1. A bond given to the United States, pursuant to 40 U.S.C. §
270, for the faithful performance of a construction contract and
for the making of prompt payment to all persons supplying the
principal with labor and materials in the prosecution of the work,
inures to the laborers and materialmen as obligees, together with
the United States, though the claims of the Government have
priority. P.
296 U. S.
135.
2. Where a bond securing payment of the claims of materialmen
was required by statute, and its full amount has been paid by the
surety and applied in part satisfaction of such claims, the surety,
against such claimants, has no equity to reimbursement from funds
of its insolvent principal until such claims have been
Page 296 U. S. 134
settled in full; such an equity does not arise from the doctrine
of subrogation, nor from an express contract of the principal, made
before he became insolvent, to indemnify the surety out of those
particular funds -- in this case the "retained percentage" due the
principal under a construction contract. P.
296 U. S.
137.
75 F.2d 377 affirmed.
Certiorari, 295 U.S. 723, to review the affirmance of a decree
of the District Court, in bankruptcy, directing that a fund
belonging to the bankrupt, which had been retained by the United
States as security from moneys due him under a construction
contract, should be devoted to payment of claims of creditors who
furnished materials for the performance of the contract, to the
exclusion of the claim for reimbursement of the surety on the
contractor's bond.
MR. JUSTICE CARDOZO delivered the opinion of the Court.
A contract for drilling a well at the Naval Air Station at
Pensacola, Florida, was made in November, 1930, between Melton J.
Gray and the United States government. It was drawn in the standard
form. Payments were to be made in accordance with approved
estimates during the progress of the work, but the contracting
officer was required to retain 10 percent of the estimated amount
"until final completion and acceptance of all work covered by the
contract." The percentage might be reduced in stated contingencies.
A bond was to be given for the protection of the government and of
persons supplying labor and materials. If, thereafter, a surety
upon the
Page 296 U. S. 135
bond became unacceptable, the contractor was to furnish such
additional security as might be required to protect the interests
concerned.
The total contract price was $13,133.36. The bond which was
executed by the contractor and by the petitioner as surety was in
the penal sum of $3,940. The condition was that the principal --
i.e., the contractor -- should perform the contract in all
its terms, and in addition should "promptly make payment to all
persons supplying the principal with labor and materials in the
prosecution of the work." The additional obligation thus incurred
is one exacted by statute. Act of August 13, 1894, c. 280, 28 Stat.
278, Act of February 24, 1905, c. 778, 33 Stat. 811, Act of March
3, 1911, c. 231, § 291, 36 Stat. 1167, 40 U.S.C. § 270. Laborers
and materialmen, together with the government, are obligees or
beneficiaries of a bond so given (
Equitable Surety Co. v.
United States, 234 U. S. 448;
Illinois Surety Co. v. John Davis Co., 244 U.
S. 376;
Brogan v. National Surety Co.,
246 U. S. 257),
though the claims, if any, of the government are to have priority
of payment. 40 U.S.C. § 270.
The contractor finished the work required by the contract, but
did not make payment to all persons supplying him with labor and
materials. Demand was made upon the surety, which paid into court
$3,940, the full amount of the penalty, for distribution among the
respondents in proportion to their interests. The payment did not
satisfy what was owing to them for labor and materials furnished
for the well. Thereupon conflicting claims arose to the 10 percent
retained by the government in accordance with the contract. On the
one hand, the surety laid claim to this reserved percentage
($2,724.23) by right of subrogation, and also and with greater
emphasis by force of a covenant of indemnity received from the
principal at the beginning of the work. On the other hand, the
reserved percentage was claimed by the respondents
Page 296 U. S. 136
on the ground that the effect of the statute, the contract, and
the bond, when read together, was to make the equity of the surety
subordinate to theirs. Out of this equity there grew, as they
contended, a right or an interest which, even if not a lien in the
strict and proper sense, brought kindred consequences along with
it. At least a court of equity would not come to the aid of one
whose equity was subordinate until claims superior in equity had
been satisfied in full.
By this time, Gray was a bankrupt, and a trustee in bankruptcy
was in charge of his affairs. The government turned over the fund
to the trustee, who held it to abide the order of the court. No
claim to any part of it was put forward by the general creditors or
by the trustee in their behalf. The controversy was solely between
the materialmen, on the one side, and the surety, on the other.
Indeed, there is nothing to show that any other creditors than
these existed. The District Court, confirming a report of a
referee, gave priority to the materialmen and made a decree
accordingly. The Court of Appeals for the Fifth Circuit affirmed,
one judge dissenting. 75 F.2d 377. A writ of certiorari brings the
case here.
The materialmen were creditors of the contractor, their standing
as such being unchallenged in the record or in argument. The
contractor was under a legal duty at the time of his insolvency to
pay their claims in full. This obligation would have been his apart
from any bond, the debtor-creditor relation subsisting
independently. As to materialmen in that relation, the statute and
the bond did not add to the extent of the contractor's obligation,
though they made it definite and certain. What their effect would
be when applied to materialmen not creditors of the contractor is a
question not before us. The obligation of the surety, however,
unlike that of the contractor, was created solely by the bond, and
is limited thereby and by the equities growing out of the
suretyship relation.
Page 296 U. S. 137
In any suit upon the bond, at least against the surety, the
nominated penalty was to be the limit of recovery. Upon payment of
that penalty, it was to be "relieved," in the words of the statute,
"from further liability." 40 U.S.C. § 270.
Liability to pay was ended, but equities growing out of the
suretyship relation survived in undiminished force. Acquittance
under the bond did not leave the surety at liberty to prove against
the assets of the insolvent principal on equal terms with the
materialmen, still less to go ahead of them. The settled principles
of the law of suretyship forbid that competition.
Jankins v.
National Surety Co., 277 U. S. 258,
277 U. S. 266.
A surety who has undertaken to pay the creditors of the principal,
though not beyond a stated limit, may not share in the assets of
the principal by reason of such payment until the debts thus
partially protected have been satisfied in full. This is the rule
where the right to a dividend has its basis in the principle of
equitable subrogation.
"A surety liable only for part of the debt does not become
subrogated to collateral or to remedies available to the creditor
unless he pays the whole debt or it is otherwise satisfied."
United States v. National Surety Co., 254 U. S.
73,
254 U. S. 76.
* If the holding
were different, the surety would reduce the protection of the bond
to the extent of its dividend in the assets of the debtor.
Jenkins v. National Surety Co., supra. The rule is the
same, and, for like reasons, where the basis of the claim is the
debtor's promise to indemnify, if the debtor is insolvent when the
promise is enforced.
Jenkins v. National Surety Co.,
supra, at pp.
277 U. S.
266-267.
Cf. Springfield National Bank v. American
Surety Co. of New York, 7 F.2d 44.
"Wherever equitable principles are called in play, as they
preeminently are in determining the
Page 296 U. S. 138
rights and liabilities of sureties and in the distribution of
insolvents' estates, they likewise forbid the surety to secure by
independent contract with the debtor indemnity at the expense of
the creditor whose claim he has undertaken to secure."
Jenkins v. National Surety Co., supra, at p.
277 U. S. 267.
This is surely so unless the contract of indemnity has the effect
of a specific lien. In the absence of such a lien, the reserved
percentages in controversy became assets available to creditors,
the respondents along with others, upon the completion of the work
to the satisfaction of the government. Insolvency supervening, the
surety must be postponed in the distribution of the assets to the
remedies of any claimants who are members of the class of creditors
covered by the bond.
The petitioner draws a distinction between a general promise to
indemnify, which would be implied if not expressed, and a promise
whereby a specific fund, whether in being or to arise thereafter,
is set apart or earmarked as collateral security. We are told in
effect that the displacement of a lien is an exercise of power more
drastic and far-reaching than the marshaling of assets where there
has been no agreement for a lien. The distinction might be
important if the contest were between the surety and creditors not
covered by the bond, or between the surety and later assignees of
the security so promised.
Prairie State Bank v. United
States, 164 U. S. 227;
Henningsen v. United States Fidelity & Guaranty Co.,
208 U. S. 404.
Such is not the situation here, even though we assume in aid of the
petitioner that the promise to indemnify, obscure in its terms, is
to be read as amounting to a specific appropriation of the
percentages reserved or of any other assets. The contest in this
cause is between the surety, on the one hand, and, on the other
hand, creditors of the class it has undertaken to protect. At such
times, the position
Page 296 U. S. 139
of the surety is not bettered though the promise is directed to
particular collateral -- at all events, where the bond is one
required by the law. What considerations may govern after payment
of the penalty in full where the bond is altogether a voluntary
security we do not need to inquire. Cases such as
Keller v.
Ashford, 133 U. S. 610,
133 U. S. 622;
Hampton v. Phipps, 108 U. S. 260,
108 U. S. 263,
and
Moses v. Murgatroyd, 1 Johns.Ch. 119, 129, though they
suggest an analogy, do not control, even in principle, for there,
the surety was in default upon his obligation to the creditor.
Slight differences in the facts may cause the equities to vary, and
thus vary the result. What concerns us here is the remedy available
where the bond has been given under the mandate of a statute.
Equity then forbids that the statutory security be whittled down
indirectly by any promise of indemnity, general or specific. Debtor
and surety may not effectually agree that materialmen and laborers
shall have less of the general assets as the price of their right
to recover on the bond. Through the bond and the statute, a new
relation has been established, with a new set of equities not
subject to destruction at the pleasure of the principal. The
integrity of that relation is in the keeping of the law.
We have no occasion to consider to what extent the creditors of
the bankrupt not covered by the bond are affected by the equities
of creditors so covered or by those of the petitioner with the
result that their claims are to be held subordinate thereto.
Cf. Prairie State Bank v. United States, supra; Henningsen v.
United States Fidelity & Guaranty Co., supra. As we have
already pointed out, the record does not show that there are any
general creditors, and, if any such exist, they are not complaining
of the decree. Our decision must be kept within the bounds of the
controversy before us.
Page 296 U. S. 140
The decree of the Circuit Court of Appeals is accordingly
Affirmed.
*
Cf. Peoples v. Peoples Bros., 254 F. 489;
Maryland Casualty Co. v. Fouts, 11 F.2d 71;
McGrath v.
Carnegie Trust Co., 221 N.Y. 92, 95, 116 N.E. 787.
MR. JUSTICE ROBERTS, dissenting.
The opinion of Judge Sibley in the court below, 75 F.2d 377,
380, seems to me conclusive upon the propositions that neither the
common law, the contract with the government, nor the bond
furnished by the contractor, give materialmen or laborers any right
of lien upon the fund or preference in distribution thereof. I also
agree with his view that the indemnity contract between the
contractor and the surety company (even if an assignment of claim
for retained percentages against the United States were valid, in
view of Rev. St. § 3477) is too vague to amount to an assignment of
the retained percentages, and that the surety is not entitled to
subrogation either to the rights of the United States or of the
materialmen and contractors. I think it clear that, in the
circumstances, the amount paid by the United States into the fund
in the hands of the trustee in bankruptcy is general assets of the
estate, and that the surety company, as respects its claim for the
amount paid under its bond and the furnishers of material and
labor, are general creditors entitled to no preference or priority
over each other. I think the judgment should therefore be
reversed.