In re MacIntyre Fuels, Inc.

Annotate this Case
In re MacIntyre Fuels, Inc. (2002-272); 175 Vt. 613; 833 A.2d 829

2003 VT 59

[Filed 30-Jun-2003]

                                 ENTRY ORDER

                                 2003 VT 59

                      SUPREME COURT DOCKET NO. 2002-272

                              APRIL TERM, 2003

  In re MacIntyre Fuels, Inc.	       }	APPEALED FROM:
  Vermont Agency of Transportation     }
                                       }
       	                               }	Environmental Board
                                       }	
                                       }
                                       }	DOCKET NO. D.R. Request #402


             In the above-entitled cause, the Clerk will enter:

       ¶  1.  MacIntyre Fuels, Inc., a Vermont corporation engaged in the
  business of transporting and selling petroleum products, appeals from the
  Environmental Board's assumption of Act 250 jurisdiction over the company's
  proposed project to construct an intermodal fuel transfer facility on a
  spur line adjacent to the main railway line in Montpelier.  We conclude
  that the Board erred in determining that the project is subject to Act 250
  jurisdiction under the 1994 rail siding amendment to 10 V.S.A. § 6001(3). 
  We concur, however, with the Board's determination that MacIntyre's project
  requires an amendment to an existing permit for part of the land upon which
  the project is located.  Accordingly, the matter is remanded for further
  consideration consistent with this opinion.

       ¶  2.  In October 2001, MacIntyre obtained site plan approval from
  the City of Montpelier to construct a facility that would allow the
  transfer of petroleum products from railroad cars to trucks for local
  delivery.  At the time, MacIntyre operated a network of similar facilities
  in Vermont and New Hampshire.  The proposed project required the relocation
  of existing track, the laying of a spur line adjacent to the main track,
  and the installation of a system of fuel tanks, pipes, and pumping
  equipment.  The project also called for the construction of a 30' x 36'
  canopy and the upgrading of an existing gravel driveway leading into the
  railroad yard.  MacIntyre was to construct the project on land that it
  leased from the railroad.  Most of that property, in turn, had been leased
  by the railroad from the State of Vermont.  A small strip of land (40' x
  100') on which the project was to be located, however, had been leased by
  the railroad from a neighboring property owner, Patrick Malone, under a
  reciprocal lease agreement.  Apparently, that strip of land was needed to
  accommodate the canopy and a turnaround area.  In its entirety, the project
  would physically alter approximately 58,000 square feet, or less than two
  acres of land.
   
       ¶  3.  In the fall of 2001, MacIntyre sought a declaratory ruling
  from the district 5 environmental coordinator that an Act 250 land-use
  permit was not needed for the project.  State officials with the Agency of
  Transportation supported MacIntyre's position that the project was outside
  of Act 250 jurisdiction.  That position was based on a 1994 amendment to 10
  V.S.A. § 6001(3) that resulted from an earlier decision by another district
  coordinator requiring an Act 250 permit for a similar railroad project. 
  The district coordinator in the earlier case determined that an Act 250
  permit was needed because, although the project itself would physically
  alter only a few acres, the railroad line serving the proposed facility
  comprised more than ten acres.  The ruling was based on § 6001(3), which
  defines "Development," in relevant part, as the "construction of
  improvements on a tract or tracts of land, owned or controlled by a person,
  involving more than 10 acres of land within a radius of five miles of any
  point on any involved land, for commercial or industrial purposes."  In
  response to this ruling, the Railroad Association of Vermont took its case
  to the Legislature, which then amended § 6001(3) by adding the following
  sentences:

    In the case of a project undertaken by a railroad, no portion of a
    railroad line or railroad right-of-way that will not be physically
    altered as part of the project shall be included in computing the
    amount of land involved.  In the case of a project undertaken by a
    person to construct a rail line or rail siding to connect to a
    railroad's line or right-of-way, only the land used for the rail
    line or rail siding that will be physically altered as part of the
    project shall be included in computing the amount of the land
    involved.

  1993, No. 200 (Adj. Sess.), § 1 (currently codified at 10 V.S.A. §
  6001(3)(c)(iv)).

       ¶  4.  Notwithstanding this amendment and the Agency of
  Transportation's support for MacIntyre's position, the district coordinator
  in the present case concluded in her November 9, 2001 jurisdictional
  opinion that MacIntyre was required to obtain an Act 250 permit.  She found
  Act 250 jurisdiction by including as involved land the entire
  fourteen-mile-long railroad right of way running from Montpelier to
  Graniteville.  In her view, the 1994 amendment did not apply because the
  project entailed more than just constructing a spur track.  She further
  concluded that, even if the railroad right of way was not considered as one
  contiguous property for jurisdictional purposes, the entire Malone
  property, approximately 100 acres, would have to be considered as involved
  land because a small part of the project was located on that property.
   
       ¶  5.  MacIntyre appealed the district coordinator's decision to the
  Environmental Board and submitted a statement of stipulated facts, which
  was joined by the Agencies of Transportation and Natural Resources.  The
  Board held a hearing on April 17, 2002, but no oral argument took place
  because MacIntyre's position was unopposed.  Instead, Board members
  directed questions to MacIntyre's attorney.  On May 21, 2002, the Board
  issued its decision upholding the district coordinator's ruling that the
  proposed project required an Act 250 permit.  The Board concluded that
  because MacIntyre was not a railroad, and because components of the
  proposed project were neither rail lines nor rail sidings, the land to be
  considered in determining Act 250 jurisdiction was all contiguous parcels -
  including the fourteen-mile railroad right of way and the entire Malone
  parcel - and not merely the two acres or so that was to be physically
  altered.  On appeal to this Court, MacIntyre argues that (1) certain Board
  findings are clearly erroneous; (2) the Board erred in concluding that the
  1994 amendment to § 6001(3) exempted only that portion of the proposed
  project involving the laying of track; and (3) with respect to both the
  railroad right of way and the Malone property, the Board should have
  considered only the land that was to be physically altered in determining
  whether an Act 250 permit was required.

       ¶  6.  Because we need not address MacIntyre's challenge to certain
  Board findings to resolve this appeal, we move directly to the central
  question in this case: Did the Board err in concluding that the 1994
  amendment to § 6001(3) exempts from Act 250 review only the component of a
  proposed project involving the laying of track - and not the construction
  of attendant facilities - when the project is undertaken by someone other
  than a railroad?  MacIntyre argues that the phrase "project undertaken by a
  person to construct a rail line or rail siding to connect to a railroad's
  line or right-of-way" should not and cannot be construed as exempting only
  the track component of proposed rail siding projects.  To do so, it argues,
  would effectively negate the amendment because tracks are never built
  without attendant facilities, and would undermine the purpose of the
  legislation to put shippers transporting goods by rail on equal footing
  with shippers transporting goods by highway.  In response, the State argues
  that the term "rail siding" has a narrow, technical meaning that refers
  only to the track itself and cannot be expanded to cover attendant
  facilities.

       ¶  7.  Although we generally defer to the Board's interpretation of
  Act 250 and its "special expertise in determining whether it has
  jurisdiction over a particular development," In re Stokes Communications
  Corp., 164 Vt. 30, 35, 664 A.2d 712, 715 (1995), we do not abdicate our
  responsibility to examine a disputed statute independently and ultimately
  determine its meaning.  When interpreting a statute, our fundamental
  objective is to discern and implement the intent of the Legislature.  See
  Green Mountain Power Corp. v. Sprint Communications, 172 Vt. 416, 420, 779 A.2d 687, 691 (2001); Perry v. Med. Practice Bd., 169 Vt. 399, 406, 737 A.2d 900, 905 (1999).  If the statutory language is absolutely clear and
  unambiguous, we generally restrict ourselves to the plain meaning of that
  language, but if any question remains as to the intent underlying the
  statute, we also look at "the legislative history and circumstances
  surrounding its enactment, and the legislative policy it was designed to
  implement."  Perry, 169 Vt. at 406, 737 A.2d  at 905.  Indeed, if "the plain
  meaning of statutory language appears to undermine the purpose of the
  statute, we are not confined to a literal interpretation, but rather must
  look to the broad subject matter of the statute, its effects and
  consequences, and the purpose and spirit of the law to determine
  legislative intent."  Town of Killington v. State, 172 Vt. 182, 189, 776 A.2d 395, 401 (2001); see Lubinsky v. Fair Haven Zoning Bd., 148 Vt. 47,
  49-50, 527 A.2d 227, 228 (1986) ("the letter of a statute or its literal
  sense must yield where it conflicts with legislative purpose"); State v.
  Baldwin, 140 Vt. 501, 510-11, 438 A.2d 1135, 1140 (1981) (plain meaning
  rule is merely legal truism that may be disregarded to carry out
  legislative intent).

        
       ¶  8.  Here, the State has failed to demonstrate that the meaning of
  the term "rail siding," particularly in the context of this statutory
  provision, is so clear that we may not examine legislative history for
  insight as to its intended meaning.  As noted, the 1994 amendment was
  enacted directly in response to the assumption of Act 250 jurisdiction over
  a project that was nearly identical to the one proposed here.  In asserting
  Act 250 jurisdiction in this case, the Board relied upon the distinction in
  the 1994 amendment between projects undertaken by "a railroad" and those
  undertaken by "a person."  10 V.S.A. § 6001(3)(c)(iv).  With respect to "a
  person," the statute exempts from Act 250 only those projects that
  "construct a rail line or rail siding to connect to a railroad's line or
  right-of-way."  Id.  This language creates a legitimate ambiguity as to
  whether the Legislature intended to exempt all aspects of rail siding
  projects, with emphasis on the word "project," or only the track component
  of such projects.

       ¶  9.  Our review of the committee hearings on the bill amending §
  6001(3), H. 575, reveals that the second sentence of the amendment was
  intended to exempt all components of rail siding projects, including both
  the laying of track and the construction of attendant facilities.  The bill
  started in the House Transportation Committee and then was transferred to
  the House Natural Resources and Energy Committee.  At the initial
  Transportation Committee hearing on February 23, 1994, a railroad
  representative appeared and testified that the purpose of the proposed
  amendment was to put the railroads on equal footing with the trucking
  industry with respect to what type of projects required Act 250 permits. 
  The representative explained that the recent ruling of the district
  coordinator including the railroad right of way as part of the involved
  land in a proposed fuel transfer project meant that any time anybody wanted
  to put a spur and facility adjacent to a rail line, that person would have
  to obtain an Act 250 permit, notwithstanding the scope of the project.  The
  representative indicated that the proposed statutory language, which was
  identical to the language eventually enacted into law, had been drafted by
  an attorney representing the railroad industry.

       ¶  10.  At the initial hearing before the House Natural Resources and
  Energy Committee on March 10, 1994, an attorney for the Railroad
  Association of Vermont testified that the purpose of the second sentence of
  the proposed amendment was that

    if you've got somebody who proposes to ship or receive materials
    by rail, and wants to construct a facility to make that possible -
    a rail siding or a spur line, I guess, in common parlance - that
    only requires an Act 250 permit if the actual project is going to
    physically affect ten acres or more. . . .  But what you don't do
    in that case is aggregate that potential shipper's entire parcel.

  The attorney explained that a shipper proposing a project adjacent to the
  rail line should not have to obtain an Act 250 permit simply because
  inclusion of the railroad right of way pushes the project over the ten-acre
  limit.  Doing so, according to the attorney, would have the effect of
  discouraging connections to rail and favoring the highway industry.  The
  attorney emphasized that the second sentence concerned shippers who wanted
  to construct a spur line or siding so that they could be serviced by the
  railroad.  In response to queries from committee members, Michael Zahner,
  the Environmental Board administrator at the time, testified that it was
  really a policy question as to whether the Legislature wanted to treat
  railroads and highways the same.  He noted that there would be "land-based
  environmental impacts that are associated with the activity . . . occurring
  at the siding, whether it's a fuel depot or whatever."  He emphasized that
  most of those concerns would be addressed through local zoning, but noted
  that Act 250 review is generally more comprehensive.  As he saw it, the
  issue was whether the Legislature, as a matter of policy, was willing to
  forego that more comprehensive review in these circumstances.
          
       ¶  11.  At a follow-up hearing the next day before the same
  committee, the committee chair stated his understanding of the second
  sentence of the proposed amendment as follows:

    So if I need to buy some land to build a siding to connect to the
    rail line, that land is involved land.  And any land that I'm
    developing for my warehouse or tank, farm, or furniture factory
    also would be involved land.  But not the railroad right of way.

  As the chair explained, under the second sentence of the proposed
  amendment, persons would not be encumbered by counting all of the land
  involved in the railroad right of way.  Rather, "just the rail siting
  acreage and whatever acreage that's associated with their project" would be
  counted - the same as if the person was locating a business near a highway. 
  At a later hearing held before the committee, the chair stated that the
  "crux" of the proposed amendment was that we would "not be calculating the
  main rail lines every time you have an adjacent project by the railroads or
  any of their customers."
   
       ¶  12.  The proposed statutory language presented to the committees
  remained exactly the same through enactment of the amendment into law. 
  Apparently, however, the statements of the committee members and those that
  testified before the committee were not made part of a written report
  distributed to all of the members of the Legislature.  Thus, they are
  certainly not conclusive as to what the disputed statutory language means. 
  Nonetheless, the common understanding of those concerned at the committee
  hearings, including the Environmental Board administrator, suggests that
  the Legislature intended the second sentence of the amendment to exempt
  rail siding projects - including those components of the projects that go
  beyond the mere laying of track.  Cf. Bd. of County Comm'rs, Clark County
  v. White, 729 P.2d 1347, 1350 (Nev. 1986) ("When a statute is of doubtful
  import and subject to opposite meanings, limited resort may be had to
  testimony and committee discussions concerning the legislation in
  question.").  Accordingly, we hold that the Board erred in including the
  fourteen-mile railroad right of way as part of the involved land in
  MacIntyre's proposed rail siding project.

       ¶  13.  One remaining problem, however, is that a small part of
  MacIntyre's project is on a private parcel leased by the railroad from
  Malone and subject to an Act 250 permit.  MacIntyre invites this Court to
  adopt a rule whereby Act 250 jurisdiction would be triggered only if the
  proposed use in cases such as this violated any of the permit conditions on
  the private land, and then to review the conditions of the Malone Act 250
  permit to determine whether the proposed project would violate any of those
  conditions.  The State responds that MacIntyre has waived this argument by
  stating in its initial stipulation of facts that it intended to join the
  owner of the Malone property in applying for an amendment to the Malone
  permit.
   
       ¶  14.    We agree with the State, and therefore decline to address
  MacIntyre's arguments concerning the Malone property.  The Board issued a
  prehearing conference report and order on February 28, 2002 establishing a
  schedule for the proceeding before it.  Pursuant to that order, within the
  next month MacIntyre and the state agencies submitted a stipulation of
  facts in which they waived an evidentiary hearing.  In so doing, they
  stated that the stipulation covered all relevant facts, and that no
  relevant fact was in dispute.  Regarding the Malone property, the
  stipulation indicated that MacIntyre intended to join the owner of the
  property in applying for an amendment to the existing Act 250 permit that
  would allow the activities contemplated for the property under MacIntyre's
  proposed project.  Later, beyond the deadline set forth in the Board's
  prehearing order, MacIntyre and the state agencies submitted a supplemental
  statement of stipulated facts and exhibits concerning the Malone property
  and its Act 250 permit.  MacIntyre also proposed conclusions suggesting
  that no Act 250 permit was needed because none of the proposed activities
  on the Malone property violated any of the conditions of the Malone permit,
  but, at the same time, reiterated its intent to seek an amendment of the
  Malone permit.

       ¶  15.  In its May 21, 2002 decision, the Board declined to consider
  the supplemental stipulation of facts and exhibits because they were not
  authorized under the prehearing order, and because the parties waived the
  right to an evidentiary hearing based on the original stipulation of facts. 
  Here, on appeal, MacIntyre has failed to demonstrate, or even argue, that
  the Board abused its discretion in refusing to consider the supplemental
  stipulation of facts and exhibits.  Therefore, we agree with the State and
  the Board that MacIntyre has waived its right to challenge the Board's
  ruling with respect to the Malone property.  For MacIntyre to proceed with
  its proposed project, it will first have to obtain an amendment to the
  Malone permit.

       The Environmental Board's May 21, 2002 order is reversed in part and
  affirmed in part, and the matter is remanded for further consideration
  consistent with this opinion.  



                                       BY THE COURT:


                                       _______________________________________
                                       Jeffrey L. Amestoy, Chief Justice

                                       _______________________________________
                                       Denise R. Johnson, Associate Justice

                                       _______________________________________
                                       Marilyn S. Skoglund, Associate Justice

                                       _______________________________________
                                       Frederic W. Allen, Chief Justice (Ret.)
                                        Specially Assigned

                                       _______________________________________
                                       Ernest W. Gibson, III, Associate Justice
                                        (Ret.) Specially Assigned



Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.