438 U. S. 72 n.
16. It suggests, instead, that the complaint states a claim against
the Nuclear Regulatory Commission, not as a joint tortfeasor under
North Carolina law, but as the administrator of an unconstitutional
federal statute. The Court's theory is that the complaint alleges
the existence of an implied right of action under the Fifth
Amendment to obtain relief against arbitrary federal statutes. It
can hardly be said that this theory of the case emerges with
crystal clarity from either the complaint or the brief of the
appellees.
More importantly, there is no allegation in this complaint that
the Nuclear Regulatory Commission has taken or will take any
unconstitutional action at all. The complaint alleges only that the
Commission granted construction permits to
Page 438 U. S. 100
Duke, and that it will enter into an agreement "to indemnify
Duke for any nuclear incident exceeding the amount of $125,000,000
subject to a maximum liability of $560,000,000." App. 31, � 13.
Neither of these actions is alleged to be unconstitutional. The
gist of the complaint is the asserted unconstitutionality of 42
U.S.C. § 2210(e) (1970 ed., Supp. V), which limits Duke's
liability. But this limitation of liability is separate and apart
from the indemnity agreement which the Commission is authorized to
execute under 42 U.S.C. § 2210(d) (1970 ed., Supp. V). The
Commission has nothing whatever to do with the administration of
the limitation of liability; whatever administration of that
statute there is to be is left in the hands of the District Court.
42 U.S.C. § 2210(
o) (1970 ed. and Supp. V). The District
Court, of course, is not a party to this suit. [
Footnote 2/3]
It simply cannot be said that these allegations make out an
actual controversy against the Commission. While the Commission may
be quite interested in the constitutionality of the statute, that
is hardly sufficient to establish a justiciable controversy.
Muskrat v. United States, 219 U.
S. 346,
219 U. S.
361-362 (1911). While appellees may have been damaged by
Duke's decision to construct these plants, there is no "challenged
action of the defendant" Commission to which their damage "fairly
can be traced."
Simon v. Eastern Ky.
Welfare
Page 438 U. S. 101
Rights Org., 436 U. S. 26,
436 U. S. 41
(1976). If Duke decided to proceed with construction despite a
declaration of the statute's unconstitutionality, there would be
nothing that the Commission could do to aid appellees. Where the
prospect of effective relief against a defendant depends on the
actions of a third party, no justiciable controversy exists against
that defendant.
Warth v. Seldin, 422 U.
S. 490,
422 U. S. 505
(1975). In short, appellees' only conceivable controversy is with
Duke, over whom the District Court had no jurisdiction.
II
As appellees themselves describe the second aspect of their
complaint,
"the central issue is whether, in the circumstances of this
case, the complete destruction of appellees' property by a nuclear
accident, occurring at one of Duke's plants, would be a 'taking' by
the United States, as that term is defined in the Fifth
Amendment."
Brief for Appellees 62. This statement makes clear that
appellees' claim arises not under the Price-Anderson Act, but under
the Fifth Amendment itself. Jurisdiction under § 1337 extends only
to actions vindicating rights created by an Act of Congress.
Compare Switchmen v. National Mediation Board,
320 U. S. 297,
320 U. S. 300
(1943),
with General Committee v. Missouri-Kansas-Texas R.
Co., 320 U. S. 323,
320 U. S. 337
(1943). Since it cannot be maintained that the Price-Anderson Act
created appellees' asserted right to be free from takings for
public use without just compensation, it follows that District
Court jurisdiction may not be predicated upon § 1337.
The District Court does have jurisdiction to consider claims of
taking under the Tucker Act, 28 U.S.C. § 1346(a)(2) (1976 ed.),
where the amount in controversy does not exceed $10,000. [
Footnote 2/4]
"But the Act has long been construed as authorizing
Page 438 U. S. 102
only actions for money judgments, and not suits for equitable
relief against the United States."
Richardson v. Morris, 409 U. S. 464,
409 U. S. 464-465
(1973). It is incontrovertibly established that neither the Court
of Claims nor the district courts have jurisdiction under the
Tucker Act to issue the sort of declaratory relief granted here.
Compare ibid. with United States v. King, 395 U. S.
1 (1969). Thus, the record does not establish any
jurisdictional basis upon which the District Court could grant
declaratory relief on appellees' taking claim.
There being no basis for District Court jurisdiction over either
of appellees' claims, its judgment should be reversed and the cause
remanded with instructions to dismiss the complaint for want of
jurisdiction.
[
Footnote 2/1]
Appellees have explicitly abandoned their claim based upon the
so-called equal protection component of the Fifth Amendment,
"since, in this case, any equal protection arguments would be
largely duplicative of appellees' due process arguments." Brief for
Appellees 21 � 26.
[
Footnote 2/2]
The Court asserts that its decision today does not undermine the
well pleaded complaint doctrine because of its conclusion "that the
complaint is more fairly read as stating a claim against the NRC
directly under the Due Process Clause of the Fifth Amendment."
Ante at
438 U. S. 69 n.
13. The supposed claim against the Commission arises only under
federal law, since the complaint does not allege and the District
Court did not find that North Carolina law would provide any remedy
against it as a joint tortfeasor. On the Court's theory of the
case, then, it need not decide whether jurisdiction could be
obtained over Duke Power under § 1331.
Ante at
438 U. S. 72 n.
16. That is a particularly felicitous conclusion from the Court's
point of view, since the complaint does not allege that each member
of the plaintiff class has a claim in excess of $10,000 against
Duke Power, which is a prerequisite to jurisdiction under § 1331.
Zahn v. International Paper Co., 414 U.
S. 291 (1973).
Despite the Court's assurances, it is conceivable that the
practical effect of today's decision could be an erosion of the
well pleaded complaint doctrine. Had the plaintiffs in
Mottley joined as defendants a federal agency having as
ephemeral a relation to the statute challenged there as does the
Commission to the statute involved here, the District Court,
according to today's decision, would have had jurisdiction to
consider the constitutionality of the statute, even though its
judgment would not have been binding against the Louisville &
Nashville Railroad. Innumerable federal statutes and regulations
affect the daily decisions of private passes, who would undoubtedly
appreciate the sort of advisory opinion rendered today on the
validity of those provisions. This Court should not encourage the
hope that such opinions may be obtained by suing an appropriate
federal agency under a claim which verges on the frivolous.
[
Footnote 2/3]
Appellees' challenge to the construction permits was rejected in
Carolina Environmental Study Group v. United States, 166
U.S.App.D.C. 416, 510 F.2d 796 (1975). It is true, as the Court
remarks,
ante at
438 U. S. 81 n.
26, that,
"absent the execution of such [indemnity] agreements between the
NRC and the licensees, the liability limitation provisions of the
Act, to which appellees object, would simply not come into
play."
That logical connection, however, does not amount to an
allegation that the Commission's execution of an indemnity
agreement is itself unconstitutional. The only federal action
challenged by this complaint is a hypothetical district court's
hypothetical invocation of the statute in the event of a
hypothetical nuclear accident. In that entire string of
hypothetical event, no action of the Commission is alleged to be
unconstitutional.
[
Footnote 2/4]
The Court concludes,
ante at
438 U. S. 71 n.
15, although appellees do not so contend, that their taking claim
is cognizable under 28 U.S.C. § 1331(a) (1976 ed.), which grants
jurisdiction to the district courts where the suit "arises under
the Constitution." The Court cites only the
Regional Rail
Reorganization Act Cases, 419 U. S. 102
(1974), in support of its conclusion that this claim may be
maintained under § 1331. It is, of course, well established
that,
"when questions of jurisdiction have been passed on in prior
decisions
sub silentio, this Court has never considered
itself bound when a subsequent case finally brings the
jurisdictional issue before us."
Hagans v. Lavine, 415 U. S. 528,
415 U. S. 535
n. 5 (1974). In the
Regional Rail Reorganization Act
Cases, this Court's opinion did not even cite the statutory
basis for jurisdiction, much less consider its validity. To
conclude that § 1331 embraces a "taking" claim makes the Tucker Act
largely superfluous,
cf. United States v. Testan,
424 U. S. 392,
424 U. S. 404
(1976), and will permit the district courts to consider claims of
over $10,000 which previously could only be litigated in the Court
of Claims.
Richardson v. Morris, 409 U.
S. 464 (1973). Such a significant expansion of the
jurisdiction of the district courts should not be accomplished
without the benefit of arguments and briefing.
MR. JUSTICE STEVENS, concurring in the judgment.
The string of contingencies that supposedly holds this
litigation together is too delicate for me. We are told that, but
for the Price-Anderson Act, there would be no financing of nuclear
power plants, no development of those plants by private parties,
and hence no present injury to persons such as appellees; we are
then asked to remedy an alleged due process violation
Page 438 U. S. 103
that may possibly occur at some uncertain time in the future,
and may possibly injure the appellees in a way that has no
significant connection with any present injury. It is remarkable
that such a series of speculations is considered sufficient either
to make this litigation ripe for decision or to establish
appellees' standing;* it is even more remarkable that this occurs
in a case in which, as MR. JUSTICE REHNQUIST demonstrates, there is
no federal jurisdiction in the first place.
The Court's opinion will serve the national interest in removing
doubts concerning the constitutionality of the Price-Anderson Act.
I cannot, therefore, criticize the statesmanship of the Court's
decision to provide the country with an advisory opinion on an
important subject. Nevertheless, my view of the proper function of
this Court, or of any other federal court, in the structure of our
Government is more limited. We are not statesmen; we are judges.
When it is necessary to resolve a constitutional issue in the
adjudication of an actual case or controversy, it is our duty to do
so. But whenever we are persuaded by reasons of expediency to
engage in the business of giving legal advice, we chip away a part
of the foundation of our independence and our strength.
I join MR. JUSTICE REHNQUIST's opinion concurring in the
judgment.
* With respect to whether appellees' claim of present injury is
sufficient to establish standing, it should be noted that some sort
of financing is essential to almost all projects, public or
private. Statutes that facilitate and may be essential to the
financing abound -- from tax statutes to statutes prohibiting
fraudulent securities transactions. One would not assume, however,
that mere neighbors have standing to litigate the legality of a
utility's financing.
Cf. Blue Chip Stamps v. Manor Drug
Stores, 421 U. S. 723.