Appeal of Coastal Resources Com'n

Annotate this Case

386 S.E.2d 92 (1989)

96 N.C. App. 468

In the Matter of Appeal of COASTAL RESOURCES COMMISSION Decision against North Topsail Water and Sewer, Inc.

No. 894SC193.

Court of Appeals of North Carolina.

December 5, 1989.

*93 Atty. Gen. Lacy H. Thornburg by Asst. Atty. Gen. Robin W. Smith, Raleigh, for respondent-appellant, N.C. Coastal Resources Com'n.

Lanier & Fountain by Gordon E. Robinson, Jr., Jacksonville, for petitioner-appellee.

JOHNSON, Judge.

In 1982, Marlow F. Bostic, president of North Topsail Water and Sewer, Inc. (petitioner), applied to the North Carolina Division of Environmental Management (DEM) for a permit to construct a spray irrigation wastewater treatment facility on a tract of land east of Highway 210 and adjacent to two tributaries of Mill Creek in Onslow County.

Mill Creek and its tributaries are seaward of the dividing line between inland and coastal waters and therefore constitute "estuarine waters" for purposes of the Coastal Area Management Act (CAMA). CAMA permits are required for any "development," as defined in G.S. sec. 113A-103, in estuarine waters or within 75 feet of estuarine waters. The permit application submitted by petitioner to DEM did not show any development activity in the northwest tributary or within 75 feet of the tributary the area subject to CAMA jurisdiction. DEM issued petitioner a permit for the treatment facility on May 11, 1982.

In 1983, petitioner began clearing, grading and filling on the three hundred acre site. In preparing the site, petitioner excavated four drainage ditches although no drainage ditches had been depicted on the development plan submitted by petitioner to DEM for review.

In late fall or early winter of 1983, petitioner also excavated the bed of the northwest tributary with a backhoe. No excavation in the tributary had been depicted on the development plan submitted by petitioner to the DEM and petitioner did not obtain a CAMA permit prior to undertaking the excavation.

On December 19, 1983, Division of Coastal Management (DCM) officials discovered the excavation in the northwest tributary. At that time, DCM officials found evidence of disturbance in the creek bed and uncontained spoil piles of five to six feet in height along the banks. DCM also found petitioner's four drainage ditches and observed that three of the four were carrying sediment-laden water from petitioner's project site directly into the northwest tributary.

DCM staff returned to the site on January 25, January 31, and February 13, 1984; DCM determined that the tributary and its shoreline was within CAMA permitting jurisdiction. On February 13, DCM staked a location for construction of an earthen dam in the northwest tributary to slow its flow and reduce the amount of sediment introduced into the primary nursery areas.

By Notice of Violation dated February 24, 1984, DCM directed petitioner to install an earthen dam in the northwest tributary at the location staked by DCM officials no later than noon on March 8, 1984. The letter further advised petitioner that failure to install the dam by noon on March 8, 1984 would result in a continuing violation and that each day petitioner failed to comply would be considered a separate violation.

On the afternoon of March 8, 1984, DCM officials found that no dam had been installed and no steps had been taken preparatory to damming the area. Muddy water *94 continued to flow into the northwest tributary from petitioner's drainage ditches.

On March 9, 1984, DCM found that the tributary still had not been dammed. Based upon the March 9, 1984 inspection, DCM sent a Notice of Continuing Violation to petitioner. The letter advised him that each day the filling of estaurine waters continued because of failure to dam the tributary would be considered a separate violation subject to a $2,500.00 per day penalty.

A site inspection on March 13, 1984 revealed that a partial dam had been installed, but was not working properly. DCM sent a second Notice of Continuing Violation dated March 13, 1984 to petitioner. This letter described the necessary steps to bring the tributary into compliance.

Inspection by DCM officials on March 27, 1984 revealed that no additional work had been done on the dam and that muddy water had continued to flow into the lower section of the northwest tributary. On March 28, 1984, DCM found that corrective work had begun on the dam. When DCM officials returned to the site on March 29, 1984 the dam was effectively diverting the sediment-laden water of the northwest tributary into an adjacent wooded swamp and preventing its introduction into primary nursery areas. At that point, petitioner had come into compliance with DCM's restoration order of February 24, 1984.

DCM assessed three civil penalties against petitioner. The first penalty in the amount of $2,500.00 was assessed for the excavation and alteration of the northwest tributary without a CAMA permit. The second penalty of $2,500.00 resulted from petitioner's filling of approximately 25,500 square feet of primary nursery with sand and silt.

The third penalty assessed against petitioner, the issue presented on appeal, was a penalty for filling primary nursery areas each of the nineteen days that sediment-laden water continued to enter the primary nursery area after noon on March 8, 1984. The civil penalty of $19,000.00 reflected DCM's determination that petitioner acted willfully. This determination was upheld under the North Carolina Coastal Resources Commission's (Commission) Use Standards.

Respondent's sole contention on appeal is that the trial court erred in concluding that there was insufficient evidence, in view of the entire record, to support the Commission's findings that the unlawful filling of estaurine waters for nineteen days, after the specified deadline, constituted a willful violation of CAMA. We agree.

The scope of an appellate review of a trial court's order affirming or reversing a final agency's decision is governed by G.S. sec. 150B-52. This Court must determine whether the trial court committed any errors of law. These errors of law, if present, could be the result of an improper application of the standard of review as articulated in G.S. sec. 150B-51. American Nat'l Ins. Co. v. Ingram, 63 N.C.App. 38, 41, 303 S.E.2d 649, cert. denied, 309 N.C. 819, 310 S.E.2d 348 (1983).

If an "agency's findings, inferences, conclusions or decisions are unsupported by substantial evidence ... in view of the entire record as submitted," the reviewing court may "reverse or modify the agency's decision." G.S. sec. 150B-51(b)(5). The statute, as interpreted by the N.C. Supreme Court, maintains the whole record test as the standard of a judicial review for issues arising under the dictates of the Administrative Procedure Act. In the Matter of the Appeal of K-Mart Corp., 319 N.C. 378, 380, 354 S.E.2d 468, 469 (1987).

The "whole record" test does not allow the reviewing court to replace the Board's judgment as between two reasonably conflicting views, even though the court could justifiably have reached a different result had the matter been before it de novo. On the other hand, the "whole record" rule requires the court, in determining the substantiality of evidence supporting the Board's decision, to take into account whatever in the record fairly detracts from the weight of the Board's evidence. Under the whole evidence rule, the court may not consider the evidence which in and of itself justifies *95 the Board's result, without taking into account contradictory evidence or evidence from which conflicting inferences could be drawn.

Goodwin v. Goldsboro Board of Education, 67 N.C.App. 243, 245, 312 S.E.2d 892, 893-94, cert. denied, 311 N.C. 304, 317 S.E.2d 680 (1984).

We must look at the trial court's decision in light of this standard of review. It is important to note, however, that "[t]he `whole record' test is not a tool of judicial intrusion; instead it merely gives [this] court the capability [of] determin[ing] whether [the] administrative decision has a rational basis in the evidence." Id.

Under the applicable section of CAMA, the Commission is authorized to "consider each day the action or inaction continues after notice is given of the violation as a separate violation [and] a separate penalty may be assessed for each such separate violation," where the action or inaction is willful. G.S. sec. 113A-126(d)(2).

In the case sub judice, petitioner was instructed, by Notice of Violation, to construct an earthen dam by noon on March 8, 1984. This notice was dated February 24, 1984. An inspection of the site on March 8, 1984, by DCM officials revealed that no dam had been constructed and no steps had been taken to damming the area. On the following afternoon, DCM officials once again inspected the area and found that the tributary still had not been dammed. A Notice of Continuing Violation, advising the petitioner that each day filling the estaurine water continued because of a failure to dam the tributary would be considered a separate violation subject to a penalty of up to $2,500.00 per day.

On March 13, 1984, another site inspection was conducted and yielded the construction of a partial dam, but it was not functioning properly. A second Notice of Continuing Violation was sent to petitioner and provided a description of the necessary steps to bring the area into compliance.

An inspection by DCM officials on March 27, 1984 revealed no additional work had been done on the dam and that muddy water had continued to flow into the lower section of the northwest tributary.

On March 28, 1984, DCM officials found that corrective work had begun on the dam. When DCM officials returned to the site on March 29, 1984, the dam was finally in compliance with DCM's restoration order of February 24, 1984.

DCM assessed petitioner with a civil penalty of $1,000.00 per day for each of the nineteen days that sediment-laden water continued to enter the primary nursery area after noon on March 8, 1984. The $1,000.00 per day fine manifested a doubling of the base penalty of $500.00 per day as mandated by the Commission's civil penalty schedule. The doubling of the base penalty resulted from the DCM's determination that petitioner acted willfully.

We believe the record contains ample evidence to support the Commission's findings and conclusions that the petitioner's continued inactions were willful. We note that the petitioner received a certified letter notifying him that the tributary was in violation as early as February 6, 1984.

Although petitioner acknowledges the physical receipt of six such letters, he also avows to not having read any of them.

This Court finds substantial evidence in the record to support the Commission's determination that petitioner's pattern of intentional resistance amounted to willful non-compliance. The trial court's application of the "whole record test" was improperly applied.

Accordingly, for the aforementioned reasons, the judgment of the trial court vacating the assessment of civil penalties is reversed and the matter is remanded for reinstatement of the Coastal Resources Commission's order in full.

Reversed and remanded.

EAGLES and GREENE, JJ., concur.

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.