An employee of respondent contractor was injured while engaging
in work that respondent was performing for the Government under a
fixed-price contract providing that the private contractor "shall
be responsible for all damages to persons or property that occur as
a result of his fault or negligence. . . ." In a suit against the
Government under the Federal Tort Claims Act, the employee was
awarded damages based upon the Government's negligence. Thereafter,
the Government brought this action for indemnification, alleging
that the contractor's negligence was solely responsible for the
employee's injuries. The District Court granted respondent's motion
to dismiss, in part on the ground, thereafter sustained by the
Court of Appeals, that the contract clause was not broad enough to
permit indemnification of the Government for its own negligence,
which had substantially contributed to the injury.
Held: Though the Government, under the contract clause
involved here, cannot recover for its own negligence, it is
entitled to indemnity on a comparative basis to the extent that it
can prove that respondent's negligence contributed to the
employee's injuries. Pp.
397 U. S.
209-217.
408 F.2d 140, reversed and remanded.
Page 397 U. S. 204
MR. JUSTICE BRENNAN delivered the opinion of the Court.
This case concerns the construction of a provision common to
fixed-price government construction contracts that states that the
private contractor "shall be responsible for all damages to persons
or property that occur as a result of his fault or negligence. . .
." The Court of Appeals for the Fifth Circuit held that the
provision could not be construed to allow the Government to recover
from the contractor damages suffered by the Government on account
of its own negligence. 408 F.2d 146 (1969). We granted certiorari
because of the large amount of litigation that this contract clause
has produced [
Footnote 1] and
because of the divergent results that the lower courts have reached
in construing the same or similar provisions. [
Footnote 2] 396 U.S. 815 (1969). We reverse.
I
The United States had entered into a contract with the Seckinger
Company for the performance of certain plumbing work at a United
States Marine base in South Carolina. While working on this
project, one of Seckinger's employees was directed by his foreman
to assist a fellow employee on a particular section of pipe that
had been partially constructed above a street. About four or five
feet above the place where the employee was working, there was an
electric wire that carried 2,400 volts of electricity. The employee
accidentally
Page 397 U. S. 205
came into contact with the wire, was thrown to the ground 18
feet below and was seriously injured.
The injured employee recovered benefits under South Carolina's
workmen's compensation law, S.C.Code Ann. §§ 72-1 to 7-504 (1962),
and then commenced a suit in the Eastern District of South Carolina
against the United States under the Federal Tort Claims Act, 28
U.S.C. §§ 2671-2680, on the theory that his injuries had been
sustained as the proximate result of the Government's negligence.
The United States, relying on the contract clause, moved to implead
Seckinger as a third-party defendant. This motion was denied on the
ground that the addition of Seckinger would "unnecessarily and
improperly complicate the issues." [
Footnote 3]
On the merits, the South Carolina District Court found that the
United States had customarily de-energized its electric wires
whenever Seckinger employees were required to work dangerously near
them. The court therefore held that the United States had been
grossly negligent in failing to de-energize the wire in this
particular case. Alternatively, the Government was held to have
been negligent in failing to advise Seckinger's employees that the
electric wire had not been de-energized. Concluding also that the
employee had in no way contributed to his injury, the District
Judge ordered that he recover a judgment against the United States
in the amount of $45,000 plus costs. No appeal was taken from this
judgment of the District Court. [
Footnote 4]
Page 397 U. S. 206
Thereafter, the United States proceeded to the District Court
for the Southern District of Georgia and commenced the instant suit
against Seckinger. The complaint alleged that Seckinger's
negligence was solely responsible for its employee's injuries,
[
Footnote 5] and that,
therefore, the United States should be fully indemnified for the
judgment which it had satisfied. In a second count, the Government
alleged that Seckinger, having undertaken to perform its contract
with the United States, was obligated "to perform the work properly
and safely and to provide workmanlike service in the performance of
said work."
The District Court granted Seckinger's motion to dismiss the
complaint on the alternative grounds, first, that the suit was
barred by the prior litigation in South Carolina, and, second, that
the contractual language was not sufficiently broad to permit the
Government to recover indemnification for its own negligence. The
Court of Appeals rejected the first ground of decision, [
Footnote 6] but sustained
Page 397 U. S. 207
the holding that any recovery on the contract was foreclosed to
the United States because its negligence had contributed
substantially to the injury. The Court of Appeals held that, under
the "majority rule," an indemnitee cannot recover for his own
negligence in the absence of a contractual provision which
unmistakably authorizes this result. Since the contract here did
not unequivocally command that the Government be indemnified for
its own negligence, and because the injuries in question were
thought to have been caused by the "active direct negligence" of
the Government with no more than a "slight dereliction" on the part
of Seckinger, no recovery whatsoever on the contract would be
permitted to the United States. [
Footnote 7]
In the Government's view, this construction of the clause
renders it a nullity, for the United States can never be held
liable in tort, under the Tort Claims Act or otherwise, in the
absence of negligence on the part of its agents. Thus, so the
argument goes, the contractual provision in question can have
meaning only in a context in which both the United States and the
contractor are jointly negligent. [
Footnote 8] In that circumstance, the contractor would be
obligated to sustain the full burden of ultimate liability for the
injuries produced. Alternatively the Government suggests that it is
entitled
Page 397 U. S. 208
to indemnity on a comparative basis to the extent that the
negligence of Seckinger contributed to its employee's injuries.
II
In the posture in which this case reaches us, the historical
background of the clause [
Footnote
9] and evidence concerning the actual intention of these
particular parties with respect to that provision are sparsely
presented. We do know that the clause was required in government
fixed-price construction contracts as early as 1938. [
Footnote 10] This fact merely
precipitates confusion, however, because it was not until the
passage of the Tort Claims Act in 1946, §§ 401-44, 60 Stat. 842, as
amended, 28 U.S.C. §§ 2671-2680, that the United States permitted
recovery in tort against itself for the negligent acts of its
agent. Viewed in the pre-Tort Claims Act context, the purpose of
the clause is totally unclear except, perhaps, as an exercise in
caution on the part of the government draftsmen, or, conceivably,
as an attempt to insulate government agents from liability in their
private capacities if their negligence arguably combined with that
of the contractor to produce a given injury.
In
American Stevedores, Inc. v. Porello, 330 U.
S. 446 (1947), we had before us a contractual provision
that was similar to that involved here. There we noted that
Page 397 U. S. 209
the clause was susceptible of several different constructions,
330 U.S. at
330 U. S.
457-458, and remanded the case to the District Court to
ascertain the intention of the parties with respect to the clause.
It does not appear that a similar course of action would be
fruitful in the instant case. In
Porello, there were clear
indications from the parties that further evidentiary proceedings
in the District Court would shed light on the actual intention of
the parties. [
Footnote 11]
Here, by contrast, there is not only no representation that further
proceedings would aid in clarifying the intentions of the parties,
but there is at least tacit agreement that the background of the
clause has been explored as thoroughly as possible. In these
circumstances, we have no alternative but to proceed directly to
the contractual construction problem.
III
Preliminarily, we agree with the Court of Appeals that federal
law controls the interpretation of the contract.
See United
States v. County of Allegheny, 322 U.
S. 174,
322 U. S. 183
(1944); [
Footnote 12]
Clearfield Trust Co. v. United States, 318 U.
S. 363 (1943). This conclusion results from the fact
that the contract was entered into pursuant to authority
Page 397 U. S. 210
conferred by federal statute and, ultimately, by the
Constitution. [
Footnote
13]
In fashioning a federal rule, we are, of course, guided by the
general principles that have evolved concerning the interpretation
of contractual provisions such as that involved here. Among these
principles is the general maxim that a contract should be construed
most strongly against the drafter, which, in this case, was the
United States. [
Footnote 14]
The Government seeks to circumvent this principle by arguing that
it is inapplicable unless there is ambiguity in the contractual
provisions in dispute and there exists an alternative
interpretation that is, "under all the circumstances, a reasonable
and practical one."
Gelco Builders & Burjay Const. Co. v.
United States, 177 Ct.Cl. 1025, 1035, 369 F.2d 992, 999-1000
(1966). The Government itself, however, has proffered two mutually
inconsistent interpretations of the contract clause. To be sure,
one of them is pressed with considerably more enthusiasm than the
other. The Government, nevertheless, must be taken implicitly to
have
Page 397 U. S. 211
conceded (a) that the clause is not without ambiguity, and (b)
that there is an alternative construction of the clause that is
both "reasonable and practical." Even in the Government's view of
the matter, therefore, there is necessarily room for the
"construction against drafter" principle to operate.
More specifically, we agree with the Court of Appeals that a
contractual provision should not be construed to permit an
indemnitee to recover for his own negligence unless the court is
firmly convinced that such an interpretation reflects the intention
of the parties. This principle, though variously articulated, is
accepted with virtual unanimity among American jurisdictions.
[
Footnote 15] The
Page 397 U. S. 212
traditional reluctance of courts to cast the burden of negligent
actions upon those who were not actually at fault [
Footnote 16] is particularly applicable to
a situation in which there is a vast disparity in bargaining power
and economic resources between the parties, such as exists between
the United States and particular government contractors.
See
United States v. Haskin, 395 F.2d 503, 508 (C.A. 10th
Cir.1968).
In short, if the United States expects to shift the ultimate
responsibility for its negligence to its various contractors, the
mutual intention of the parties to this effect should appear with
clarity from the face of the contract. We can hardly say that this
intention is manifested by the formulation incorporated into the
present contract. [
Footnote
17] By its terms, Seckinger is clearly liable for its
negligence, but the contractual language cannot readily
Page 397 U. S. 213
be stretched to encompass the Government's negligence as well.
[
Footnote 18]
On the other hand, we must not fail to accord appropriate
consideration to Seckinger's clear liability under the contract for
"
all damages" that resulted from its "fault or
negligence." (Emphasis added.) The view adopted by the Court of
Appeals, and now urged by Seckinger, would drain this clause of any
significant meaning or protection for the Government, and, indeed,
would tend to insulate Seckinger from potential liability
Page 397 U. S. 214
in any circumstance in which any negligence is also attributable
to the United States. Whatever may have been the actual intention
of the parties with respect to the meaning of the clause, it is
extremely difficult to believe that they sought to utilize this
contractual provision to reduce Seckinger's potential liability
under common law or statutory rules of contribution or indemnity.
[
Footnote 19] Yet that is
arguably the result if the clause is
Page 397 U. S. 215
interpreted to mean that Seckinger's liability is limited to
situations in which it, as opposed to the United States, is the
sole negligent party.
Furthermore, in this latter situation, it is perfectly clear
that, both before and after the passage of the Tort Claims Act, the
United States could not, in any event, be charged with liability in
the absence of negligence on its part. In short, the construction
of the clause adopted by the Court of Appeals tends to narrow
Seckinger's potential liability, and also limits its application to
circumstances in which no doubt concerning Seckinger's sole
liability existed. In the process, considerable violence is done to
the plain language of the contract that Seckinger be responsible
for all damages resulting from its negligence.
A synthesis of all of the foregoing considerations leads to the
conclusion that the most reasonable construction of the clause is
the alternative suggestion of the Government, that is, that
liability be premised on the basis of comparative negligence.
[
Footnote 20] In the first
place, this interpretation is consistent with the plain language of
the clause, for Seckinger will be required to indemnify the United
States to the full extent that its negligence, if any, contributed
to the injuries to the employee.
Secondly, the principle that indemnification for the
indemnitee's own negligence must be clearly and unequivocally
indicated as the intention of the parties is
Page 397 U. S. 216
preserved intact. In no event will Seckinger be required to
indemnify the United States to the extent that the injuries were
attributable to the negligence, if any, of the United States. In
short, Seckinger will be responsible for the damages caused by its
negligence; similarly, responsibility will fall upon the United
States to the extent that it was negligent.
Finally, our interpretation adheres to the principle that, as
between two reasonable and practical constructions of an ambiguous
contractual provision, such as the two proffered by the Government,
the provision should be construed less favorably to that party
which selected the contractual language. This principle is
appropriately accorded considerable emphasis in this case because
of the Government's vast economic resources and stronger bargaining
position in contract negotiations. [
Footnote 21]
Page 397 U. S. 217
For these reasons, we reverse the judgment of the Court of
Appeals and remand this case to the District Court for further
proceedings consistent with this opinion. [
Footnote 22]
Reversed and remanded.
MR. JUSTICE MARSHALL took no part in the consideration or
decision of this case.
[
Footnote 1]
In the petition for certiorari, the Solicitor General advised
that there are presently pending 200 government suits involving the
same or similar clauses.
[
Footnote 2]
Compare, e.g., Fisher v. United States, 299 F. Supp.
1 (D.C.E.D.Pa.1969), and
United States v. Accrocco,
297 F. Supp. 966 (D.C. D.C.1969),
with, e.g., the decision
of the Court of Appeals in the instant case.
[
Footnote 3]
The third-party complaint was therefore dismissed "with leave to
. . . the United States . . . to the such further action at an
appropriate time." The order was not appealed, and we imply no view
concerning the propriety of the District Court's action.
[
Footnote 4]
The District Court concluded,
inter alia, that the
negligence of the United States was the "sole cause" of the
employee's injuries. We do not pause to consider what effect, if
any, under all the circumstances of this case, the South Carolina
judgment could properly have in the instant case. The effect of the
prior judgment was not raised below except as a defense contention
that it constituted an absolute bar to the instant proceedings.
[
Footnote 5]
Specifically, the United States alleged that Seckinger was
negligent in that it (1) failed to request that the power
distribution line be de-energized; (2) failed to request that the
wires at the place where the accident occurred be insulated; (3)
failed to provide safety insulation on the wires; (4) permitted,
and in fact directed, the subsequently injured employee to work in
close proximity to the wires, and (5) failed to prevent the
employee from proceeding in a manner that was dangerous and that
caused him to be injured.
[
Footnote 6]
The Court of Appeals held that the Government's suit was not
barred by principles of
res judicata, because the South
Carolina District Court expressly left open the option of the
United States to pursue its claim against Seckinger at a later
time. We agree with this conclusion of the Court of Appeals.
[
Footnote 7]
In the present state of the record, we neither accept nor reject
this characterization of the relative degrees of fault of Seckinger
and the United States.
[
Footnote 8]
The Government, therefore, does not take issue with those
authorities that exhibit reluctance to permit a negligent
indemnitee to recover from a faultless indemnitor unless this
intention appeared with particular clarity from the contract.
See, e.g., Associated Engineers, Inc. v. Job, 370 F.2d
633, 651 (C.A. 8th Cir.1966),
cert. denied sub nom. Troy Cannon
Const. Co. v. Job, 389 U.S. 823 (1967).
[
Footnote 9]
In context, the clause in question appears as follows:
"11. PERMITS AND RESPONSIBILITY FOR WORK, ETC."
"The Contractor shall, without additional expense to the
Government, obtain all licenses and permits required for the
prosecution of the work. He shall be responsible for all damages to
persons or property that occur as a result of his fault or
negligence in connection with the prosecution of the work. He shall
also be responsible for all materials delivered and work performed
until completion and final acceptance, except for any completed
unit thereof which theretofore may have been finally accepted."
[
Footnote 10]
See, e.g., 41 CFR §§ 11.1, 11.3, 12.23, Art. 10
(1938).
[
Footnote 11]
The objective of the remand was frustrated when no additional
evidence was presented to the District Court. That court merely
adhered to the construction of the contract that had been adopted
by the Court of Appeals, 153 F.2d 605 (C.A.2d Cir.1946), namely,
that the United states was entitled to full indemnity from a
stevedoring contractor although both the United States and the
contractor were found to have been negligent.
Porello v. United
States, 94 F. Supp.
952 (D.C.S.D.N.Y.1950).
[
Footnote 12]
"The validity and construction of contracts through which the
United States is exercising its constitutional functions, their
consequences on the rights and obligations of the parties, the
titles or liens which they create or permit, all present questions
of federal law not controlled by the law of any State."
322 U.S. at
322 U. S.
183.
[
Footnote 13]
Congress has provided extensive arrangements for the
procurement, management, and disposal of government property.
See generally 40 U.S.C. §§ 471-535 (1964 ed. and Supp.
IV). As part of this statutory scheme, the Administrator of General
Services is authorized to issue regulations necessary to perform
his various managerial functions. 40 U.S.C. § 486(c). Pursuant to
this authority, various form contracts, one of which includes the
provision that is the subject of this suit, have been promulgated
for official use. 41 CFR §§ 1-16.401 to 1-16.404, 1-16.901-23A,
Art. 12 (1969).
See generally State Bar of California,
Committee on Continuing Education of the Bar, Government Contracts
Practice § 13.93 (1964).
[
Footnote 14]
See, e.g., Sternberger v. United States, 185 Ct.Cl.
528, 543, 401 F.2d 1012, 1021 (1968);
Sun Shipbuilding &
Drydock Co. v. United States, 183 Ct.Ch. 358, 372, 393 F.2d
807, 816 (1968);
Jones v. United States, 304 F. Supp. 94,
103 (D.C.S.D.N.Y.1969).
[
Footnote 15]
A number of courts take the view, frequently in a context in
which the indemnitee was solely or principally responsible for the
damages, that there can be indemnification for the indemnitee's
negligence only if this intention is explicitly stated in the
contract.
See, e.g., Freed v. Great A. & P. Tea Co.,
401 F.2d 266 (C.A. 6th Cir.1968) (intention of parties must be
"clear and unambiguous" necessitating a clause such as "including
damage from indemnitee's own negligence");
Brogdon v. Southern
R. Co., 384 F.2d 220 (C.A. 6th Cir.197) (same);
City of
Beaumont v. Graham, 441 S.W.2d 829
(Tex.1969) (indemnitor's promise to indemnify for his negligent
acts does not extend to indemnification for indemnitee's
negligence);
Young v. Anaconda American Brass Co., 43
Wis.2d 36,
168 N.W.2d
112 (1969) (indemnitor not liable for such portion of total
liability attributable to act of indemnitee unless indemnity
contract by express provision and strict construction so provides);
cases collected in Annot., 175 A.L.R. 8, 29-38 (1948).
Other cases do not require that indemnification for the
indemnitee's negligence be specifically or expressly stated in the
contract if this intention otherwise appears with clarity.
See,
e.g., Auto Owners Mut. Ins. Co. v. Northern Ind.Pub. Serv.
Co., 414 F.2d 192 (C.A. 7th Cir.1969);
Eastern Gas &
Fuel Associates v. Midwest-Raleigh, Inc., 374 F.2d 451
(C.A.4th Cir.1967);
Unitec Corp. v. Beatty Safway Scaffold
Co., 35 F.2d 470 (C.A. 9th Cir.1966);
Batson-Cook Co. v.
Industrial Steel Erectors, 257 F.2d 410 (C.A. 5th
Cir.1958).
[
Footnote 16]
Several earlier cases declared clauses that purported to
indemnify for the indemnitee's negligence void as contrary to
public policy.
See, e.g., Sternaman v. Metropolitan Life Ins.
Co., 170 N.Y. 13, 62 N.E. 763 (1902);
Johnson's
Administratrix v. Richmond & D. R. Co., 86 Va. 975, 11
S.E. 829 (1890).
See also Bisso v. Inland Waterways Corp.,
349 U. S. 85
(1955);
Otis Elevator Co. v. Maryland Cas. Co., 95 Colo.
99, 33 P.2d 974 (1934).
[
Footnote 17]
An example of an indemnification clause that makes specific
reference to the effect of the negligence of the indemnitee is the
following recommendation of the American Institute of
Architects:
"4.18. INDEMNIFICATION "
"4.18.1. The Contractor shall indemnify and hold harmless the
Owner and the Architect and their agents and employees from and
against all claims, damages, losses and expenses including
attorneys' fees arising out of or resulting from the performance of
the Work, provided that any such claim, damage, loss or expense (a)
is attributable to bodily injury, sickness, disease or death, or to
injury to or destruction of tangible property (other than the Work
itself) including the loss of use resulting therefrom, and (b) is
caused in whole or in part by any negligent act or omission of the
Contractor, any Subcontractor, anyone directly or indirectly
employed by any of them or anyone for whose acts any of them may be
liable, regardless of whether or not it is caused in part by a
party indemnified hereunder."
AIA Document A 201, Sept.1967.
We specifically decline to hold that a clause that is intended
to encompass indemnification for the indemnitee's negligence must
include an "indemnify and hold harmless" clause, or that it must
explicitly state that indemnification extends to injuries
occasioned by the indemnitee's negligence. Thus, contrary to the
view apparently adopted in the dissenting opinion, we assign no
talismanic significance to the absence of a "hold harmless" clause.
Our approach is, in this respect, consistent with
American
Stevedores, Inc. v. Porello, 330 U.S. at
330 U. S.
457-458. Contract interpretation is largely an
individualized process, with the conclusion in a particular case
turning on the particular language used against the background of
other indicia of the parties' intention. Consequently, we hold only
that, in this case, the clause that provides that Seckinger will be
responsible for all damages resulting from its negligence is
insufficiently broad to encompass responsibility for injuries
resulting from the negligence of the Government. And, of course,
the Government is entitled to no recovery unless it establishes
that Seckinger was negligent. Thus, the dissenting opinion
mischaracterizes the scope of our holding when it states that
Seckinger must "reimburse the Government for losses it incurs
resulting from its negligence."
[
Footnote 18]
See, e.g., United States v. Haskin, 395 F.2d 503 (C.A.
10th Cir.1968);
Brogdon v. Southern R. Co., 384 F.2d 220
(C.A. 6th Cir.1967);
Shamrock Towing Co. v. City of New
York, 16 F.2d 199 (C.A.2d Cir.1926);
Williams v. Midland
Constructors, 221 F.
Supp. 400 (D.C.E.D. Ark.1963);
City of Beaumont v.
Graham, 441 S.W.2d 829
(Tex.1969);
Young v. Anaconda American Brass Co., 43
Wis.2d 36,
168 N.W.2d
112 (1969).
[
Footnote 19]
An employer's liability for injuries suffered by his employees
to which his negligence partially contributed varies from
jurisdiction to jurisdiction. In the absence of workmen's
compensation statutes, the employer and the third-party tortfeasor
would be jointly and severally liable, under traditional
principles, for the injuries produced. In a majority of
jurisdictions, contribution or indemnity is available either by
statute or common law, as a device for the redistribution of the
burden among the joint tortfeasors.
See generally W.
Prosser, Law of Tort.s §§ 47, 4 (3d ed.1964). In 1956, when
Seckinger's employee was injured, South Carolina law was unclear in
this respect, apparently permitting contribution or indemnity under
some circumstances.
See generally Comment, Indemnity Among
Joint Tort-Feasors As Affected by the Federal Employers Liability
Act, 17 S.C. L.Rev. 423 (1965).
Workmen's compensation provisions, now enacted in all States,
have considerable effect on the employer's potential liability to
the third-party tortfeasor. However, these statutes vary greatly in
the categories of employers and employees to which they apply,
see generally A. Reede, Adequacy of Workmen's Compensation
(1947), and, even today, about two-thirds of the statutes provide
that coverage is voluntary as to both employers and employees. 2 A.
Larson, The Law of Workmen's Compensation § 67.10 (1969).
When a workmen's compensation plan does cover particular
employers and employees, a third-party suit against an employer who
was also negligent is barred by the majority rule, although
recovery is not infrequently permitted on implied or
quasi-contractual theories.
See, e.g., Associated
Engineers, Inc. v. Job, 370 F.2d 633, 651 (C.A. 8th Cir.1966);
2 A. Larson,
supra, §§ 76.00-76.53. Whether such a suit is
permitted under South Carolina law apparently has not been
authoritatively determined.
See generally Burns v. Carolina
Power & Light Co., 88 F. Supp.
769 (D.C.E.D. S.C.1950).
[
Footnote 20]
A number of courts have reached comparable results.
See,
e.g., Brogdon v. Southern R. Co., 384 F.2d 220 (C.A. 6th Cir.
1967);
Williams v. Midland Constructors, 221 F.
Supp. 400 (D.C.E.D.Ark.1963);
C & L Rural Elec. Coop.
Corp. v. Kincaid, 221 Ark. 450,
256 S.W.2d
337 (1953),
after remand, 227 Ark. 321,
299 S.W.2d
67 (1957);
Young v. Anaconda American Brass Co., 43
Wis.2d 36,
168 N.W.2d
112 (1969).
See also United States v. Haskin, 395 F.2d
503 (C.A. 10th Cir.1968);
Shamrock Towing Co. v. City of New
York, 16 F.2d 199 (C.A.2d Cir.1926).
[
Footnote 21]
While it is true that the interpretation adopted by the Court of
Appeals is even less favorable to the Government than that which we
adopt, we have concluded, for reasons previously stated, that the
Court of Appeals' view would drain the clause of any significant
meaning, and is decidedly contrary to its plain language.
A 1941 letter from the Comptroller General, 21 Comp.Gen. 149,
relied upon in dissent, sheds no light whatever on the problem of
contract construction before us. There, the Comptroller General, in
commenting upon a question that he said was "of first impression,"
suggested that, under some circumstances, a contractor under a
cost-plus-fixed fee contract may seek reimbursement from the
Government, as an element of his actual costs, for damages that he
sustained by reason of his negligence. Since the contract clause in
question was introduced long before the 1941 letter, it obviously
was not responsive to any issues raised by the Comptroller.
Moreover, we deal in this case with a fixed-price construction
contract, a type of contract with which the Comptroller General was
in no way concerned. Thus, no support is provided for the facile
assumption of the dissent that, merely because a cost-plus
contractor may arguably seek reimbursement for additional costs
produced by his own negligence, it follows that a contractor
committed to complete a project for a fixed price also may seek
reimbursement because of damage caused by his own negligent
acts.
We agree with the dissenting opinion that the contract clause
does mean exactly what it says. What it says is that Seckinger
shall be "responsible for all damages" arising from its negligence,
that is, that the burden of Seckinger's negligence may not be
shifted to the United States. To be sure, the clause bars any
attempt by Seckinger to obtain reimbursement from the Government
for Seckinger's negligence. But an interpretation that limited the
operation of the clause to this narrow situation would constitute
an impermissible frustration of the contractual scheme, for such a
construction would shift the burden of Seckinger's negligence to
the United States through the medium of a recovery against the
Government by the injured employee. The contractual objective --
that liability for the contractor's negligence not be shifted to
the United States -- can be achieved in cases of concurrent
negligence when there has been a prior recovery against the
Government only by resort to the comparative negligence analysis
that we have adopted, which requires Seckinger to indemnify the
Government, but only to the extent that the Government was called
upon, in the first instance, to respond in damages as a result of
Seckinger's negligence.
[
Footnote 22]
Because we have taken the view that the rights and liabilities
of Seckinger and the United States
inter sese are governed
by contract, we need not reach the Government's alternative theory,
rejected by the Court of Appeals, that Seckinger breached an
implied warranty of workmanlike service.
MR. JUSTICE STEWART, with whom THE CHIEF JUSTICE and MR.
JUSTICE; DOUGLAS joins, dissenting.
The standard form that the Government uses for its fixed-price
construction contracts has long contained a single sentence saying
that the contractor
"shall be responsible
Page 397 U. S. 218
for all damages to persons or property that occur as a result of
his fault or negligence in connection with the prosecution of the
work. [
Footnote 2/1]"
For more than 30 years, it has evidently been understood that
these words mean what they rather clearly say -- that the
contractor cannot hold the Government for losses he incurs
resulting from his own negligence. [
Footnote 2/2] The provision, in short, is what the Court
of Appeals called "a simple responsibility clause." 408 F.2d 146,
148. [
Footnote 2/3] But today this
innocuous boilerplate language is turned inside out. For the Court
says that the provision really is a promise by the contractor to
reimburse the Government for losses it incurs resulting from
its negligence.
To be sure, the Court does not go quite so far as to hold that
this obscure clause operates as a complete liability insurance
policy. But the Court does hold that the clause requires the
contractor to indemnify the Government "to the full extent that its
negligence, if any, contributed to the injuries to the employee."
The magnitude of the burden the Court imposes is well
illustrated
Page 397 U. S. 219
by the circumstances of this case. Here, an employee of the
contractor was injured in the scope of his employment on plumbing
work that the contractor was performing at the Paris Island Marine
Depot in South Carolina. The employee recovered from the contractor
the benefits to which he was entitled under the state workmen's
compensation law. The employee then sued the Government under the
Federal Tort Claims Act, claiming that his injuries had actually
been caused by the Government's negligence. The Federal District
Court agreed, finding that the negligence of the United States was
the "sole cause" of the employee's injuries and awarding him
$45,000 in damages. The Court today says that the United States can
now recover an indeterminate portion of this $45,000 from the
contractor, because the contractor has agreed to "indemnify the
United States. . . ."
Despite intimations in the Court's opinion to the contrary, we
do not deal here with "common law or statutory rules of
contribution or indemnity." [
Footnote
2/4] The only question the Court decides is the meaning of the
words of a clause in a government contract. [
Footnote 2/5] I think the
Page 397 U. S. 220
meaning attributed to that clause today is as unconscionable as
it is inaccurate.
The clause first appeared in government contracts at least eight
years before the enactment of the Federal Tort Claims Act in 1946.
Before the passage of that Act, the United States could not be sued
in tort for personal injuries. Thus, there was absolutely no reason
for the Government to secure for itself a right to recovery over
against an alleged joint tortfeasor. Yet we are asked to believe
that the drafter of this clause was so prescient as to foresee the
day of government tort liability nearly a decade in the future, and
so ingenious as to smuggle a provision into a standard contract
form that would, when that day arrived, allow the Government to
shift its liability onto the backs of its contractors. This theory
is nothing short of incredible.
In drafting its construction contracts, the United States
certainly has both the power and the resources to write contracts
providing expressly that it will pass off onto its contractors,
either in whole or in part, liability it incurs for damages caused
by its own judicially determined negligence. The Government could
require its contractors to hold it harmless without regard to fault
on their part, or it could establish a proration of liability
arising from the joint negligence of the parties. But the
contractual provision before us does neither. It no more says that
the contractor shall reimburse the Government for his share of
joint negligence than that he shall be a liability insurer for the
Government's sole negligence.
Page 397 U. S. 221
The Court nonetheless manages to discover that the clause
amounts to a contribution agreement, relying for its conclusion
upon cases involving not the simple responsibility clause before
us, but express indemnification agreements with "hold harmless"
clauses. [
Footnote 2/6] This result
is said to be desirable because it ensures a fair distribution of
loss between those jointly responsible for the damage. But when
Seckinger entered into this contract, it had every reason to expect
that its liability for injuries to its employees would be limited
to what is imposed by the South Carolina compensation law. That law
relieved it of responsibility in tort in exchange for its guarantee
that its employees would recover without regard to fault.
Presumably its bid on the government project reflected its
reasonable expectation that this would be the extent of its
liability on account of employee accidents. Now the Court heaps an
unforeseen federal contractual burden atop the requirement the
State has already imposed. [
Footnote
2/7]
If the Government wants to impose additional liabilities upon
those with whom it contracts to do its work, I would require it to
do so openly, so that every bidder may clearly know the extent of
his potential liability. Even in the domain of private contract
law, the author of a standard-form agreement is required to state
its terms with clarity and candor. [
Footnote 2/8] Surely no less is required
Page 397 U. S. 222
of the United States of America when it does business with its
citizens. [
Footnote 2/9]
Mr. Justice Holmes once said that "[m]en must turn square
corners when they deal with the Government." [
Footnote 2/10] I had always supposed this was a
two-way street. The Government knows how to write an
indemnification or contribution clause when that is what it wants.
It has not written one here.
I would affirm the judgment.
[
Footnote 2/1]
This sentence is contained in a paragraph entitled "Permits and
Responsibility for Work, etc."
See ante at
397 U. S. 208
n. 9.
[
Footnote 2/2]
I have found no previous reported decision construing this
clause as the Court construes it today.
[
Footnote 2/3]
It will not do to say, as the Court says today, that this
construction of the clause makes its purpose "totally unclear," or
"would drain this clause of any significant meaning or protection
for the Government. . . ." For, without such a clause, there would
surely be room for the contractor to claim reimbursement from the
Government for unforeseen increased costs incurred on account of
his negligence, particularly where the Government was jointly
negligent. With respect to contracts not containing such a clause
-- cost-plus contracts, for example, -- the Comptroller General
advised the Secretary of War almost 30 years ago that the
Government may, indeed, be liable to the contractor under such
circumstances.
See 21 Comp.Gen. 149, 156-157 (1941).
[
Footnote 2/4]
Under the law of South Carolina -- which determines the
Government's liability in tort. to the injured employee, 28 U.S.C.
§ 1346(b);
Richards . United States, 369 U. S.
1 -- the general rule is that there is no right to
contribution among joint tortfeasors.
Atlantic Coast Line R.
Co. v. Whetstone, 243 S.C. 61, 68-70,
132
S.E.2d 172, 175-176. Moreover, since the injured employee has
accepted his award against Seckinger under the state workmen's
compensation statute, he cannot hold Seckinger in tort. S.C.Code
Ann. §§ 72-121, 72-123 (1962);
Adams v. Davison-Paxon Co.,
230 S.C. 532, 545,
96 S.E.2d
566, 572-573. So Seckinger can hardly be cast in the role of a
tortfeasor in any event.
[
Footnote 2/5]
The Court's conclusion that the Court of Appeals' construction
of the clause might "reduce Seckinger's potential liability under
common law or statutory rules of contribution or indemnity" seems
wholly incorrect. The contractor's agreement not to seek
reimbursement or contribution from the Government would have no
bearing upon the question whether local "common law or statutory
rules of contribution and indemnity" give the Government any right
to recover from the contractor.
[
Footnote 2/6]
These cases are cited in the Court's opinion,
ante at
397 U. S. 215
n. 20.
[
Footnote 2/7]
Under South Carolina law, Seckinger has been subrogated to its
injured employee's claim against the United States to the extent of
its own compensation payment. S.C.Code Ann. § 72-124 (1962). But
the Court today subjects Seckinger to the incremental risk of
liability in contribution, in a yet-to-be-determined proportion,
for the employee's added recovery in his tort suit against the
Government.
[
Footnote 2/8]
E.g., Chrysler Corp. v. Hanover Ins. Co., 350 F.2d 652,
655;
Riess v. Murchison, 329 F.2d 635, 642; Restatement of
Contracts § 235(e); 3 A. Corbin on Contracts § 559 (1960).
[
Footnote 2/9]
Sternberger v. United States, 185 Ct.Cl. 528, 543, 401
F.2d 1012, 1021; Jones v. United States, 304 F. Supp. 94, 101.
[
Footnote 2/10]
Rock Island, A. & L. R. Co. v. United States,
254 U. S. 141,
254 U. S. 143.