Case Resources
Search this Case
in Google Scholar
on the Web
Google Web Search
MSN Web Search
Yahoo! Web Search
in the News
Google News Search
Google News Archive Search
Yahoo! News Search
in the Blogs
BlawgSearch.com Search
Google Blog Search
Technorati Blog Search
in other Databases
Google Book Search
Online Research Resources
Cornell LII
Cornell Wex Dictionary & Encyclopedia
LLRX.com - Legal Research
Expert Witness Directory
Nolo Consumer & Business
US Court Forms
USA Constitution Annotated
WashLaw Directory
World LII
Online Case Law
Cornell LII
FastCase $
Lexis $
LexisOne
Loislaw $
USSCPlus.com $
VersusLaw $
Link to the Case Preview: http://supreme.justia.com/us/321/730/
Link to the Full Text of Case: http://supreme.justia.com/us/321/730/case.html
U.S. Supreme Court
United States v. Blair, 321 U.S. 730 (1944)
United States v. Blair
No. 75
Argued February 1, 1944
Decided April 10, 1944
321 U.S. 730
Syllabus
1. The Government construction contract here involved imposed no duty on the Government to take affirmative steps to prevent a contractor from unreasonably delaying or interfering with the attempt of another contractor to complete construction in advance of the time specified, and the Government was not liable for damages for such delay. P. 321 U. S. 733.
The fact that, after the execution of the contract, the contractor gave notice to all other parties of his intention to finish ahead of schedule does not alter the obligation of the Government.
2. An award of damages by the Court of Claims against the Government on items which were the subject of "disputes concerning questions arising under this contract" -- though the actions of the Government agents upon which the claims were based be assumed to have been unauthorized, unreasonable and arbitrary -- held erroneous in view of the failure of the contractor to appeal to the departmental head as required by Article 15 of the contract, it not appearing that the appeal procedure provided was in fact inadequate. P. 321 U. S. 735.
3. The Court of Claims properly allowed a claim of the contractor, to the use of a subcontractor, for extra labor costs incurred by the subcontractor under conditions erroneously imposed by the Government superintendent. P. 321 U. S. 737.
99 Ct.Cls. 71 reversed in part.
Certiorari, 320 U.S. 720, to review a judgment for the plaintiff in a suit against the Government upon a contract.