A contract between the United States and A. for his removal of
the rock at the entrance of a certain harbor provided that he
should complete the work at a specified time and that if he should
delay or be unable to proceed with it in accordance with the
contract, the officer in charge might terminate the contract and
employ others to complete the work, deducting expenses from any
money due or owing to A., who was also to be responsible for any
damages caused to others by his delay or noncompliance. Payment
upon the completion and acceptance of the several sections was to
be made, reserving ten percent therefrom until the completion and
acceptance of the whole work. The work was not completed at the
specified time, chiefly in consequence of the failure of a third
party to deliver to A. the necessary explosive, and the officer in
charge terminated the contract, but the evidence does not show that
his action was wrongful. The work was completed by other parties at
much lower terms. A. brought suit against the United States.
Held that, the United States having sustained no lose by
the failure of A., he is entitled to the reserved ten percent, but
not to the profits that he would have made had he performed the
contract, nor to the difference between the contract price and that
at which the work was completed by others.
The facts are sufficiently stated in the opinion of the
Court.
Page 99 U. S. 31
MR. JUSTICE MILLER delivered the opinion of the Court.
On the tenth day of August, 1867, David Quinn, the appellant's
intestate, entered into a written contract with J. B. Wheeler, of
the Engineer Corps for the United States, to remove the rock at the
entrance of Eagle Harbor, Michigan, and deposit it at such point as
the engineer in charge should direct, and he agreed to commence the
work on or before the first day of September thereafter and
complete the removal of the rock on or before Oct. 1, 1868.
"It was also agreed that if, in any event, the contractor shall
delay, or be unable to proceed with the work in accordance with its
terms, the engineer officer in charge shall have full right and
authority to take away the contract and employ others to complete
the work, deducting the expenses from any money that may be due and
owing him, and the contractor will be responsible for any damages
caused to others by his delay or noncompliance."
He was to be paid for his work as sections of it were completed
to the required depth, the government reserving ten percent from
such payments until the whole was completed and accepted.
Quinn having failed to complete the work by the 1st of October,
it was taken from him on the 9th of November, 1868, and, after
advertising, let to other parties. For all the work completed he
was paid at the contract price, except that the government retained
ten percent on the estimated sum.
He brings this suit in the Court of Claims on the contract, and
his petition being dismissed he appeals to this Court.
He claims that he was wrongfully prevented from completing his
work, and is entitled to the profits he would have made, to-wit,
$58,682, or, if not this, that the United States, by letting the
contract to other parties, had the work done for $33,060 less than
they agreed to pay him, and he claims that sum. He claims, in any
event, the ten percent retained, amounting to $1,740.
In support of the claims for profits on work not performed by
him, two propositions are advanced:
1. That although the time had elapsed within which claimant was
bound by the contract to complete the work, and it
Page 99 U. S. 32
was unfinished, the engineer had no lawful authority to
terminate the contract, because the fault in the delay was in the
government and its officers.
2. That conceding the authority to terminate the contract was
lawfully exercised, the consequence was that when the work was done
by the government, or by other contractors at its instance, such
work was done at his risk of loss or of profit, and if, when
finished, it cost the United States more than it would if done
under his contract, he was responsible for the loss, and if done
for less, the gain was his.
We cannot concur in this latter proposition.
It seems very doubtful if, in the event of the termination of
his contract under the clause authorizing the engineer to do so,
the contractor is liable to the United States for anything beyond
the ten percent retained. This ten percent is retained, in the
language of the contract, until the whole shall be completed. It is
retained as security for that end. The work is to be completed by
others, and the expenses deducted from any money that may be due
him. He is to be responsible for damages caused to others by the
delay. If, therefore, he is responsible to the United States beyond
the sum due him at the time the contract is taken from him, it is
not by the express terms of the contract, but on the general
doctrine of damages on failure to fulfill and contract.
So, on the other hand, we think it equally clear that when his
contract is rightfully terminated, he is entitled to no further
rights in regard to its performance by others. The government does
not, by reason of being compelled by his failures to resume control
of the work, do so for his benefit, but for its own. They do not
thus become his agents to do the work for him which he failed to
do, and let him reap the profits of a work which he refused or
neglected to perform.
Nor are we able to see that the contract was wrongfully taken
from him.
It may very well be contended that the engineer in charge is by
the agreement of the parties made the judge of the existence of
"such delay or inability to proceed with the work in accordance
with the contract" as justifies him in taking it away, and that his
action in that regard is conclusive. But the
Page 99 U. S. 33
counsel for the United States have not assumed that ground here,
and it is not necessary to the decision of the case.
It may be safely asserted, however, that it will be presumed
that his action was well founded until it is impeached by
satisfactory evidence, and especially where, as in this case, the
time limited for the completion of the work had passed. Such
evidence is wanting in this case. It is true that there was some
delay in the autumn of 1867 on the part of the engineers in
locating the precise point where the rock was to be excavated and
in determining the low water mark with reference to which all the
work was to be done, and this was not perfected until February,
1868. But there is no evidence that Quinn demanded that this should
be done sooner, or that he desired to commence his work
earlier.
There is satisfactory evidence that his delay was caused mainly,
if not solely, by his inability to procure the nitroglycerine
which, under his plan of working, was the only explosive that he
could use. He had the entire work honeycombed with cells drilled
for the reception of this explosive in due time, and if he could
have procured it, would have completed the work in time, or at
least his contract would not have been taken away. The excuse is
that the party who had contracted to deliver the nitroglycerine
failed in business and failed to deliver. But the authority of the
engineer to terminate the contract did not depend on the value of
excuses or the difficulty of performance. He had "full right and
authority" to do this for inability to proceed with the work
according to the contract, as well as for delay.
There was both delay and inability in this case, and we do not
see that they were due to any failure on the part of the
government.
In this connection, it is said that Quinn should receive pay for
the holes drilled for reception of the explosive in that part of
the work not completed when it was taken from him. But the finding
of the Court of Claims is that this was not used by the government
or by the subsequent contractor, because the latter used gunpowder,
which could not be profitably exploded in the holes drilled for the
nitroglycerine.
We think that the Court of Claims was right in rejecting
Page 99 U. S. 34
the two first items of the claim as we have mentioned them.
But it is otherwise with regard to the ten percent of the price
of the work completed, retained by the government.
We have already seen that this was retained for the purpose of
securing the completion of the work, and that if not completed by
the contractor, it was to be used in paying the expenses of such
completion. In our view, it is a fair construction of this part of
the agreement that the money retained under it is for security that
the contractor will not abandon his work, but will proceed in it
with due vigor, and for indemnity to the United States in case he
fails to do this. Unless, therefore, the government has sustained
some loss, some pecuniary or legal damage by his failure, the money
which he has fairly earned should be paid to him when the work
which he agreed to do has been completed, though by others. In the
case before us, the United States made a clear gain of $33,000 by
taking away his contract and making a new and more advantageous one
with another person. Under such circumstances, the United States no
longer has a right to the money withheld for indemnity and
security, because the risk is over, the event has occurred, and
instead of loss or damage there has been a gain by the
transaction.
The judgment of the Court of Claims dismissing the petition will
therefore be reversed and the case remanded to that court with
directions to render a judgment for claimant for the sum of $1,740,
and it is
So ordered.