1. Broad provisions in a government contract authorizing the
government to change the obligations imposed on the other party
should be interpreted not as permitting government officials to
remold the contract at will, but as confined to what was fairly and
reasonably within the contemplation of the parties when the
contract was made. P.
260 U. S.
62.
2. Where a contractor undertook a circuit mail carriage service
from and back to a city post office site via scheduled stations,
with stops en route to collect mail from letter carriers, to be
paid for at so much for every mile traveled, a stipulation in the
contract authorizing the Postmaster General to establish service to
and from like offices, stations, etc., to those named in the
schedules, to be paid for at the contract rate per mile of travel,
did not authorize substitution of a much heavier service, in
transporting all mail between railroad stations and another post
office site, involving increased equipment and expense, and paid
for at the same mileage rate but without counting trips on which no
mail was carried. P.
260 U. S.
64.
3. Contractors who were encouraged by agents of the Post Office
Department to enter into a mail carriage contract and give a heavy
bond, without notice of the Department's purpose to substitute a
more onerous service under color of the contract but not within its
terms, and who performed the new service under protest, rather than
incur the risk to themselves and their bondsmen of throwing up the
contract,
held not to have acquiesced in the change. P.
260 U. S.
68.
4. A mail carriage contractor who, under duress of the Post
Office Department, performs service not called for by his contract
is entitled to recover, in the Court of Claims, the reasonable
value of such service, including a fair profit. P.
260 U. S.
69.
56 Ct.Clms. 15 reversed.
Appeals from a judgment allowing in part a claim for service in
carrying the mails.
Page 260 U. S. 61
MR. CHIEF JUSTICE TAFT delivered the opinion of the Court.
This is a suit against the government to recover $34,012.90 as
the remainder unpaid of an amount earned by 16 months' service in
carrying the mails by wagons in the City of St. Louis. After
official advertisement, a bid was made by appellants April 4, 1911,
and accepted April 20, 1911, for service on a particular route
described by a schedule, for a certain annual gross sum, which,
being divided by the miles to be covered, made a certain rate per
mile. A contract was signed May 22nd. The contract was for four
years, beginning July 1, 1911. The route was for seven daily
circuit trips from and back to the new St. Louis Post Office. That
office was not ready for occupancy on July 1, 1911, or for 16
months thereafter, and the old post office, which was 13 blocks
from the new one, continued to be used. The Post Office Department,
relying on certain clauses in the contract and upon a notice given
to bidders, substituted another route and ordered the contractor to
begin performance on July 1st at what the Department held to be the
same rate per mile of service. The contractors protested, but,
threatened with suit upon their bond, performed the service and
accepted periodical payments on the new route until October 28,
1912, the date of occupying the new post office, when the route bid
upon and contracted for was initiated and the contractors did the
work under it till the term ended. The cost to the contractors of
doing the work on the substitute route was $43,726.89,
Page 260 U. S. 62
and they were paid by the government $24,289.62. Thus, their
loss was, in round numbers, $19,500 during the 16 months of the
substituted route. After October 12, 1912, on the original route,
the contractors made a profit of 42 percent on its cost in what
remained of the term.
The contractors' claim was that the substitution of the new
route for the one they bid on was not within the terms of the
contract, but was unconscionable, and that they were entitled to
recover for the work done on the new route on a
quantum
meruit. The Court of Claims held that it was not necessary to
determine whether the new route was properly substituted for the
old, because the contractors had acquiesced in this view by their
performance, but that the government had not, in adapting the
mileage rate of the original route under the contract to the new
route, done justice to the contractors in the number of miles
allowed, and, on this basis, gave judgment for $7,346.66. From
this, the contractors appealed. The government brings a
cross-appeal, claiming that, as the contractors accepted full pay
under the contract as construed and expressed by the Department,
they should recover nothing.
It is, of course, wise and necessary that government agents, in
binding their principal in contracts for construction or service,
should make provision for alterations in the plans or changes in
the service within the four corners of the contract, and thus avoid
the presentation of unreasonable claims for extras. This Court has
recognized that necessity and enforced various provisions to which
it has given rise. But sometimes such contract provisions have been
interpreted and enforced by executive officials as if they enabled
those officers to remold the contract at will. The temptation of
the bureau to adopt such clauses arises out of the fact that they
avoid the necessity of labor, foresight, and care in definitely
drafting the contract, and reserve power in the bureau. This
does
Page 260 U. S. 63
not make for justice, it promotes the possibility of official
favoritism as between contractors, and results in enlarged
expenditures, because it increases the prices which contractors, in
view of the added risk, incorporate in their bids for government
contracts. These considerations, especially the first, have made
this Court properly attentive to any language or phrase of these
enlarging provisions which may be properly held to limit their
application to what should be regarded as having been fairly and
reasonably within the contemplation of the parties when the
contract was entered into. These observations are justified and
illustrated by decisions of this Court in
United States v.
Stage Co., 199 U. S. 414, and
Hunt v. United States, 257 U. S. 125.
The Court of Claims, after giving the two schedules in full,
sums up the contrast between them as follows:
"The service bid upon was a circuit service on seven circuits,
on a mileage basis, each circuit beginning and ending at the new
post office and for which the contractor was paid for every mile
traveled regardless of the quantity of mail carried or whether, for
any part of the distance, no mail was carried. The restated service
[
i.e., on the new route] was a trip service for which
payment was made on a mileage basis when mail was carried, but no
payment was made for a return trip if mail was not carried, or for
distance traveled by empty vehicles in going to a point from which
mail was to be moved."
"The service bid upon involved the handling of the mails for a
small area, and was a comparatively light service. The restated
service required the hauling of incoming and outgoing mails for the
entire city, and involved handling several times the weight of
mail. The service bid on required 6 automobiles. The restated
service required 18 wagons of different capacity exceeding several
times in aggregate capacity that required for the bid on the
service. The mileage of each wagon, when carrying
Page 260 U. S. 64
mail was allowed and paid for. The larger bulk of mail required
proportionately more time in loading and unloading."
"The bid upon service, with the exception of one early trip on
each of these circuits, was all to be performed within 12 hours
from approximately 8 a.m. to 8 p.m. The restated service required
trips during practically every hour of the 24."
By a note in the advertisement, by paragraph ten in the
contract, and by further somewhat more elaborate stipulation in the
contract, provision was made for changes. The last contained all
that was in the others, and was as follows:
"It is hereby stipulated and agreed by said contractors and
their sureties that the Postmaster General may change the schedule,
vary, increase, or decrease the trips on this route, or extend the
trips to any new location of the post offices, railroad stations,
steamboat landings, mail stations, or points of exchange, with
cable or electric cars named in the schedule for service for said
route, in said advertisement, establish service to and from like
offices, stations landings, or points not named therein, and vary,
increase, or decrease the trips thereto, and discontinue service
between any of the post offices, railroad stations, steamboat
landings, mail stations, or points of exchange with electric or
cable cars, or between any of them:
Provided, that for any
increase or decrease in the service authorized by the Second
Assistant Postmaster General, the pay of the contractors shall be
increased, as the case may be at the rate per mile of travel agreed
to be paid for service under this contract, as shown by the annual
rate of compensation and the annual miles of travel, based on the
frequency and distances shown in the schedule of service for said
route in said advertisement."
There are two limitations in this very broad provision which
deserve notice. One is that the offices, stations,
Page 260 U. S. 65
landings, and points, not named in the schedule, to and from
which the Postmaster General was permitted to establish service,
were to be like those named in the schedule, and the other is that
the substituted service was to be such that the method of fixing
pay in the original contract could be applied to it. Now it is
clear to us that the substituted route did not establish a route to
like stations and points. The findings give the two schedules and
we reproduce them in the margins.
* An
examination
Page 260 U. S. 66
shows that the one was a light service of circuits from the post
office and back again to take up collections from
Page 260 U. S. 67
letter carriers. The other was the heavy work of transporting
all the arriving and departing mail of the city from the railway
stations to the old post office and back again. On the one, the
contractors received pay for every mile traveled. On the other, the
pay was made dependent on the carriage of mail, and no empty trips
of going or returning were included in the mileage paid for,
although the schedule made many of them necessary. It is
impossible, therefore, save by forcing, to adapt the rate per mile
of one route to the other. What has been said shows how different
was the equipment needed, how variant the tonnage carried, what
disparity between the hours of readiness required, and the
differing methods of calculating compensation. This substituted
route was undoubtedly necessary in the transportation of mails in
the City of St. Louis, but it was for a different purpose from that
of the original route. The Department merely took advantage of
general words in the appellants' contract to meet an emergency
presented by the delay in finishing the new post office and the
refusal of another contractor to continue this indispensable
service beyond his term, to thrust this entirely new task upon the
appellants here.
It is sought in the argument for the government to distinguish
this case from the
Stage Company case and the
Hunt case on the ground that, in them, the compensation
was for a lump sum, and the new work required was not to be paid
for at all, while here, the additional or variant work was to be
done at a rate of so many cents per mile. We do not think this is a
real difference. The radical change made in the character of the
work to be done on the substituted route and the wholly inadequate
price to be paid for it as found by the Court of Claims make the
injustice just as clear as in the cited cases. We hold that the
substitution of the new route and schedule for the one bid upon was
not within the terms of the contract.
Page 260 U. S. 68
But it is said that, in view of the attitude of the government,
the conduct of the contractors constituted such an acceptance of
the new route as within the original contract as to rebut any
implication of a different contract for a reasonable price on the
part of the government. Consideration of this argument requires a
review of the circumstances. The findings show that the
advertisement for bids referred bidders to the city postmaster for
any additional information concerning the matter, and that he
advised these contractors, when they doubted whether they could get
their equipment ready by July 1st, that the new post office could
not be completed at that time, that the work bid for could not
begin then, and that the Department would take care of the
situation. They thereupon made their bid, accompanying it as
required with a bond for $25,000. The bid was accepted by the
Department with a special notice as to the necessity of being ready
with equipment July 1st, and enclosing the contract. The city
postmaster, being applied to again by the anxious bidders, assured
them that the matter would be adjusted in due time, and urged them
to sign the contract. Accordingly, on May 23d, the contractors
signed and forwarded the contract to the Department, with a request
for extension of time. This was denied, and, on application to the
Department June 20th for relief because of the assurance of the
postmaster, they were told that they would be given a substituted
route then in the course of preparation. They objected that they
could not prepare for this substituted route, which, as already
said, was a mere continuance of old service by another contractor.
They were told that they must be ready for the restated route at
the time appointed, and, on June 30th, they were furnished with a
schedule of the new service. The contractors protested to the
Second Assistant Postmaster General, to the postmaster at St.
Louis, and to one Porter, a representative of the Department at
Page 260 U. S. 69
St. Louis, saying that they were not required to perform this
service by the terms of the contract, because it was entirely
different from that contemplated, and that they would be ruined
financially. Porter, whose authority is not otherwise shown, told
them that his business was to see that the service commenced on
July 1st, and, if they did not begin, the contract would be
readvertized, and they would be sued on their bond. The contractors
then hired the equipment and outfit of the old contractor, with the
result, already stated, that they lost $19,500 in 16 months.
We think that there was no acceptance of the new route under the
circumstances which would bar a recovery for what the services were
reasonably worth. The
Hunt case was not a stronger case
than this, and, in the
Stage Company case, the right to
recover for work not properly and legally included in the contract
was not even questioned, although in both cases the work demanded
was done and periodical payments accepted. It is said on behalf of
the government that those cases are to be distinguished from this
because the contractor was in the midst of his work under his
contract, and he could not be expected to throw it up, with all the
uncertainties and certain losses he would sustain, while here the
contractors had not begun work or extended preparation. But, while
the cases are different, the difficulties faced by the contractors
here were quite as formidable. They had been nursed into making the
bid and giving the bond by the assurance as to the possible date of
beginning the contract by the postmaster, to whom they had been
officially referred for information. They thus became bound under
their bond to sign and complete the contract before they had been
otherwise advised as to the actual date when their service would
begin. At the time the contract was executed, the Department had
formed the purpose to thrust on the contractors this burdensome
route, but it
Page 260 U. S. 70
did not advise them of it until ten days before July 1st, and,
indeed, did not give them the exact schedule until the day before
they were to begin it. Then the only course open to them was either
to engage the old contractor's equipment at a heavy loss or throw
up the original contract and run the risk of the government's
reletting at a higher bid and charging the possible heavy
difference in cost to it against them on their bond for a five-year
contract. We cannot ignore the suggestion of duress there was in
the situation, or the questionable fairness of the conduct of the
government, aside from the illegality of the construction of the
contract insisted on, and have no difficulty, therefore, in
distinguishing this case from the so-called
Railroad Mail
Cases (
Eastern R. Co. v. United States, 129 U.
S. 391;
Chicago, Milwaukee & St. Paul Ry. Co. v.
United States, 198 U. S. 385;
Atchison Railway v. United States, 225 U.
S. 640;
New York, New Haven & Hartford R. Co. v.
United States, 251 U. S. 123;
New York, New Haven & Hartford R. Co. v. United
States, 258 U. S. 32),
which are cited on behalf of the United States.
We think that the contractors are entitled to recover the
reasonable value of their services for the 16 months, including a
fair profit.
This relieves us of considering the conclusion reached by the
Court of Claims.
The judgment is reversed, the cross-appeal of the United States
is dismissed, and the case is remanded to the Court of Claims with
directions to find the value of the services rendered by appellants
on the substituted or restated route, including a fair profit, and
to enter judgment for the balance found due.
*
bwm:
Route No. 445004. (Mileage Basis) -- Regulation
Screen-Wagon
Service at St. Louis Mo. -- Mail-Station Service
-------------------------------------------------------------------------------------------------------
Num- Total
ber of Num- num-
trips ber of ber of Run-
Dis- daily trips trips ning
From By To tances except on holi- time
Sun- Sun- days
day day (7)
(306)
-------------------------------------------------------------------------------------------------------
Miles Min.
Circuit No. 1: Central Station Post office (new site) 2.00 23 5
5 25
Post Office (old post and 4 stops per trip
(new site) office) en route to receive
mail collections from
letter carriers
Circuit No. 2: Cupples and Post office (new site) 2.60 9 5 5
30
Post Office Merchants and 1 stop per trip
(new site) stations en route to receive
mail collections from
letter carriers
Circuit No. 3: Progress and Post office (new site) 3.00 9 5 5
30
Post Office Bridge sta- and 7 stops per trip
(new site) tions en route to receive
mail collections from
letter carriers
Circuit No. 4: Cupples and Post office (new site) 2.80 11 0 0
30
Post Office Merchants and 6 stops per trip
(new site) stations en route to receive
mail collections from
letter carriers
Circuit No. 5: Merchants and Post office (new site) 2.80 11 0 0
30
Post Office Central (old and 2 stops per trip
(new site) post office) en route to receive
stations mail collections from
letter carriers.
Circuit No. 6: Bridge and Post office (new site) 3.00 11 0 0
30
Post Office Progress and 2 stops per trip
(new site) stations en route to receive
mail collections from
letter carriers
Circuit No. 7: Progress sta- Post office (new site) 2.20 11 0 0
30
Post Office tion and 5 stops per trip
(new site) en route to receive
mail collections from
letter carriers
-------------------------------------------------------------------------------------------------------
ewm:
Postoffice Department
Second Assistant Postmaster General
Washington, June 30, 1911
"Postmaster, St. Louis, Mo."
"Sir: An order has been issued today on route No. 445004,
screen-wagon service at St. Louis, Mo. restating the service from
July 1, 1911, making total annual travel 57,679.60 miles and pay
$18,265.61 per annum, being pro-rata of original contract
price."
bwm:
------------------------------------------------------------------------------------------------
No. of
No. of trips daily trips Addi-
Length except Sundays on tional
From To of trip, and holidays Sun- trips a
miles (306) day week
(52) (52)
------------------------------------------------------------------------------------------------
GPO Union Depot 1.18 71 37 4
71 Holidays (7)
Union Depot GPO 1.18 32 25 2
32 Holidays (7)
GPO United Rys. of St. 0.21 29 6
Louis (8th and Market) 23 Holidays (7)
United Rys. of St. Louis GPO 0.21 31 4
(8th and Market) 12 Holidays (7)
GPO United Rys. of St. 0.09
Louis (8th and Locust)
United Rys. of St. Louis GPO 0.09 8 1
(8th and Locust) 3 Holidays (7)
GPO Cupples Sta. 0.50 10
5 Holidays (7)
Cupples Sta. GPO 0.5 10
5 Holidays (7)
GPO Merchants Sta. 0.5 9
4 Holidays (7)
Merchants Sta. GPO 0.5 9
5 Holidays (7)
GPO via Merchants Sta. Bridge Sta. 0.76 2
1 Holiday (7)
Bridge Sta. via Mer-
chants Sta. GPO 0.76 1
GPO Bridge Sta. 0.60 3
2 Holidays (7)
Bridge Sta. GPO 0.60
1 Holiday (7)
GPO Progress 0.70 8
4 Holidays (7)
Progress GPO 0.70 5
3 Holidays (7)
Progress Sta. Annex Sta. 0.60 2
Merchants Sta. via GPO 0.76 2
Bridge Sta. 0.50 2 Holidays (7)
18th and Olive (345001) Annex Sta. 0.50 3
18th and Clark (345001) Annex Sta. 0.09 2
------------------------------------------------------------------------------------------------
ewm:
"Respectfully,"
(Signed) JOSEPH STEWART
Second Assistant Postmaster General