1. The third section of an Act of Congress, approved April 20,
1832, 4 Stat. 505, which is still in force, enacts that four
sections of land, including the hot springs in Arkansas, shall be
reserved for the future disposal of the United States and shall not
be entered, located, or appropriated for any other purpose
whatever. The Indian title to them was not extinguished until Aug.
24, 1818, nor were the public surveys extended over them until
1838, nor has the sale of them ever been authorized by law. No part
of said sections was therefore ever subject to preemption or to
location, and no claim thereto has been validated or confirmed by
any act of Congress.
2. The "Act for the relief of the inhabitants of the late County
of New Madrid in Missouri Territory, who suffered by earthquakes,"
approved Feb. 17, 1815, 3 Stat. 211, required the following steps
to be taken: application to the recorder of land titles, showing
the party's claim and praying a certificate of location --
certificate of location issued by the recorder, setting forth the
amount of land to which the applicant was entitled -- application
to the surveyor, presenting the certificate of location, and
designating the lands which the party desired to appropriate --
survey and plat made by the surveyor -- return of the survey and
plat to the recorder to be filed and recorded, with a notice
designating the tract located and the name of the claimant --
certificate of the recorder, stating the facts, and that the panty
was entitled to a patent -- transmission of this certificate to the
General Land Office -- the patent. In addition to these requisites,
the land thus appropriated must have been a part of the public
lands of the territory, the sale of which was authorized by law. A
survey, therefore, of part of said four sections made in 1820, if
never returned to the recorder's office, did not within the meaning
of said act or of the Act of April 26, 1822, 4 Stat. 668,
Page 92 U. S. 699
locate or segregate from the public domain the land thereby
covered and so appropriate it to the claimant as to give him a
vested right thereto and prevent the operation of the said Act of
April 20, 1832.
2. The asserted rights of the respective claimants to the land
in controversy discussed and disallowed.
MR. JUSTICE BRADLEY delivered the opinion of the Court.
The title to a well known watering place in the State of
Arkansas called the Hot Springs, now located in Hot Springs County,
has been contested by a number of claimants for nearly half a
century. These springs are situated in a narrow valley or ravine
between two rocky ridges in one of the lateral ranges of the Ozark
Mountains, about sixty miles to the westward of Little Rock. Though
not easily accessible, and in a district of country claimed by the
Indians until after the treaty made with the Quapaws in 1818, they
were considerably frequented by invalids and others as early as
1810 or 1812, but no permanent settlement was made at the place
until a number of years afterwards. Temporary cabins were erected
by visitors, and by those who resorted there to dispose of articles
needed by visitors, but were only occupied during a portion of the
year. The public surveys were not extended to that portion of the
country until 1838.
In order to settle, if possible, the controversies which existed
and which seemed interminable, none of the parties having any
regular government title, and it being doubtful whether any of them
were entitled thereto, Congress, on the thirty-first day of May,
1870, passed the following act:
"AN ACT in relation to the Hot Springs Reservation in
Arkansas."
"
Be it enacted by the Senate and House of Representatives of
the United States of America in Congress assembled that any
person claiming title, either legal or equitable, to the whole or
any
Page 92 U. S. 700
part of the four sections of land constituting what is known as
the Hot Springs Reservation, in Hot Springs County, in the State of
Arkansas, may institute against the United States in the Court of
Claims and prosecute to final decision any suit that may be
necessary to settle the same,
provided that no such suits
shall be brought at any time after the expiration of ninety days
from the passage of this act, and all claims to any part of said
reservation upon which suit shall not be brought under the
provisions of this act within that time shall be forever
barred."
"SEC. 2.
And be it further enacted, that all such suits
shall be by petition in the nature of a bill in equity and shall be
conducted and determined in all respects, except as herein
otherwise provided, according to the rules and principles of equity
practice and jurisprudence in the other courts of the United
States, and for the purposes of this act the Court of Claims is
hereby invested with the jurisdiction and powers exercised by
courts of equity, so far as may be necessary to give full relief in
any suit which may be instituted under the provisions of this
act."
"SEC. 3.
And be it further enacted that notice of every
suit authorized by this act shall be executed by the delivery of a
true copy thereof, with a copy of the petition, to the Attorney
General, whose duty it shall be, for and in behalf of the United
States, to demur to or answer the petition therein, within thirty
days after the service of such process upon him, unless the court
shall, for good cause shown, grant further time for filing the
same."
"SEC. 4.
And be it further enacted that if two or more
parties claiming the same lands under different titles shall
institute separate suits under the provisions of this act, such
suits shall be consolidated and tried together, and the court shall
determine the question of title and grant all proper relief as
between the respective claimants, as well as between each of them
and the United States."
"SEC. 5.
And be it further enacted that if, upon the
final hearing of any cause provided for in this act, the court
shall decide in favor of the United States, it shall order such
lands into the possession of a receiver to be appointed by the
court, who shall take charge of and rent out the same for the
United States until Congress shall by law direct how the same shall
be disposed of, which said receiver shall execute a sufficient bond
to be approved by the court, conditioned for the faithful
performance of his duties as such, render a strict account of the
manner in which he shall have discharged said duties, and of all
moneys received by him as a receiver as aforesaid, which shall be
by said court approved or rejected accordingly as it
Page 92 U. S. 701
may be found correct or not, and pay such moneys into the
Treasury of the United States, and he shall receive such reasonable
compensation for his services as said court may allow; and in case
of a failure of said receiver to discharge any duty devolving upon
him as such, the court shall have power to enforce the performance
of the same by rule and attachment. But if the court shall decide
in favor of any claimant, both as against the United States and
other claimants, it shall so decree, and proceed by proper process
to put such successful claimant in possession of such portion
thereof as he may be thus found to be entitled to, and upon the
filing of a certified copy of such decree with the Secretary of the
Interior, he shall cause a patent to be issued to the party in
whose favor such decree shall be rendered for the lands therein
adjudged to him,
provided that either party may within
ninety days after the rendition of any final judgment or decree in
any suit authorized by this act, carry such suit by appeal to the
Supreme Court of the United States, which court is hereby vested
with full jurisdiction to hear and determine the same on such
appeal in the same manner and with the same effect as in cases of
appeal in equity causes from the circuit courts of the United
States;
and provided further that in case the judgment or
decree of the Court of Claims in any such suit shall be adverse to
the United States, the Attorney General shall prosecute such appeal
within the time above prescribed, and the taking of an appeal from
any such judgment or decree shall operate as a supersedeas thereof
until the final hearing and judgment of the Supreme Court
thereon."
"J. G. BLAINE"
"
Speaker of the House of Representatives"
"SCHUYLER COLFAX"
"
Vice-President of the United States and President of the
Senate"
"Received by the President May 31, 1870."
"[NOTE BY THE DEPARTMENT OF STATE -- The foregoing act having
been presented to the President of the United States for his
approval, and not having been returned by him to the House of
Congress in which it originated within the time prescribed by the
Constitution of the United States, has become a law without his
approval.]"
The various parties setting up a claim to the property having,
in pursuance of the act, filed their respective petitions in the
Court of Claims; and the cases having been consolidated, the court,
after a very full investigation, rendered a decree in
Page 92 U. S. 702
favor of the United States, and adverse to all the claimants.
That decree is brought here by appeal.
Three different titles are set up against the United States, two
of them under claims of preemption, and one under a New Madrid
location.
1. John C. Hale claims the southwest quarter of section 33,
township 2 south, range 19 west, of the fifth principal meridian in
Hot Springs County, Ark., embracing the hot springs, which are the
object of contention. He claims as representative of John Percifull
by right of preemption under the fifth section of the Act of
Congress, passed April 12, 1814, entitled "An Act for the final
adjustment of land titles in the State of Louisiana and Territory
of Missouri." By this section it was provided, amongst other
things, that every person, and the legal representatives of every
person, who had actually inhabited and cultivated a tract of land
lying in the Territory of Missouri not rightfully claimed by any
other person, and who should not have removed from the territory,
should be entitled to the right of preemption in the purchase
thereof under the same restrictions and regulations as directed in
a similar Act passed Feb. 5, 1813, in relation to Illinois. Those
restrictions and regulations were that the price should be the same
as that of other public lands in the territory; that only one
quarter-section should be thus sold to one individual; that it
should be bounded by the sectional and divisional lines of the
public survey; and that the sale should not embrace lands reserved
from sale by former acts, or directed to be sold in town lots,
&c. It was further required by the Act of 1813, that every
person claiming under the act must make known his claim by
delivering a notice in writing to the register of the land office
for the district in which h e land should lie designating his
claim, and to be filed in the office. If it appeared to the
satisfaction of the register and receiver that he was duly
entitled, he was allowed to enter the land on payment of
one-twentieth of the price, but the entry must be made at least two
weeks before the time of the commencement of public sales in the
district or the right would be forfeited.
Hale sets forth in his petition that, at the time when the said
act was passed -- namely, April 12, 1814 -- John Percifull
Page 92 U. S. 703
had actually inhabited and cultivated the tract of land
embracing the hot springs, and forming a portion of the
quarter-section claimed by him; that he had settled upon the same
as early as 1809, and had continued to reside thereon and cultivate
the same up to the time of the passage of the act; but that he
could not comply with the act as to making entry &c., because
the land was not publicly surveyed until the year 1838. That as
soon as practicable after the survey was made -- namely, on the
27th of September, 1838 -- Sarah and David Percifull, the widow and
heir-at-law of John Percifull (who was then deceased), gave notice
of the said claim, verified by affidavits, to the register of the
proper land office at Washington, Ark., and applied to the register
and receiver to enter the same; but that their application was
rejected. That this decision of the register and receiver was
subsequently confirmed by the Commissioner of the General Land
Office on the ground that the hot springs, and four sections of
land around the same, had been reserved for the future disposal of
the United States by an Act of Congress passed April 20, 1832.
The act of 1832, referred to, was an act authorizing the
Governor of Arkansas Territory to lease the salt springs therein.
By the third section of the act, it was enacted that the hot
springs in said territory, together with four sections of land
including said springs, as near the center thereof as may be, shall
be reserved for the future disposal of the United States and shall
not be entered, located, or appropriated for any other purpose
whatever.
Besides this act which the claimant had to contend with, the
Indian title to that portion of the country was not extinguished
until Aug. 24, 1818, when it was ceded to the United States by the
treaty made with the Quapaws. Attorney General Butler, in 1836,
being applied to for his opinion on the subject, held that none of
the lands ceded by that treaty were, or ever had been, subject to
preemption claims under the Act of 1814, because no settlement or
cultivation of the lands prior to that act could have been made
consistently with the rightful claims of others -- namely the
Quapaw Indians. The land department always acted in conformity with
this opinion. And it is difficult to see how a different result
could have been
Page 92 U. S. 704
reached. It was the declared policy of the government at an
early day to prohibit any settlement of lands belonging to the
Indians. A proclamation to this effect was issued by the old
Congress, Sept. 22, 1783. Journals, vol. iv. p. 275; Land Laws,
1828, p. 388. An enactment of the same purport was made by Congress
in 1802, in the act to regulate trade and commerce with the
Indians, sec. 5. 2 Stat. 141, 142. After the acquisition of
Louisiana, it was repeated in reference to that territory. Act
March 26, 1804, 2 Stat. 289.
But it is contended that this difficulty has been obviated by
the Act of March 1, 1843, 5 Stat. 603, passed to perfect the titles
of land south of the Arkansas River, held under New Madrid
locations and preemption rights, especially in reference to the
Indian title. By the third section of this act, it was enacted that
every settler on the public lands south of the Arkansas River
should be entitled to the same benefits accruing under the Act of
1814 as though they had resided north of said river. What does this
mean? We know the fact that the lands north of the Arkansas had
been ceded to the United States by the Great and Little Osages by
the treaty of 1808, and that the Indian title, therefore, was
extinguished in 1814. Does the act mean that the settlers south of
the river should have the same benefit as if the Indian title had
been extinguished in and prior to 1814? If it meant this, why did
it not say it? But supposing that the act had this effect, so that
the objection arising from the Indian title was removed, the act
still left unshaken the reservation made by the Act of 1832. This
act is absolute in its terms. It contains no saving clause. It
declares that the hot springs shall be reserved for the future
disposal of the United States, and that they shall not be entered,
located, or appropriated for any other purpose whatever. This
positive prohibition would have prevented the representatives of
Percifull from availing themselves of any benefit which the removal
of the obstacle arising from the Indian title gave them. Entry and
location were still necessary to give them title.
The counsel for Hale, however, strenuously contends that the Act
of 1843 was intended to validate the preemption claim of Percifull
to the property in question, and that it must be construed to
effect a repeal of the Act of 1832 by implication. In
Page 92 U. S. 705
favor of this view he alleges as a fact that this was the only
case to which the act could apply. We cannot know this. There is
nothing on the face of the act to indicate it. If it was intended
to repeal the Act of 1832 and to confirm Percifull's title, why was
it not so expressed? A plain word or two would have done it. If
such had been the legislative intent, we cannot believe that this
intent would have been left in such deep obscurity, and dependent
on so many implications. The act of 1832 expressed very clearly the
intent of Congress to reserve the hot springs from private
appropriation. If the Act of 1843 was intended to revoke this
reservation, it ought to have been expressed with like
clearness.
But besides these legal obstacles in the way of this claim, it
is not clear from the evidence that Percifull came within the
description of the Act of 1814. He resorted to the hot springs
temporarily during the visiting season, to deal in such articles as
the persons who frequented the place for their health needed. When
they left, he left. If he erected shanties or cabins, it was not
for the purpose of permanent residence, but for temporary
accommodation. His actual residence was several miles distant.
There is no clear evidence of an intent on his part at that time
(1814) or previously to make this retired spot in the Indian
country his home.
We think this claim cannot be maintained either at law or in
equity. Whatever hardship exists in the case must be submitted to
the just consideration of the government.
2. William H. Gaines and wife and others, as heirs of one
Ludovicus Belding, claim the same quarter-section as is claimed by
Hale, by virtue of an alleged residence and settlement on the land
in 1829 and 1830, under the Preemption Act of May 29, 1830, 4 Stat.
420. This was a general act, and declared that every settler or
occupant of the public lands prior to its passage, who was then in
possession, and cultivated any part thereof in the year 1829, might
enter with the register of the land office for the district in
which such lands should lie, by legal subdivisions, any number of
acres not more than one hundred and sixty, or a quarter-section, to
include his improvements, upon paying to the United States the
minimum price, with a proviso that no entry or sale of any land
should be made under the act which
Page 92 U. S. 706
should have been reserved for the use of the United States, or
either of the states. Other provisions of the act as well as that
here recited demonstrate that it was only intended to apply to
lands which had been publicly surveyed. By its very language it
could apply to no other. It evidently did not apply to the lands in
question. They were not surveyed until 1838. The act contained the
further provision that it should remain in force for one year. It
ceased to have effect, therefore, on the 29th of May, 1831. On the
20th of April, 1832, the act was passed reserving the hot springs.
But the heirs of Belding rely on the Act of July 14, 1832, 4 Stat.
603, by which it was declared that all occupants and settlers upon
the public lands of the United States who were entitled to a
preemption according to the Act of 1830 and had not been able to
make proof and enter the same within the time limited therein in
consequence of the public surveys not having been made and
returned, or where the land was not attached to any land district,
or where the same had been reserved from sale on account of a
disputed boundary between any state and territory, should be
permitted to enter said lands on the same conditions in every
respect as were prescribed in that act, within one year after the
surveys were made, &c. It is difficult to see how this act can
aid the claimants. The conditions of the Act of 1830 are not only
not waived, but they are expressly reimposed. One of those
conditions, as seen above, was, that no entry or sale of any land
should be made which should have been reserved for the use of the
United States or either of the states. This very thing had been
done by the reservation of the hot springs by the Act of 1832. No
vested right had accrued to Belding before that reservation, for
the preemption act of 1830 did not extend to the lands in question
until the passage of the Act of July, 1832, even if a vested right
could be set up against the government before entry and location.
The counsel for the claimants, however, bases an ingenious argument
upon that phrase in the act reserving the hot springs, by which
they are reserved "for the future disposal of the United States."
He supposes that this differs from a reservation "to the United
States." And as they are only reserved for future disposal, it may
well be said that such disposal was made by the Act of
Page 92 U. S. 707
July 14, 1832, in subjecting them to the right of preemption
given by the Act of 1830. But this argument is too far-fetched and
circuitous. In the first place, we think that a reservation for the
future disposal of the United States was a reservation to the
United States. And in the next place, that Congress could hardly
have entertained an intent to dispose of the Hot Springs
Reservation by any such general phraseology as that which was
employed in the Act of July 14, 1832. Certain reservations are
expressly referred to in the act as no longer to be in the way of
preemption, and the express mention of these makes the omission of
others more emphatic. The argument of the counsel would have the
effect of defeating all governmental reservations made between
April, 1830, and July, 1832, for the United States had the power of
disposing of all of them, whether expressly retained or not.
Without referring, therefore, to the character of Belding's
occupation, his want of title, either legal or equitable, is
manifest upon the face of the statutes under which he claims, taken
in connection with the Act of April 20, 1832, reserving the
property to the government. If it were necessary to examine his
mode of occupation, it would be open to some very just criticism,
for which it is sufficient to refer to the opinion of the court
below.
3. The remaining title is that claimed by Henry M. Rector (and,
under him, Russell), under a New Madrid location, in right of
Francis Langlois. The earthquake or succession of earthquakes which
occurred along the Mississippi below the mouth of the Ohio in 1811
and 1812, was particularly disastrous to the county and village of
New Madrid, in Missouri Territory (then the District of Louisiana),
leaving a large portion of the land now known as the "sunk country"
under water. For the relief of the inhabitants, Congress, on the
17th of February, 1815, passed an act authorizing those whose lands
had been materially injured by earthquakes to locate the like
quantity of land on any of the public lands of the said territory
the sale of which was authorized by law. It was provided, however,
that no person should be permitted to locate a greater quantity
than he had before, except where that was less than one hundred and
sixty acres, and in no case a greater
Page 92 U. S. 708
quantity than six hundred and forty acres; and that, in every
case where such location should be made according to the provisions
of the act, the title of the person or persons to the land injured
should revert to and become absolutely vested in the United States.
By the second section of the act, proof of the applicant's title to
the lands injured was required to be made to the recorder of land
titles for the Territory of Missouri, who thereupon was to issue a
certificate of the party's right. A location being selected, and
the certificate being presented to the principal deputy surveyor of
the territory, it became his duty to cause a survey thereof to be
made and to return a plat of the location made to the recorder,
together with a notice in writing designating the tract thus
located, and the name of the claimant on whose behalf it was made,
which notice and plat the recorder was required to have recorded in
his office. By the third section it was made the duty of the
recorder to transmit a report of the claims allowed, and locations
made under the act, to the Commissioner of the General Land Office,
and to deliver to the party a certificate stating the circumstances
of the case, and that he was entitled to a patent for the tract
designated. This certificate being presented to the land office, a
patent was issued for the land.
These are the substantial provisions of the act. As apparent on
its face, it required the following steps to be taken:
1. Application to the recorder of land titles showing the
party's claim and praying a certificate of location.
2. Certificate of location issued by the recorder showing the
amount of land to which the applicant was entitled.
3. Application to the surveyor presenting the certificate of
location, and designating the lands which the party desired to
appropriate.
4. Survey and plat made by the surveyor.
5. Return of the survey and plat to the recorder of land titles
to be filed and recorded, with a notice designating the tract
located and the name of the claimant.
6. Certificate of the recorder stating the facts and that the
party was entitled to a patent.
7. Transmission of this certificate to the General Land
Office.
8. The patent.
Page 92 U. S. 709
In addition to these requisites, the land thus appropriated must
be located on the public lands of the territory the sale of which
was authorized by law.
It is shown by the claimant that Francis Langlois was the owner
of a tract of two hundred arpents of land (about one hundred and
seventy acres), in the County of New Madrid, which was materially
injured by the earthquakes. It is also satisfactorily shown that
application was made on his behalf on the 26th of November, 1818,
to the recorder of land titles at St. Louis, for a certificate of
location of a like quantity of lands, and that the said recorder
did on that day grant and issue to him a certificate accordingly
(being certificate No. 467), stating that Langlois or his legal
representatives were entitled to locate two hundred arpents of land
on any of the public lands of the Territory of Missouri the sale of
which was authorized by law. It also seems that Langlois at the
same time, by his attorney, executed a release to the United States
of his said lands in New Madrid. As this, however, was not
necessary, inasmuch as the New Madrid land would revert to the
United States on the completion of the substituted title to other
lands of like amount, under the act, it could have no effect on the
validity of Langlois' title to the lands which he sought in
exchange therefor. The certificate of location thus procured from
the recorder was subsequently assigned to other parties, and came
to the hands of Samuel Hammond and Elias Rector, under whom the
present claimant deraigns title. In January, 1819, Hammond and
Rector made formal application to the surveyor general (the officer
who succeeded the principal deputy surveyor) for the entry of two
hundred arpents of land to satisfy certificate No. 467, to be
surveyed in a square tract, with lines corresponding to the
cardinal points of the compass so as to include the said hot
springs, as near the center of the square as circumstances would
admit. This application was in writing, and was filed in the office
of the surveyor general, who directed James S. Conway, a deputy
surveyor, to make the survey. Thereupon Conway made the survey as
requested, and on the 16th of July, 1820, made out a plat and
descriptive statement of the same, which he numbered "Survey No.
2903, Certificate 467." This survey was deposited by the deputy in
the office of the
Page 92 U. S. 710
surveyor general at St. Louis; but it was not recognized or
recorded by the surveyor general, nor was it returned to the
recorder of land titles. Of course no patent was obtained upon
it.
Subsequently, in 1838, when the public surveys were extended to
that region, the then surveyor general in his instructions to the
deputy surveyor who prosecuted the work, whether on Rector's
application does not clearly appear, directed him to survey for
Francis Langlois or his legal representatives a tract of two
hundred arpents, having the main spring in the center, according to
the location of New Madrid certificate No. 467, which would be
furnished to him. The survey was made and returned accordingly, and
duly returned to the office of the recorder of land titles, who
issued a patent certificate thereon. No patent, however, was ever
issued on this location, as it was made subsequent to the Act of
April 20, 1832, reserving the hot springs and surrounding lands to
the United States. This act clearly rendered void all subsequent
appropriations of land unless it was repealed by the Act of 1843
before referred to. The first section of that act declared that the
locations of warrants issued under the Act of Feb. 17, 1815
(relating to sufferers at New Madrid), on the south side of the
Arkansas River, if made in pursuance of the provisions of that act
in other respects, should be perfected into grants in like manner
as if the Indian title to the lands on the south side of said river
had been completely extinguished at the time of the passage of said
act.
Attorney General Cushing, in an opinion on this title given in
1854, pertinently remarks that the only obstacle removed from the
New Madrid locations by this act was that of the existence of the
Indian title at the time of the passage of the Act of 1815. No such
title existed when the survey was subsequently made, and if that
were the only objection to the title in question, it would be
entitled to recognition. But there stands the Act of 1832 reserving
the lands to the United States. Unless, therefore, the title of
Rector, or those whose estate he represents, became fixed and
vested as against the government before the passage of that act, so
as to make the act obnoxious to the objection of taking private
property without just compensation,
Page 92 U. S. 711
it cannot be maintained. Hence it is all important to ascertain
the effect of the survey made for Hammond and Rector in 1820.
As before observed, that survey was not recognized nor recorded
in the surveyor general's office, nor returned to, nor recorded in,
the office of the recorder of land titles. It is proper to consider
the reasons why this was not done.
The difficulty was this: the act for the relief of the sufferers
of New Madrid required that the lands to be given to them in
exchange for their injured lands should be located on public lands
of the territory "the sale of which was authorized by law." Mr.
Wirt, the then attorney-general, gave it as his opinion that no
lands were authorized by law to be sold which had not been publicly
surveyed, according to the general system of sections and
townships; and as the region in which the hot springs were located
was subject to the Indian title until 1818, and had never been
publicly surveyed, no lands could be located there under a New
Madrid claim in 1820, when the attempt was made by Hammond and
Rector as above stated. This opinion of the Attorney General was
followed by the General Land Office, and patents were refused for
any lands thus attempted to be located. Hence the surveyor general
did not recognize the survey of Conway, and never returned it to
the recorder.
Vide Wirt's Opinions, 1 Opin. 361, 372.
But on the 26th of April, 1822, Congress passed an act, entitled
"An Act to perfect certain locations and sales of public lands in
Missouri," by which it was enacted that the locations theretofore
made of warrants issued under the Act of Feb. 15, 1815 (the act for
the relief of the New Madrid sufferers), if made in pursuance of
the provisions of that act in other respects, should be perfected
into grants in like manner as if they had conformed to the
sectional or quarter-sectional lines of the public surveys; and the
sales of fractions of the public lands theretofore created by such
locations should be as valid and binding on the United States as if
such fractions had been made by rivers or other natural
obstructions, and the second section of the act declared that
thereafter the holders and locators of such warrants should be
bound, in locating them, to conform to the sectional and
quarter-sectional lines of the public
Page 92 U. S. 712
surveys, and that all such warrants should be located within one
year after the passage of the act.
In delivering the opinion of this Court in
Barry v.
Gamble, 3 How. 52, where the construction and
effect of this act were brought under review, Mr. Justice Catron
considered that the act only had reference to lands which had not
been surveyed when the imperfect locations were made and had been
surveyed prior to the passage of the act, for, in making provision
for the fractions created by such irregular surveys, reference is
only made to fractions "heretofore created." If this view of the
act is correct, it decides the case, for the public surveys were
not extended to these lands until long after 1822 -- namely, 1838.
As this was not the point involved in that case, however, it is
proper to look further in reference to the effect of the Hammond
and Rector survey of 1820.
The petitioner's counsel insist that the Act of 1822 removed the
objection that the location did not conform to the public surveys,
without reference to the time when those surveys were or might be
made, whether before or after the date of the act.
Conceding for the sake of the argument that this may be the true
construction of the act, what is it that the act saves? It is
"locations."
"The location heretofore made, of warrants issued under the act
&c., if made in pursuance of the provisions of that act in
other respects, shall be perfected into grants,"
&c. By the second section, locations thereafter to be made
were to conform to the sectional and quarter-sectional lines. It
becomes important, therefore, to know what is meant by a location
in the Act of 1815. It evidently meant a completed location. When
the land became located, the title of the applicant to his New
Madrid lands at once reverted to the government. The words of the
act are:
"In every case where such location shall be made according to
the provisions of this act, the title of the person or persons to
the land injured as aforesaid shall revert to and become absolutely
vested in the United States."
Now when did this take place? Certainly not on the mere
application to the surveyor general to survey the tract which the
party desired to appropriate. nor when the surveyor had
Page 92 U. S. 713
planted his last stake or heap of stones on the ground, nor when
he had returned home with his notes in his pocket, nor when he had
made out his survey and plat. This survey and plat did not belong,
the instant they were finished, to the applicant; neither did the
land, until something more was done. What was that something more?
The act tells us that the surveyor must return the survey and plat,
and the notice as to the party for whom the survey was made, to the
office of the recorder of land titles, to be by him filed and
recorded. Then, and not till then, the applicant was entitled to a
patent. Then the land first became appropriated. It then first
appeared on the records of the country as his. This point has been
repeatedly adjudged by this Court, and has become part of the
established land law of the country, and we should do a great wrong
at this late day to shake it.
Bagnell v.
Broderick, 13 Pet. 436;
Stoddard
v. Chambers, 2 How. 284;
Barry v.
Gamble, 3 How. 32;
Lessieur
v. Price, 12 How. 60;
Hale v.
Gaines, 22 How. 144;
Rector v.
Ashley, 6 Wall. 142;
Mackay
v. Easton, 19 Wall. 633. In the last case, the
Court, MR. JUSTICE FIELD delivering the opinion, says as
follows:
"The act of Congress . . . declared that when a location was
made under its provisions, the title of the person to the land
injured should vest in the United States. It contemplated that
there should be a concurrent investiture of title; that the title
of the owners of the land injured in New Madrid County should pass
to the United States, and that at the same time the title to the
land located in lieu thereof should pass to the claimant, or rather
the right of the title, for the strict legal title did not pass
until the patent issued, and that this exchange of titles should
take place when the claimant obtained his patent certificate, or
the right to such certificate, and that he could not acquire until
the plat of the survey was returned to the recorder of land titles.
Until the plat was placed in the public depository in the
territory, of evidences of title issuing from the United States,
there was no official recognition of the proceedings taken by the
claimant which bound the government."
A brief reference to the history of land titles in the Louisiana
country will show the ground and reason for the importance attached
to a return of the survey to the office of the recorder
Page 92 U. S. 714
of land titles. It is well known that the territory purchased of
the French government in 1803 was, in the following session of
Congress, divided into two territories -- one called the Territory
of Orleans, comprising West Florida and the present State of
Louisiana, and the other, called the District of Louisiana, and
comprising the whole region west of the Mississippi and north of
that state. Act March 26, 1804, 2 Stat. 283. The treaty by which
this territory was acquired, guaranteed, on the part of the United
States, to the inhabitants the free enjoyment of their liberty,
property, and religion. The land titles which had been perfected
and located by surveys offered no difficulties, but there were many
inchoate titles which had never been perfected, which by the laws
of France and Spain the claimants had a right to perfect. In order
that the government of the United States might know what claims it
was bound in good faith to respect, measures were taken to have all
outstanding claims brought in and recorded and located by surveys
where these should be necessary. By the Act of March 2, 1805, 2
Stat. 324, the Territory of Orleans was divided into two land
districts, for each of which a register was appointed; but for the
District of Louisiana an officer was created, called the Recorder
of Land Titles, who continued for many years to exercise important
functions in regard to the public lands in the district even after
the appointment of a surveyor and of registers and receivers under
the general land laws. The act referred to required every person
claiming lands, whether by complete or incomplete title, within a
limited time to deliver to the registers of Orleans, or to the
recorder of land titles of the District of Louisiana, a notice of
his claim, with a plat of the tract claimed, and also his grant,
order of survey, or other written evidence of his claim, which
documents the said registers and recorder respectively were to
record in proper books. Claims not so presented and recorded within
the proper time were to be barred as against grants from the United
States. The act further provided for the appointment of two
additional persons in each district, to act with the register or
recorder as a board of commissioners to examine and decide upon the
claims which should be presented, whose duty it was, after
deciding, to report their decisions to Congress, and
Page 92 U. S. 715
to deposit the same, with all the evidence and documents, in the
offices of the register and recorder respectively within whose
district the lands lay. At a later period, the additional
commissioners were dispensed with and the powers of the board were
vested in the register and recorder respectively. The reports of
these commissioners and the acts of Congress confirmatory thereof
formed the basis of the titles derived from the French and Spanish
authorities. And this constitution of the office and duty of the
recorder of land titles in the District of Louisiana led to the
importance subsequently attached to the return and registration of
other surveys in the same office. It was there that the officers of
the government looked, or were supposed to look, for all authentic
claims to land in the district. No lands were supposed to be
appropriated or segregated from the public domain unless recorded
or registered there.
Now the difficulty in this case is that the survey of 1820 was
never returned to the recorder's office, and therefore this land
never became located within the meaning of the Act of 1815 or the
Act of 1822. It never became segregated from the public domain. It
never became so appropriated to the claimants as to give them a
vested right and prevent the operation of the Act of April 20,
1832, by which it was reserved to the United States.
But the claimant insists that this was not the fault of Hammond
and Rector, that they did all they could do, and that the surveyor
general could not, by neglecting his duty -- namely, that of
recording the survey and returning it to the recorder of land
titles -- deprive them of their just rights. But when the survey
was made, the Act of 1822 was not in existence; the laws then were,
as the Attorney General held them to be, that unsurveyed lands were
not lands the sale of which were authorized by law; and as this
doctrine was received and acted upon by the land department of the
government, we should not feel authorized at this late day to
reverse it. And it is not shown that any further efforts were made
to have the location perfected until after the passage of the Act
of 1832. If at any subsequent time it became the duty of the
surveyor general to return the survey to the recorder's office, no
application for that purpose seems to have been made. A clear duty
on his part could have
Page 92 U. S. 716
been enforced by mandamus had he refused to perform it. But it
is unnecessary to speculate. Nothing further was done, and no
vested right accrued under the claim.
In conclusion, we feel bound to decide that none of the
claimants are entitled to the lands in question. The claims
advanced all depend on one or other of the titles which we have
considered, and all are equally untenable. Whatever hardship, if
any, may ensue from this declaration of the law of the case, we
have no doubt will be duly taken into consideration by the
legislative department of the government in dealing with the
subject of the future disposition of those lands.
It is just to say that we have been much aided in the
investigation of this case by the able arguments of the counsel on
both sides and by the elaborate opinion of the Court of Claims,
which supersedes the necessity of our going more into detail in the
discussion of the various questions involved.
Decree affirmed.