1. A., who had undertaken to build a railroad for a company,
entered July 18, 1872, into a sealed contract with B. for building
a hundred and sixty miles of the road. The contract, among other
things, provided that B. should complete the first section, of
forty miles, on or before the first day of September then next
ensuing; the third section, of twenty miles, by the fifteenth day
of that month; the fourth section, of twenty miles, on the
fifteenth day of the following November; the fifth section, of
twenty miles, on the fifteenth day of December, and so on, the
whole to be completed May 1, 1873. Payment was to be made to B. as
the work progressed, the 15th of each month, on monthly estimates,
by the engineer of the railroad company, of the work done the
previous month, except fifteen percent after the completion of
forty miles, which was to be retained as security for the
performance by B. until the work should be completed, and to be
forfeited to A., and applied to any claim for damages which he
might sustain by the failure of B. to have the stipulated work
completed at the time specified. Fifteen percent of the estimates
on the first forty miles, and a liquidated sum of $15,000 agreed to
be paid for extra work on that section, were to be retained as
security for the completion of the first sixty miles. B. failed to
finish any portions of the work by the specified time, but A.,
although authorized by the contract to declare it forfeited,
excused the failure, paid B. the estimate for the work then done,
and permitted him to proceed with the work. B. continued to do so
until A. failed to pay the large sums due him by the estimates for
work done in October and November. B. then learned from A. that the
latter was unable to pay those estimates, and would probably be
unable for a time to pay future monthly estimates. B. thereupon
ceased to do any further work and brought this suit.
Held:
1. that the declaration of B. was sufficient on demurrer, as it
averred, in substance, that from the time he entered upon tie
performance of the contract in July, 1872, until the fifteenth day
of December of that year, when A. wholly failed to make the
stipulated payment for tire work then actually done, he, with a
large force and with suitable equipments along the whole line of
the road, had prosecuted the work with all the energy and skill
that be possessed, and that A. had expressed satisfaction at the
manner in which the work was done; 2. that A. so far waived
absolute performance on the part of B. as to consent to be liable
on his covenant for the contract price of the completed work, but
did not waive his right to whatever damages he may have sustained
by the failure of B. to perform
Page 91 U. S. 647
such work by the specified time, and that A. might set up such
damages by way of cross-demand against B; 3. the court below erred
in charging the jury that time was not of the essence of the
contract sued on, and that such damages could not, therefore, be
recovered, but, inasmuch as there was no legal evidence of such
damages, the misdirection of the court worked no prejudice to A.,
and affords no ground for reversing the judgment; 4. that B. was
not required, after A. had defaulted on a payment due, to proceed
with the work at the hazard of further loss, and that he was
entitled to recover the contract price of the work done, together
with the fifteen percent on the estimates, and the $15,000, both of
which had been retained by A. as a security for B.'s performance of
the contract.
2. In an action of covenant, evidence of a parol contract is
inadmissible. Had the declaration averred such a contract, it would
have been bad on demurrer in the courts of Illinois, as the common
law rules of pleading and the distinction between forms of action
prevail in that state.
3. Fifty-two assignments of error were filed in this case. The
Court condemns such a practice as a flagrant perversion of the rule
on that subject.
MR. JUSTICE MILLER delivered the opinion of the Court.
The plaintiff in error, who was defendant in the circuit court,
is a corporation organized under the laws of Wisconsin. It had
undertaken to build the whole or a large part of the Wisconsin
Central Railroad, and had made contracts with the defendants in
error, whom we shall hereafter call plaintiffs, as they were in the
circuit court, for the construction of a part of this road. These
contracts were drawn with the minuteness of detail usual in such
cases, and provided, among other things, that payments should be
made by defendant, as the work progressed, on estimates made
monthly by the engineer of the railroad company, on the fifteenth
day of each month, for all the work done the previous month, except
fifteen percent retained by defendant as security for performance
on the part of plaintiffs until the work was completed.
The plaintiffs brought their action of covenant on these
contracts, alleging that they had commenced the work in the month
of July, 1872, shortly after the contracts were signed,
Page 91 U. S. 648
and prosecuted it vigorously until some time in December; that
defendant had failed to pay the large sums due by the estimates for
work done in October and November, and, seeing no prospect of
payments, plaintiffs were compelled to abandon the work and bring
this suit. They assert a claim for all the work done as estimated,
and for various items of damage suffered by them in consequence of
this failure of defendant to comply with its covenant to pay as
agreed.
A demurrer to this declaration having been overruled, defendant
filed fifteen pleas in bar, also an amended plea, and on these
numerous issues of fact were finally joined.
A verdict and judgment were rendered in favor of plaintiffs for
$119,061.46, to reverse which this writ of error is brought.
In this Court, plaintiff in error, by one counsel, files
forty-five assignments of error, and by another seven more, making
fifty-two in all.
The object of the rule requiring an assignment of errors is to
enable the court and opposing counsel to see on what points the
plaintiff's counsel intend to ask a reversal of the judgment, and
to limit the discussion to those points. This practice of unlimited
assignments is a perversion of the rule, defeating all its
purposes, bewildering the counsel of the other side, and leaving
the court to gather from a brief, often as prolix as the
assignments of error, which of the latter are really relied on. We
can only try to respond to such points made by counsel as seem to
be material to the judgment which we must render.
Before we proceed to this examination, however, it may be as
well to say that in addition to a general verdict in favor of
plaintiffs for $107,353.44, the jury made three special findings on
matters suggested by the court. These are:
1. That at the time of the alleged breach of covenant by
defendant, it had waived or excused the failure of plaintiffs up to
that time to complete certain parts of their work within the times
stipulated in the contract, and that plaintiffs were at the time of
said breach engaged in the performance of said work with the
consent of defendant.
2. That defendant, at the time plaintiffs stopped the work, had
given plaintiffs to understand that defendant was financially
Page 91 U. S. 649
unable to pay the estimates for work then done, and would
probably be unable for a time to pay future monthly
installments.
3. That defendant had agreed to pay plaintiffs the extra cost of
doing the earth work by train on certain sections, and that the
amount of this extra cost was $11,708.
These findings must be presumed to be in accordance with the
facts, and must stand as foundations for the judgment of the court
unless it can be shown that they are affected by some erroneous
ruling of the court in regard to the admission of evidence or
instructions to the jury.
We now proceed to notice such objections to the rulings of the
circuit court as we deem of sufficient importance to require
it.
1. It is said that the declaration is fatally defective because
it does not aver that the plaintiffs were ready, willing, and able
to perform the covenants on their part to be performed by the
contract. It is true that this might have been alleged in more
formal and apt terms than it is. But they do aver that from the
time they entered upon the work in July until the fifteenth day of
December -- the day of the alleged breach on the part of defendant
-- they prosecuted the same with all the energy and skill they
possessed, having men in large numbers -- to-wit, more than 1,000
-- with suitable teams and other equipments, along the whole line
of the road of 160 miles, and that defendant had expressed entire
satisfaction with the manner in which plaintiffs were doing the
work.
We are inclined to think that, coupled with the allegation that
defendant was in default for nonpayment for work actually done,
this was sufficient. It is not like a case where a plaintiff has
done nothing, but is required to put a defendant in default by
offering to perform or showing a readiness to perform. Plaintiffs
here had already performed, and the defendant failed to do its
corresponding duty under the contract, and, defendant having
defaulted on a payment due, plaintiffs are not required to go on at
the hazard of further loss.
2. By the terms of the contract, plaintiffs bound themselves to
complete the first section of forty miles by the first day of
September; the third section of twenty miles by the fifteenth
Page 91 U. S. 650
day of the same month; the fourth section of twenty miles by the
fifteenth day of November, and so on, and it is conceded that no
one of these sections was completed within the time prescribed. It
was also agreed that if plaintiffs failed in this respect, or
failed in the opinion of the engineer-in-chief of the railroad
company to prosecute the work with sufficient vigor to completion
according to the terms of the contract, the defendant might declare
it abandoned and the amount retained out of the monthly estimates
forfeited. This was fifteen percent of each monthly estimate,
which, by the agreement, was retained by defendant as security for
the due progress of the work.
The main proposition underlying the whole argument of the
defense on the general merits is that these covenants to complete
certain sections within a definite time, and the covenant to pay,
are mutual and dependent covenants, and that time is so far of the
essence of this covenant of plaintiffs that they can recover
nothing, because they completed nothing within the specified
time.
Where a specified thing is to be done by one party as the
consideration of the thing to be done by the other, it is
undeniably the general rule that the covenants are mutual and are
dependent if they are to be performed at the same time, and if, by
the terms or nature of the contract, one is first to be performed
as the condition of the obligation of the other, that which is
first to be performed must be done or tendered before that party
can sustain a suit against the other. There is no doubt that in
this class of contracts, if a day is fixed for performance, the
party whose duty it is to perform or tender performance first must
do it on that day or show his readiness and willingness to do it or
he cannot recover in an action at law for nonperformance by the
other party.
But, both at common law and in chancery, there are exceptions to
this rule growing out of the nature of the thing to be done and the
conduct of the parties. The familiar case of part performance,
possession &c., in chancery, where time is not of the essence
of the contract or has been waived by the acquiescence of the
party, is an example of the latter, and the case of contracts for
building houses, railroads, or other large and expensive
constructions, in which the means of the builder and
Page 91 U. S. 651
his labor become combined and affixed to the soil or mixed with
materials and money of the owner, often afford examples at law.
If A. contract to deliver a horse to B. on Monday next, for
which B. agrees to pay $100, A. cannot recover by an offer to
deliver on Tuesday; but if A. agree to deliver a horse, buggy, and
harness on Monday, and B. accepts delivery of the horse and buggy,
can he refuse to pay anything, though he accepts delivery of the
harness on Tuesday? This is absurd. He waives, by this acceptance,
the point of time as to the harness, at least so far as A.'s right
to recover the agreed sum is concerned. If B. have suffered any
damage by the delay, he can recover it by an action on A.'s
covenant to deliver on Monday; or, if he wait to be sued, he may
recoup by setting it up in that action as a cross-demand growing
out of the same contract.
Such we understand to be especially the law applicable to
building contracts.
If the builder has done a large and valuable part of the work,
but yet has failed to complete the whole or any specific part of
the building or structure within the time limited by his covenant,
the other party, when that time arrives, has the option of
abandoning the contract for such failure, or of permitting the
party in default to go on. If he abandons the contract, and
notifies the other party, the failing contractor cannot recover on
the covenant, because he cannot make or prove the necessary
allegation of performance on his own part. What remedy he may have
in assumpsit for work and labor done, materials furnished &c.,
we need not inquire here, but if the other party says to him, "I
prefer you should finish your work," or should impliedly say so by
standing by and permitting it to be done, then he so far waives
absolute performance as to consent to be liable on his covenant for
the contract price of the work when completed.
For the injury done to him by the broken covenant of the other
side, he may recover in a suit on the contract to perform within
time, or, if he wait to be sued, he may recoup the damages thus
sustained in reduction of the sum due by contract price for the
completed work.
It is said on the other side in this case that the right of
the
Page 91 U. S. 652
defendant to abandon the contract and retain in its hands the
fifteen percent is its only remedy, and that that has been waived.
We need not decide this point here, for we are only answering the
argument that plaintiffs have lost all right to sue on the contract
by their failure to complete the sections in the times named.
As it is perfectly clear from the testimony that defendant, at
the time these several sections should have been completed, made no
point of the failure to do so, but urged the plaintiffs to go on,
expressed satisfaction at the manner in which the work was
progressing, and paid the estimate after such failure, the verdict
of the jury, that defendant had waived strict performance as to
time, was so far well founded as to enable plaintiffs to recover
for work actually done.
3. This is an appropriate place to dispose of another objection.
Defendant set up in its pleas and offered evidence to prove the
damage sustained by those delays.
But the court instructed the jury that under this covenant time
was not of the essence of the contract; that on that point it was
flexible, and defendant could not recover for the delay. As we have
stated above, we are inclined to the opinion that defendant did
not, by any of the acts proved in this case, waive its right to
damages arising from this failure of the plaintiffs to complete the
sections in time, but only waived the forfeiture, if it may be so
called, of all right on the part of plaintiffs to sue. But an
attentive examination of the testimony offered and of the charge of
the court on that subject shows that no legal evidence of any
damage was offered.
The attempt was to show that by the use of the road at an
earlier day, much profit would have resulted. But the witness
stated that the road ran through a wild uninhabited country; that
he expected that saw mills would have been established along the
line of the road, and the transportation of lumber incident to the
use of such mills would have made the defendant a profit of
$20,000.
The whole basis of this calculation is conjectural, uncertain,
and vague. It is manifestly no safe basis on which it can be
assumed that any business would have been done in the few days of
the delay, or that, if done, it would have been done at
Page 91 U. S. 653
a profit. There was nothing on which a jury could have done
anything but conjecture and speculate at the hazard of sacrificing
truth and justice.
There was therefore no error to defendant's prejudice in this
part of the case.
4. It is said that the court erred in admitting evidence on the
part of plaintiffs of the profits they would have made on the
remaining part of the road if defendant had paid, so that they
could go on.
Whether the evidence which was given on this subject was
admissible or not was rendered immaterial by the subsequent ruling
of the judge, who instructed the jury to disregard it and to allow
plaintiffs nothing on the ground of such supposed profits, and it
is manifest from the record that nothing was allowed for this in
the verdict.
5. The foregoing are the material objections, which are of a
general character, to the rulings of the court. The items for which
the general verdict ($107,353.44) was had may be divided into three
classes:
I. An agreed sum of $15,000, which was to be paid on the
completion of the first sixty miles of the road by the terms of the
contract, and which was exclusive of the estimates for work done.
Defendant resisted this on the ground that plaintiffs, not having
finished the sixty miles, could not recover it in this action, and
also because they had abandoned the work.
In the view we have already expressed, neither of these
objections is sound. If, by defendant's breach, plaintiffs were
justified in abandoning the work, then they were entitled to all
they had earned under that contract, including the $15,000; because
the $30,000, of which this $15,000 was part, was a liquidated sum
agreed upon as compensation for extra work on the first forty miles
of the road which had been completed, and was only withheld, like
the fifteen percent, as security for the future performance by
plaintiffs.
Defendant, having by its default terminated the work, had no
longer any right to retain either of these sums.
II. The next class consisted of the estimates under the
contract, which were unpaid. This is by far the largest item of the
verdict, and no serious contest is made except as to $19,937.55,
which constituted the reserved fifteen percent already
mentioned.
Page 91 U. S. 654
As in the case of the $15,000, we are of opinion that since the
work was abandoned and the contract, by reason of the breach
thereof by the defendant, ended, it can have no right to retain any
part of the estimates for work actually performed. This was to be
retained as a security against failure or default of
plaintiffs, and cannot be held by
defendant after
its own default has caused the abandonment of the work.
III. The third class is composed of a large number of items of
damages incidental to the abrupt cessation of the work by reason of
defendant's failure to pay -- such as loss of material, supply
road, shanties, travel of hands, depreciation in value of tools,
materials &c. We cannot go into all these. After mature
consideration of the very full briefs and arguments on these
matters, we see no error in any ruling of the court in regard to
them, and so dismiss their further consideration.
6. A more difficult point remains to be considered.
The plaintiffs were allowed to introduce evidence to prove that
the defendant had made a verbal promise to pay the extra cost of
doing by train the earth work of the sections between 40 and 46,
and the jury found a special and separate verdict that it had so
promised and that this extra cost was $11,708.
There is no allegation of this promise in the declaration, which
is an action of covenant on the sealed agreement. There is no
allusion to it, or provision for it, in that instrument. It is
found by the special verdict to be a promise, and the record shows
that it was by parol. Defendant objected to the admission of the
evidence of this contract on the specific ground that if valid, it
could be enforced in assumpsit only, and not in an action founded
solely on the specialty.
The work done under the written contract could be estimated by
the engineer, because a price was fixed by it for everything. He
had only to ascertain quantities, apply the prices, and ascertain
the amount to be paid. For this extra cost of a special mode of
doing part of the work, he had no elements out of which to make an
estimate.
It is certainly opposed to the common law system of pleading
which prevails in the Illinois circuit -- to join the actions of
covenant and assumpsit. If this had been done in the declaration,
the defendant could have successfully demurred.
Page 91 U. S. 655
It is equally clear that covenant cannot be sustained on a
verbal promise. Can the plaintiffs be allowed to prove a cause of
action, which, if alleged in the declaration, would have been fatal
to it on demurrer? and can they recover in an action of covenant on
a special parol promise?
The judge below said he would not hazard the general verdict by
permitting this matter to be embraced in it. He took the special
verdict and, notwithstanding his doubts, embraced the amount of it
in the final judgment.
This matter grows immediately out of, and is intimately
connected with, the work done under the written contract. It is
merely a verbal agreement that if the plaintiffs would do the work
in a manner different from their obligation, more advantageous to
defendant, and more expensive, defendant would pay this difference
in expense. It seems reasonable that the claim for this extra cost
should be decided in the suit in which the other compensation for
the same work is recovered; that plaintiffs, having proved their
case and recovered a verdict, should not be compelled to resort to
a new suit in which this verdict would stand for nothing. Only a
rule of pleading stands in the way, in this Court, of doing what
the very right of the case requires. We can give the plaintiffs
their judgment for the amount of the general verdict, and reject
this, or we can do complete justice and affirm the judgment of the
circuit court in full.
But the State of Illinois has adhered to the system of pleading
which recognizes the lines that separate the forms of action at
common law, and the act of Congress requires the circuit courts to
conform to the mode of pleading of the state in which the court
sits. Undoubtedly there was error under that system in admitting
proof of a parol contract of this kind in an action of covenant,
and as the defendant made this precise objection, and took an
exception when overruled, we do not see how we can refuse to give
it the benefit of its objection. In those states where the
distinction between forms of action have been abolished, the
declaration could have been amended, and the two matters joined in
the same action. In that case, we might, under the statute of
jeofails, disregard the error as one capable of removal by
amendment below, and as cured by verdict and judgment when it comes
here.
Page 91 U. S. 656
But sec. 954 of the Revised Statutes, which was sec. 32 of the
Judiciary Act of 1789, was founded on the English statute of 32
Henry VIII., and is no broader. This act of Congress has been
frequently construed by this Court in such a manner as to forbid
its application to the case before us.
Garland v.
Davis, 4 How. 131;
Stockton
v. Bishop, 4 How. 155;
Jackson v.
Ashton, 10 Pet. 480.
There is no room here for amendment. There could have been none
in the court below. To allow a verdict to stand which is responsive
to no issue made by the pleadings, or which could have been made by
any pleading in that action, is farther than we can go in the
promotion of abstract justice.
The judgment of the circuit court must be reversed, with
direction to the court below to set aside the special verdict of
the jury for the $11,708 and to enter a judgment in favor of
plaintiffs on the general verdict of $107,353.44, with interest
from the day it was rendered; and the plaintiff in error is to
recover costs in this Court.
If, however, the defendants in error shall within a reasonable
time, during the present term of this Court, file in the circuit
court a remittitur of so much of the judgment of that court in
their favor as is based on the special verdict, and produce here a
certified copy of the remittitur, the judgment of that court will
be affirmed.