FIDELITY CONSTRUCTION COMPANY, INC. v. T.A. BLAIR, INC.
Annotate this Case
Download PDF
RENDERED: JULY 30, 2004; 2:00 p.m.
NOT TO BE PUBLISHED
Commonwealth Of Kentucky
Court of Appeals
NO. 2003-CA-000935-MR
AND
CROSS-APPEAL NO. 2003-CA-001035-MR
FIDELITY CONSTRUCTION COMPANY, INC.
APPELLANT/CROSS-APPELLEE
APPEALS FROM WARREN CIRCUIT COURT
HONORABLE THOMAS R. LEWIS, JUDGE
ACTION NO. 01-CI-01065
v.
T.A. BLAIR, INC.
APPELLEE/CROSS-APPELLANT
OPINION
AFFIRMING IN PART, REVERSING IN PART
AND REMANDING
** ** ** ** **
BEFORE:
BUCKINGHAM, JOHNSON AND KNOPF, JUDGES.
JOHNSON, JUDGE:
Fidelity Construction Company, Inc. has
appealed from a judgment of the Warren Circuit Court entered on
March 12, 2003, which, following a bench trial, determined that
T.A. Blair, Inc. had breached two agreements with Fidelity, and
awarded Fidelity reliance damages.
Fidelity appeals from that
portion of the trial court’s judgment denying a damage award for
expectation damages, or lost profits.
T.A. Blair has cross-
appealed from that portion of the trial court’s judgment which
found that it had breached the two agreements.
Having concluded
that the trial court did not err by determining that T.A. Blair
had breached the two agreements, we affirm that portion of the
trial court’s judgment.
However, having further concluded that
the trial court erred by determining that Fidelity was not
entitled to expectation damages, we reverse that portion of the
trial court’s judgment and remand for further proceedings.
For the most part, the relevant facts of this case are
not in dispute.
Fidelity and T.A. Blair are both Kentucky
corporations headquartered in Warren County, Kentucky.
Tim
Howell is the president of Fidelity and Tom Blair is the sole
shareholder in T.A. Blair.
Fidelity is primarily engaged in the
business of general contracting, while T.A. Blair owns several
commercial properties in and around Bowling Green, which it
leases to various businesses.
On April 16, 1998, a severe hail storm struck the
Bowling Green area, which damaged several properties owned by
T.A. Blair.
In order to maximize recovery from T.A. Blair’s
property insurer, Westfield, Tom Blair contracted with Scott
deLuise, a public adjustor, to assist T.A. Blair in its
negotiations with Westfield.
At some point, deLuise asked
Howell to prepare storm damage repair estimates on behalf of
Fidelity.
-2-
In mid-July 1998, Fidelity submitted written repair
proposals for four of T.A. Blair’s properties, which included
the Greenwood Plaza property, the Big B Cleaners property, the
Bluegrass Copy Products property, and the South Central Bell
property.
All four proposals contained detailed repair
estimates and included figures taking into account a 10% profit
margin and a 10% charge for overhead expenses.
In addition, all
four proposals contained “acceptance” language, and a clause
subjecting the proposals to “additional terms and conditions” in
a separately executed construction agreement.
Both Howell and
Tom Blair signed the proposals on behalf of their respective
companies.
On July 17, 1998, Howell and Tom Blair signed a
document entitled “Agreement.”1
Among other things, Article 2 of
this document specifically incorporated the four written
proposals which had previously been signed by both Howell and
Tom Blair.
According to the terms of the 1998 agreement,
Fidelity would repair the damage done to the four properties for
a total price of $738,387.37.
At trial, Tom Blair testified that he entered into
this agreement solely for the purpose of enabling T.A. Blair to
present Westfield with repair estimates during their settlement
negotiations, and that any work to be performed by Fidelity was
1
The 1998 agreement was prepared by using an American Institute of Architects
(AIA) form agreement as a model.
-3-
conditioned upon Tom Blair giving Fidelity the “green light” to
begin repairs.
However, Howell testified that at all times he
expected to eventually perform the work called for in the 1998
agreement.
Regardless of the parties’ differing beliefs, it is
undisputed that Tom Blair never gave Fidelity permission to
commence the repair work called for under the 1998 agreement.
On July 21, 1998, Fidelity submitted another written
repair proposal for T.A. Blair’s FiServ property.
Tom Blair
signed this proposal on December 10, 1998, and the repair work
for this property was completed in early summer 1999, for the
agreed price of $38,908.00.
Unlike the previous four signed
proposals, the FiServ proposal was not made subject to the
“additional terms and conditions” in the separately executed
construction agreement.
On April 5, 2000, Fidelity submitted yet another
written repair proposal for T.A. Blair’s National City Bank
property, which Tom Blair signed on April 10, 2000.
In addition
to containing the similar “acceptance” language that was present
in the first four written proposals, the National City Bank
proposal contained a handwritten note stating that the proposal
was “subject to previously executed AIA agreement.”
-4-
Both Howell
and Tom Blair signed their initials next to this handwritten
The price of this proposal totaled $352,504.15.2
language.
Throughout August, September, and October 2000, Howell
sent T.A. Blair several inquiries via letters and facsimiles
regarding the planned repair work at the National City Bank
property.
These correspondences generally inquired as to when
Fidelity would be given permission to begin the repair work.
In
addition, one of these inquiries explained that T.A. Blair could
choose between two methods for repairing the roof at National
City Bank.
At trial, Tom Blair testified that during this time
period, he informed Fidelity that he was not ready to proceed
with the work at that time.
In December 2000 T.A. Blair finally settled all of its
insurance claims with Westfield.
In May 2001 Howell once again
sent T.A. Blair a letter asking when Fidelity could commence
repair work on the National City Bank property.
On June 18,
2001, after this latest inquiry purportedly went unanswered,
attorneys for Fidelity sent T.A. Blair a letter stating that
Fidelity had suffered damages as a result of T.A. Blair’s
alleged breach of the April 10, 2000, agreement (2000
agreement).
This notice informed T.A. Blair that a legal action
2
An addendum was added to this proposal, which had an original value of
$349,562.41. The addendum was also made “subject to previously executed AIA
agreement,” and added a $2,500.00 repair proposal for “copper stain removal.”
This addendum was signed and dated by both Howell and Tom Blair.
-5-
would be filed by Fidelity unless T.A. Blair was willing to
discuss a settlement of Fidelity’s alleged damages.
On August 20, 2001, Fidelity filed a complaint in the
Warren Circuit Court alleging that T.A. Blair had breached the
2000 agreement.
Specifically, Fidelity alleged that T.A. Blair
had “wrongfully refused, without legal or factual justification
or excuse, to permit Fidelity to perform repairs” as called for
in the 2000 agreement.
Approximately one year later, after a
good deal of discovery had taken place, Fidelity filed an
amended complaint alleging that T.A. Blair had also breached the
1998 agreement.
Once again, Fidelity alleged that T.A. Blair
had “wrongfully refused” to permit Fidelity to perform the
repairs as called for in the 1998 agreement.
On February 4-5, 2003, after still more discovery had
taken place, a bench trial was held in the Warren Circuit Court.
After the trial was concluded, and after both parties were given
time to submit written memoranda in support of their respective
positions, the trial court entered findings of fact, conclusions
of law, and judgment on March 12, 2003.
The trial court found
that Fidelity and T.A. Blair had entered into two binding
contracts, and that by “preventing Fidelity’s performance,” T.A.
Blair had breached both the 1998 and 2000 agreements.
On the
issue of damages, the trial court awarded Fidelity reliance
damages, but declined to award expectation damages, i.e., the
-6-
trial court declined to award Fidelity damages for its lost
profits under the agreements.
The trial court gave Fidelity 30
days in which to submit proof regarding its reliance damages.
On March 19, 2003, Fidelity filed a motion to alter,
amend, or vacate the trial court’s judgment.
Specifically,
Fidelity asked the trial court to add a finding that Fidelity
did perform some repair work for T.A. Blair between the signings
of the 1998 and 2000 agreements.
In addition, Fidelity once
again asked the trial court to award expectation damages.
On
April 14, 2003, the trial court entered an order granting
Fidelity’s motion in part and denying it in part.
The trial
court entered a finding that Fidelity did perform repair work on
T.A. Blair’s FiServ property between 1998 and 2000.
However,
the trial court denied Fidelity’s request that it be awarded
expectation damages.
On April 23, 2003, by an agreed order of the parties,
the trial court noted that Fidelity had declined to take proof
on the issue of reliance damages, and entered an order declaring
the March 12, 2003, judgment final and appealable.
Fidelity’s
appeal and T.A. Blair’s cross-appeal followed.
The parties have raised a number of issues on appeal.
We first turn to T.A. Blair’s claim that the trial court erred
by determining that it had breached the 1998 and 2000
agreements.
In support of this argument, T.A. Blair first
-7-
argues that under the express terms of the agreements,
Fidelity’s performance in repairing the storm damage was
conditioned upon T.A. Blair giving Fidelity the “green light” to
commence the repair work.
In particular, T.A. Blair argues:
The clear import of the language used
by the parties in the [1998 and 2000
agreements] was to preserve [T.A. Blair’s]
control over when and how much of the storm
repair work would be undertaken by Fidelity.
The work could not begin until [T.A. Blair]
so instructed, and [T.A. Blair] had the
right to make “any and all changes” with
corresponding changes in the contract price.
These provisions clearly entitled [T.A.
Blair] to elect not to have the work
performed and negate any claim by Fidelity
that [T.A. Blair] breached the contract.
We disagree and hold that according to the express terms of the
1998 and 2000 agreements, T.A. Blair was not entitled “to elect
not to have the work performed.”
The construction and interpretation of a contract is a
question of law which is subject to de novo review on appeal.3
In the absence of an ambiguity, we give the words used in a
contract their plain and ordinary meaning.4
As we mentioned
previously, both the 1998 and 2000 agreements consisted of
written proposals submitted by Fidelity and a form construction
agreement.
All four written proposals in the 1998 agreement and
3
Frear v. P.T.A. Industries, Inc., Ky., 103 S.W.3d 99, 106 (2003).
4
Id.
-8-
the written proposal in the 2000 agreement contained the
following language:
Acceptance of Proposal:
The above prices, specifications, and
conditions are satisfactory and are hereby
accepted[.] Fidelity Construction Co., Inc.
is authorized to perform work as specified
[emphasis added].
In addition, all five written repair proposals
contained language making the proposals subject to the
“additional terms and conditions” in the separately executed
construction form agreement.5
Finally, all of the proposals were
signed by both Howell and Tom Blair on behalf of their
respective companies.
Turning to the construction agreement, which was also
signed by both Howell and Tom Blair, we highlight the following
provisions:
WITNESSETH, That [Fidelity] hereby
agrees to furnish to [T.A. Blair] all labor
and material and perform all work required
for STORM DAMAGE REPAIR AND RENOVATIONS in
accordance with [Fidelity’s specifications]
[emphasis added].
NOW, THEREFORE, [Fidelity] and [T.A.
Blair], for and in consideration of the
mutual and reciprocal obligations
5
The proposals for the Greenwood Plaza property, the Big B Cleaners property,
the Bluegrass Copy Products Property, and the South Central Bell property
contained pre-printed language subjecting those proposals to the form
construction agreement. The proposal for the National City Bank property
contained handwritten language, which was initialed by both Howell and Tom
Blair, subjecting that proposal to the same construction agreement.
-9-
hereinafter stipulated, do contract and
agree as follows [emphasis added]:
ARTICLE 1. [Fidelity] hereby agrees
. . . to complete the work specified in this
Contract in all respects as is herein
required by [T.A. Blair] [emphasis added].
. . .
ARTICLE 2. [Fidelity] hereby certifies
that [it] has examined all the plans,
drawings and specifications prepared by
[T.A. Blair] for the entire work covered by
this Contract. Said plans and
specifications are hereby referred to and
made a part of this Contract [emphasis
added].
. . .
ARTICLE 3. It is understood and agreed
by and between the parties hereto, that the
work included in this Contract is to be done
under the direction of [T.A. Blair], and
that [its] decisions as to the true
construction and meanings of the plans and
specifications shall be final.
. . .
ARTICLE 5. [Fidelity] hereby agrees to
make any and all changes and furnish the
materials and perform the work that [T.A.
Blair] may require, without nullifying this
Agreement, at a reasonable addition to, or
deduction from, the contract price [emphasis
added].
. . .
ARTICLE 7. [Fidelity] hereby agrees
that the work under this Contract is to be
provided for immediately, and shall be begun
when notified in writing by [T.A. Blair],
and completed upon the mutual agreement of
-10-
[T.A. Blair] and [Fidelity] [emphasis
added].
. . .
ARTICLE 13. [T.A. Blair] hereby agrees
to pay [Fidelity] for such labor and
material herein undertaken to be done and
furnished for the work as mentioned above
the sum of $738,234.11, subject to additions
and deductions as hereinbefore provided.
. . .
ARTICLE 20. All previous negotiations,
proposals, discussions and/or agreements are
null and void.
Hence, while the agreements did provide that T.A.
Blair retained the right to make reasonable additions to or
subtractions from the contemplated repair work, there is no
language indicating that T.A. Blair retained the right to
unilaterally elect not to have any of the work performed.
Indeed, as the trial court noted, if the agreements were
construed in such a manner as to give T.A. Blair the right to
unilaterally cancel the contemplated repair work, there would
have been no legally binding contract between the parties.6
Such
a construction would be contrary to the clear intent of the
parties as expressed by the specific language in the agreements.7
6
Kovacs v. Freeman, Ky., 957 S.W.2d 251, 254 (1997)(stating that “[m]utuality
of obligations is an essential element of a contract, and if one party is not
bound, neither is bound”).
7
Puckett v. Hatcher, 307 Ky. 160, 163, 209 S.W.2d 742, 744 (1948)(stating
that “[t]he rule is universal that the intention which the writing itself
shows the parties contemplated is the one to be applied and enforced by
courts”).
-11-
Thus, we reject T.A. Blair’s claim that it was entitled “to
elect not to have the work performed” as specified in the 1998
and 2000 agreements.
Therefore, according to the express terms
of the 1998 and 2000 agreements, T.A. Blair was bound to permit
Fidelity to perform the repair work as contemplated in those
agreements.
T.A. Blair next argues that in determining the
parties’ intentions under the 1998 and 2000 agreements, the
agreements must be construed by taking into account the
surrounding circumstances which existed when the agreements were
executed.
T.A. Blair points to three factors in support of its
contention that the parties entered into the agreements solely
for the purpose of enabling T.A. Blair to present Westfield with
repair estimates during settlement negotiations.
First, T.A.
Blair notes that it had tentatively agreed to sell two of the
properties covered by the 1998 agreement (the Greenwood Plaza
property and the Big B Cleaners property) prior to the
hailstorm, and that when these property transfers were completed
after the 1998 agreement had been signed, there was no mention
in the property transfer agreements of an obligation on the part
of T.A. Blair to repair any storm damage.
Thus, T.A. Blair
argues that “[i]t simply defies common sense that [T.A. Blair]
would have entered into an unconditional contract for
-12-
[$500,000.00] worth of repairs to these properties when [it] had
no obligation to make the repairs.”
Second, T.A. Blair argues that both parties knew when
the 1998 and 2000 agreements were signed that the repair
estimates were “inflated quite a bit.”
Third, T.A. Blair claims
that “some of the work covered by the [submitted repair]
proposals had already been [completed]” when the 1998 and 2000
agreements were signed.
Hence, T.A. Blair asserts that these
three factors all lead to a conclusion that the 1998 and 2000
agreements were executed solely for the purpose of enabling T.A.
Blair to present Westfield with its own damage repair estimates
during their settlement negotiations.
We disagree with T.A.
Blair and conclude that there is no need to resort to
considering “surrounding circumstances” in determining the
parties’ intentions in executing the 1998 and 2000 agreements.
It is true that when determining the intentions of the
parties to a contract, a court may under certain circumstances
consider the “subject matter of the contract, the objects to be
accomplished, the situation of the parties and the conditions
and circumstances surrounding them[.]”8
However, “where the
instrument is so clear and free of ambiguity as to be selfinterpretive, it needs no construction and will be performed or
8
McHargue v. Conrad, 312 Ky. 434, 437, 227 S.W.2d 977, 979 (1950).
-13-
enforced in accordance with its express terms.”9
An ambiguous
contract is one that is susceptible to more than one reasonable
interpretation.10
In the case at bar, we hold that the 1998 and
2000 agreements are free of ambiguity and that the parties’
intentions may therefore be gleaned from the express terms.
As we stated previously, there is no language, either
in the signed repair proposals or in the form construction
agreement, indicating that Fidelity and T.A. Blair intended the
1998 and 2000 agreements to be merely “tentative” agreements, or
documents solely for T.A. Blair to use during its settlement
negotiations with Westfield.11
To the contrary, the language of
the agreements leads to only one reasonable construction, i.e.,
that while T.A. Blair retained some control over how the repair
work would proceed, Fidelity would in fact eventually be given
permission to begin and complete the contemplated repair work.
Indeed, T.A. Blair has failed to point to any specific provision
or provisions in the 1998 and/or 2000 agreements which are
allegedly unclear or ambiguous.
9
10
Ex parte Walker’s Executor, 253 Ky. 111, 68 S.W.2d 745, 747 (1933).
Central Bank & Trust Co. v. Kincaid, Ky., 617 S.W.2d 32, 33 (1981).
11
Tom Blair admitted during his testimony that there is no language in the
1998 or 2000 agreements supporting his contention that the parties entered
into those agreements solely for the purpose of enabling T.A. Blair to
present Westfield with repair estimates during settlement negotiations.
-14-
In reviewing contractual agreements, a court is not
permitted to create an ambiguity where none exists,12 and “an
otherwise unambiguous contract does not become ambiguous” merely
because one of the parties asserts, post-hoc, that the contract
failed to state what the parties truly intended.13
Therefore,
since the terms of the agreements are free of ambiguity, the
parties’ intentions may be determined solely from the
agreements’ express terms.
Accordingly, we reject T.A. Blair’s
claim that in determining the parties’ intentions under the 1998
and 2000 agreements, the circumstances surrounding the execution
of those agreements must be taken into account.
In a closely-related argument, T.A. Blair contends
that the true intent of the parties may be determined by
examining their “course of performance” with respect to the 1998
and 2000 agreements.
In support of this argument, T.A. Blair
notes (1) that Fidelity never demanded in writing to begin
performance under the 1998 agreement; (2) that the repair work
which was completed on the FiServ property was not governed by
the form construction agreement; (3) that prior to executing the
2000 agreement, Howell sent T.A. Blair a letter allegedly
12
First Commonwealth Bank of Prestonsburg v. West, Ky.App., 55 S.W.3d 829,
836 (2000).
13
Frear, 103 S.W.3d at 107 (stating that “an otherwise unambiguous contract
does not become ambiguous when a party asserts--especially post hoc, and
after detrimental reliance by another party--that the terms of the agreement
fail to state what it intended”).
-15-
stating that T.A. Blair might wish to “cancel” the agreement;14
and (4) that after signing the 2000 agreement, Howell continued
to send communications to T.A. Blair regarding proposed methods
for repairing the National City Bank property.15
T.A. Blair
argues that these factors show that it “had the right to
determine if and when the [repair] work would be done” under the
1998 and 2000 agreements.
Once again, we disagree.
The so-called “doctrine of contemporaneous
construction [ ] embraces no more than the practice of looking
to the voluntary and positive acts of the parties in executing
and fulfilling the terms of the contract.”16
However, the
doctrine may only be invoked where the contract at issue is
ambiguous and susceptible to more than one reasonable
14
This letter was accompanied by a repair proposal for the National City Bank
property. The precise language of this letter, which was dated March 4,
2000, approximately one month prior to the execution of the 2000 agreement,
stated in part:
This agreement between us can be increased or
decreased [through] change orders, also the scope of
work can be changed [through] changes of orders. You
[T.A. Blair] may wish to cancel the contract in its
[entirety] for your convenience, if that is the case,
YOU & I can agree on a lump sum settlement.
In short, it is not at all clear which “contract” Howell was referring to
when he stated that T.A. Blair might wish to “cancel the contract” in its
entirety for its “convenience,” since the 2000 agreement had not at that time
been finalized.
15
The fact that Howell continued to send letters to T.A. Blair regarding
options on how it might wish to proceed with the repair of the National City
Bank property is, notwithstanding T.A. Blair’s argument to the contrary,
consistent with the 2000 agreement. As we mentioned above, T.A. Blair
retained some control over how the repair work was to be completed.
16
William S. Haynes, Kentucky Jurisprudence, Contracts § 15-11, p. 268-69
(1986).
-16-
interpretation.17
As we stated previously, the 1998 and 2000
agreements are not ambiguous, and T.A. Blair has not argued to
the contrary.
Thus, the doctrine of contemporaneous
construction is not applicable and the intentions of the parties
may be gleaned solely from the express terms of the agreement.
Therefore, having concluded that, according to the express terms
of the 1998 and 2000 agreements, T.A. Blair was bound to permit
Fidelity to perform the repair work as called for under those
agreements, we turn to the trial court’s finding that T.A. Blair
breached the agreements by preventing Fidelity’s performance.
In its brief to this Court, T.A. Blair has not argued
that the trial court erred by finding that it prevented Fidelity
from performing the repair work as called for under the 1998 and
2000 agreements.
Rather, T.A. Blair has argued that it was
entitled “to elect not to have the work performed” under the
terms of those agreements.
However, as we stated previously,
this interpretation is at odds with the express terms of the
agreements in question.
Accordingly, we affirm that portion of
the trial court’s order which found that T.A. Blair had breached
the 1998 and 2000 agreements.
17
See Wathen v. Schleicher, Ky., 510 S.W.2d 22, 23 (1974)(stating that “[i]n
order for the doctrine of contemporaneous construction to be utilized, the
contract first has to be ambiguous”); and Haynes, supra at 269 (noting that
“the doctrine of contemporaneous construction is inapplicable to contract
terms which are clear and unambiguous”).
-17-
We now consider Fidelity’s argument on its appeal that
the trial court erred by denying its request for expectation
damages.
As Fidelity points out, the trial court offered three
primary reasons for declining to award expectation damages.
First, the trial court placed a great deal of emphasis on the
fact that Fidelity never began performance under the 1998 or
2000 agreements, and concluded that “the [c]ourt declines to
compensate Fidelity for doing nothing.”
Second, the trial court
denied Fidelity’s request for expectation damages on grounds
that such an award would result in “disproportionate
compensation.”
Third, the trial court denied Fidelity a
recovery for lost profits under the 2000 agreement on grounds
that those losses were “foreseeable” and “avoidable.”
Fidelity
claims that all of the grounds stated were improper reasons for
denying its request for expectation damages.
We agree.
In Kentucky it is well-settled that in an action for
breach of contract, the measure of damages “is that sum which
will put the injured party into the same position he would have
been in had the contract been performed.”18
Where the breaching
party “has prevented the plaintiff from performing any part [of
the contract, the measure of damages] is the net profit which
would have been made; that is, the difference between the
18
Perkins Motors, Inc. v. Autotruck Federal Credit Union, Ky.App., 607 S.W.2d
429, 430 (1980).
-18-
contract price and the reasonable cost of performance.”19
Simply
stated, the trial court did not cite, and our own research has
not disclosed, any authority which stands for the proposition
that where a breaching party has improperly prevented
performance under a contract, the non-breaching party must have
actually begun performance before a recovery for expected lost
profits will be available.
To the contrary, both Koplin and
Janin v. Herron,20 involve situations in which the non-breaching
parties were permitted to recover lost profits despite the fact
that they had not yet began performance when the breaching party
improperly prevented them from performing under the contracts at
issue.
Accordingly, the trial court erred by making this
distinction as grounds for denying Fidelity an award for
expectation damages.
Similarly, the trial court’s ruling that under the
facts of the case at bar, an award for lost profits would result
in “disproportionate compensation” was not a proper basis for
denying Fidelity’s request for expectation damages.
In making
its ruling, the trial court apparently relied on Section 351(3)
19
See, e.g., Koplin v. Faulkner, Ky., 293 S.W.2d 467, 469 (1956).
20
206 Ky. 171, 266 S.W. 1058, 1059 (1924).
-19-
of the Restatement (Second) of Contracts,21 which reads in full
as follows:
A court may limit damages for
foreseeable loss by excluding recovery for
loss of profits, by allowing recovery only
for loss incurred in reliance, or otherwise
if it concludes that in the circumstances
justice so requires in order to avoid
disproportionate compensation.
Comment f to Section 351 suggests that this
limitations provision is most applicable to situations in which
the contract arose in an informal or non-commercial setting, or
where there is “an extreme disproportion” between the amount of
the losses claimed and the value of the services at issue.22
Clearly, neither situation is present under the facts of the
instant case.
The 1998 and 2000 agreements were executed by two
21
Neither the trial court nor the parties were able to cite a published
Kentucky case adopting this section of the Restatement. Likewise, our own
research did not reveal a reported Kentucky decision citing this particular
provision of the Restatement.
22
Comment f reads in pertinent part as follows:
It is not always in the interest of justice to
require the party in breach to pay damages for all of
the foreseeable loss that he has caused. There are
unusual instances in which it appears from the
circumstances either that the parties assumed that
one of them would not bear the risk of a particular
loss or that, although there was no such assumption,
it would be unjust to put the risk on that party.
One such circumstance is an extreme disproportion
between the loss and the price charged by the party
whose liability for that loss is in question. The
fact that the price is relatively small suggests that
it was not intended to cover the risk of such
liability. Another such circumstance is an
informality of dealing, including the absence of a
detailed written contract, which indicates that there
was no careful attempt to allocate all of the risks.
-20-
experienced businessmen in a commercial setting, and Fidelity’s
request to recover approximately 17% of the total value of both
agreements as lost profits does not amount to an “extreme
disproportion” between the losses claimed and the value of the
services in question.23
Therefore, even if Section 351(3) were
controlling, the trial court erred in its application of that
section to the facts of the case at bar.
Finally, the trial court denied Fidelity’s request for
expectation damages for the 2000 agreement on the grounds that
any lost profits under this agreement were “foreseeable” and
“avoidable” due to T.A. Blair’s unwillingness to proceed with
the repair work under the 1998 agreement.
Once again, this was
an improper basis upon which to deny Fidelity an award for
expectation damages.
As we will explain in further detail
below, in the context of awarding expectation damages, the
doctrine of foreseeability requires that before lost profits
will be awarded, the non-breaching party’s damages must have
been reasonably foreseeable to the parties at the time of
contracting.
Hence, the trial court erred with respect to its
foreseeability analysis.
Therefore, having concluded that all
23
The total value of both agreements was $1,090,891.51. Fidelity’s request
to recover $186,872.78 in expectation damages represents approximately 17% of
the total value of both agreements. For a case in which the trial court
relied upon the “extreme disproportion” language found in § 351(3) as a basis
for denying a party’s request for “compensatory damages,” see International
Ore & Fertilizer Corp. v. SGS Control Services, Inc., 743 F.Supp. 250, 257
(S.D.N.Y. 1990)(denying plaintiff’s request for $2,400,000.00 in damages
where the contract price was only $150.00, which represented “a ratio of
16,000 to one”).
-21-
of the trial court’s stated grounds for denying Fidelity an
award for expectation damages were erroneous, we turn to the
question of whether an award for lost profits under the facts of
the case sub judice was proper.
Where a party has been improperly prevented from
performing under a contract, there are essentially two
requirements that must be met before the non-breaching party
will be entitled to an award for expectation damages.
First,
the non-breaching party’s lost profits must have been reasonably
foreseeable at the time the parties entered into the contract.
In Kentucky Consumers Oil Co. v. General Bonding Warehousing
Corp.,24 the former Court of Appeals stated:
“In addition to general damages, the
injured party is entitled to recover special
damages which arise from circumstances
peculiar to the particular case, where those
circumstances were communicated to or known
by the other party at the time the contract
was made; that is, he may recover such
damages as are the reasonable and natural
consequences of the breach under the
circumstances so disclosed, and as may
reasonably be supposed to have been in the
contemplation of both parties. In such
case, the special circumstances become an
24
299 Ky. 161, 165-66, 184 S.W.2d 972, 974 (1945)(quoting Baker v. Morris,
168 Ky. 168, 172, 181 S.W. 943, 945 (1916)). See also Warren Post No. 23,
American Legion v. Jones, 302 Ky. 861, 865, 196 S.W.2d 726, 728
(1946)(stating that “‘[a]s a general rule, profits which would have been
realized if a contract had been performed may be recovered as damages for its
breach, provided they are susceptible of being ascertained with reasonable
certainty, and their loss may reasonably be supposed to have been within the
contemplation of the parties when the contract was made, as the probable
result of its violation’”)(quoting 15 Am.Jur. Damages, § 151).
-22-
implied element of the contract, and of the
duty thereby imposed.”
. . .
“Loss of profits growing out of an
existing collateral or subordinate agreement
may be recovered where they were within the
contemplation of the parties when the
original contract was made; but, as in other
cases of special damage, the defendant must
have had notice of such collateral contract
at that time.”
Second, the amount of lost profits must be proven to a
degree of reasonable certainty.
In Illinois Valley Asphalt,
Inc. v. Harry Berry, Inc.,25 our Supreme Court discussed this
requirement:
Loss of anticipated profits as an
element of recoverable damages for breach of
contract is fully recognized in Kentucky.
Mere uncertainty as to the amount will not
preclude recovery. There must be presented,
however, sufficient evidence on which a
reasonable inference as to the amount of
damage can be based [citations omitted].
Furthermore, it has been held that “uncertainty which
prevents a recovery is uncertainty as to the fact of damage and
not as to its amount.
Where it is reasonably certain that
damage has resulted, mere uncertainty as to the amount does not
preclude one’s right of recovery or prevent a jury decision
awarding damages.”26
25
Ky., 578 S.W.2d 244, 245-46 (1979).
26
Johnson v. Cormney, Ky.App., 596 S.W.2d 23, 27 (1979), overruled on other
grounds by Marshall v. City of Paducah, Ky.App., 618 S.W.2d 433 (1981).
-23-
During the proceedings below, the trial court denied
Fidelity’s request for expectation damages without considering
whether Fidelity had satisfied either of the two aforementioned
requirements for recovering lost profits.
Consequently, the
trial court made no factual findings with respect to this issue.
Hence, a remand of this matter for further fact-finding is
necessary.
Accordingly, we reverse that portion of the trial
court’s judgment denying Fidelity’s request for expectation
damages, and remand this matter with instructions to consider
whether Fidelity has satisfied the “foreseeability” and
“reasonable certainty” requirements discussed above.
Based on the foregoing, the judgment of the Warren
Circuit Court is affirmed in part and reversed in part and this
matter is remanded for further proceedings consistent with this
Opinion.
ALL CONCUR.
BRIEFS FOR APPELLANT/CROSSAPPELLEE:
BRIEFS FOR APPELLEE/CROSSAPPELLANT:
Ryan C. Reed
Brett A. Reynolds
Bowling Green, Kentucky
Greg N. Stivers
Scott D. Laufenberg
Bowling Green, Kentucky
ORAL ARGUMENT FOR
APPELLANT/CROSS-APPELLEE:
ORAL ARGUMENT FOR
APPELLEE/CROSS-APPELLANT:
Ryan C. Reed
Bowling Green, Kentucky
Greg N. Stivers
Bowling Green, Kentucky
-24-
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.