1. Where the Secretary of the Navy possesses the power, under
the legislation of Congress and the orders of the President, to
enter into contracts for work connected with the construction,
armament, or equipment of vessels of war, he can suspend the work
contracted for when from any cause the public interest may so
require, and where such suspension is ordered, he is authorized to
settle with the contractor upon the compensation to be paid for the
partial performance of the contracts.
2. When a settlement in such a case is made upon a full
knowledge of all the facts, without concealment, misrepresentation,
or fraud, it is equally binding upon the government and the
contractor.
The facts upon which the decision of the court rests are set
forth in its opinion.
MR. JUSTICE FIELD delivered the opinion of the Court.
This case comes before us on appeal from the Court of Claims,
and involves a consideration of the validity and binding character
of a settlement, made between the Secretary of the Navy and the
claimant, for work performed by the latter upon contracts with the
Navy Department. There is no dispute about the facts of the case
(they are fully and clearly stated in the findings of the Court of
Claims), and it would seem that there ought not to be any dispute
as to the law applicable to them. The validity of the contracts is
not questioned. The work upon them was done under the supervision
of an inspector of the Navy Department, and no complaint is made of
the manner in which it was done. When, in 1869, the department,
upon the recommendation of a board of officers of the navy
appointed by it, suspended the further progress of the work under
the contracts, the claimant made a written proposition, in the
alternative, either to take all the machinery and receive $150,000,
or to deliver it in its then incomplete condition at the Navy Yard
at Charlestown for $259,068, payable on delivery there. The
department accepted the latter proposition, recognizing the amount
specified as the balance due on settlement of the contracts;
stating, however, that, in consequence of the very limited
Page 91 U. S. 322
appropriations, only a partial payment would be made on delivery
of the machinery at the Charlestown Navy Yard, and that the balance
could not be paid until Congress should make a further
appropriation, but that a certificate for the amount due would be
given to the claimant.
The machinery was accordingly delivered at the Navy Yard, with
the exception of a few articles, for which a deduction from the
amount of the settlement was allowed, and the certificate
stipulated was given to the claimant. Previous to this, however,
the chief engineer of the navy, under direction of the department,
examined the machinery and made a detailed report by which the
department was fully informed of its condition, the progress made
in its construction, and what remained to be done for its
completion under the contracts. There is no allegation or
suggestion that the claimant was guilty of any fraud, concealment,
or misrepresentation on the subject, but on the contrary, it is
clear that every fact was known to both parties and that the whole
transaction, as stated by the court below, was unaffected by any
taint or infirmity. If such a settlement, as the Chief Justice of
the Court of Claims very justly observes, accompanied by the giving
up by one and the taking possession by the other of the property
involved, cannot be judicially maintained, it would seem that no
settlement by any contractor with the government could be
considered a finality against the government.
The duty of the Secretary of the Navy, by the Act of April 30,
1798, creating the Navy Department, extends, under the orders of
the President, to
"the procurement of naval stores and materials and the
construction, armament, equipment, and employment of vessels of
war, as well as all other matters connected with the naval
establishment of the United States."
1 Stat. 553. The power of the President in such cases is, of
course, limited by the legislation of Congress. That legislation
existing, the discharge of the duty devolving upon the Secretary
necessarily requires him to enter into numerous contracts for the
public service, and the power to suspend work contracted for,
whether in the construction, armament, or equipment of vessels of
war, when from any cause the public interest requires such
suspension, must necessarily rest with him. As in making
Page 91 U. S. 323
the original contracts he must agree upon the compensation to be
made for their entire performance, it would seem that when those
contracts are suspended by him, he must be equally authorized to
agree upon the compensation for their partial performance.
Contracts for the armament and equipment of vessels of war may and
generally do require numerous modifications in the progress of the
work where that work requires years for its completion. With the
improvements constantly made in shipbuilding and steam machinery
and in arms, some parts originally contracted for may have to be
abandoned and other parts substituted, and it would be of serious
detriment to the public service if the power of the head of the
Navy Department did not extend to providing for all such possible
contingencies by modification or suspension of the contracts and
settlement with the contractors.
When a settlement in such a case is made upon a full knowledge
of all the facts, without concealment, misrepresentation, or fraud,
it must be equally binding upon the government as upon the
contractor -- at least such a settlement cannot be disregarded by
the government without restoring to the contractor the property
surrendered as a condition of its execution.
But aside from this general authority of the Secretary of the
Navy, under the orders of the President, he was, during the
rebellion, specially authorized and required by acts of Congress,
either in direct terms or by specific appropriations for that
purpose, to construct, arm, equip, and employ such vessels of war
as might be needed for the efficient prosecution of the war. In the
discharge of this duty, he made the original contracts with the
claimant. The completion of the machinery contracted for having
become unnecessary from the termination of the war, the Secretary,
in the exercise of his judgment, under the advice of a board of
naval officers, suspended the work. Under these circumstances, we
are of opinion that he was authorized to agree with the claimant
upon the compensation for the partial performance, and that the
settlement thus made is binding upon the government.
Decree affirmed.