In the case of
Slater v.
Emerson, 19 How. 224, this Court held that where
there was a contract to finish a railroad by a given day, the
parties to which were the contractor with the railroad company of
the one part, and a stockholder in the company of the other part,
time was of the essence of the contract, and there could be no
recovery on the written agreement without showing performance
within the time limited, but added that a subsequent performance
and acceptance by the defendant would authorize a recovery in a
quantum meruit.
This Court now holds that the promise of the stockholder
contained in the written agreement was an original undertaking, on
a good and valid consideration moving between the parties to the
instrument, and not a special promise for the debt, default, or
misdoings, of another. Consequently, it is not within the operation
of the statute of frauds.
The cases upon this point examined.
Being an original contract, parol evidence was admissible to
show that the parties had, subsequently to the date of the contract
and before a breach of it, made a new oral agreement, on a new and
valuable consideration, enlarging the time of performance, and
varying its terms.
This was the same case which was before this Court at a previous
term, and is reported in
60 U. S. 19 How.
224.
The substance of that case and the new view of the present one
are fully stated in the opinion of the Court, to which the reader
is referred.
Page 63 U. S. 35
MR. JUSTICE CLIFFORD delivered the opinion of the Court.
This case comes before the court upon a writ of error to the
Circuit Court of the United States for the District of
Massachusetts. It was an action of assumpsit, brought by the
plaintiff in error against the present defendant, upon a written
agreement, bearing date on the fourteenth day of November,
1854.
By the terms of the instrument, the plaintiff covenanted and
agreed with the defendant, in consideration of the agreements of
the latter therein contained, and of one dollar to him paid, that
he, the plaintiff, would complete all the bridge work to be done by
him for the Boston and New York Central Railroad Company, ready for
laying down the rails for one track, by the first day of December
next after the date of the contract. In consideration whereof, the
defendant agreed that he would pay the plaintiff, within two days
from the date of the agreement, the sum of forty-four hundred
dollars in cash; and also give to the plaintiff, on the completion
of the bridges, and when the rails for one track were laid from
Dedham to the foot of Summer street, in Boston, his, the
defendant's, five notes, for two thousand dollars each, dated when
given, as provided, and made payable to the plaintiff or order, in
six months from their date. Another stipulation of the agreement
was that the notes, when paid, were to be applied towards the
indebtedness of the railroad company to the plaintiff, and that the
agreement was in no way to affect any contract of the plaintiff
with the railroad, or any action then pending between them.
When the declaration was filed, it contained three special
counts, drawn upon the written agreement, together with the common
counts, as in actions of
indebitatus assumpsit.
Page 63 U. S. 36
Performance on the part of the plaintiff, and neglect and
refusal on the part of the defendant to give the five notes
specified in the agreement, after seasonable demand, constitute the
cause of action set forth in the several special counts. They
differ in nothing material to be noticed in this investigation,
except that, in the first count, performance on the part of the
plaintiff is alleged, according to the contract, on the first day
of December, 1854, while in the second and third counts it is
alleged at a period twenty days later.
An additional special count was afterwards filed by consent,
which, in one respect, varies essentially from the other counts.
After setting out the substance of the contract, it alleges that
the defendant waived performance at the day stipulated in the
agreement, and extended the time to the twentieth day of the same
December, and that the plaintiff performed and completed the work
within the extended time. Demand of the notes prior to the
commencement of the suit, substantially as alleged, was admitted at
the trial, as were also the execution of the agreement and the
payment by the defendant of the forty-four hundred dollars.
As appears by the transcript, the cause has been twice tried
upon the same pleadings. At the first trial, the verdict was for
the plaintiff; but the defendant excepted to the rulings and
instructions of the circuit court, and, after judgment, removed the
cause into this Court by writ of error.
Among the questions presented on the writ of error, the
principal one was whether, by the true construction of the written
agreement, time was of the essence of the contract. That question
was directly presented by the fourth exception, and this Court held
that the refusal of the circuit judge to instruct the jury, prayed
by the defendant, that the plaintiff could not recover on the
special counts without showing that the work was completed by the
day stipulated in the contract, was error. Accordingly, the
judgment was reversed and the cause remanded with directions to
issue a new venire.
In the opinion delivered on the occasion, this Court said in
effect that in cases where time is of the essence of the contract,
there can be no recovery on the written agreement without
Page 63 U. S. 37
showing performance within the time limited; but added, that a
subsequent performance and acceptance by the defendant will
authorize a recovery in a
quantum meruit. Slater v.
Emerson, 19 How. 239.
Failing to show performance at the day named in the agreement,
the plaintiff, at the last trial, offered to prove by parol to the
effect that after the date of the agreement, and before as well as
after the day specified for the completion of the work, the
defendant, by his conduct, acts, and declarations, waived and
dispensed with performance at the day named in the written
agreement and agreed to substitute therefor performance on the
twentieth day of the same December, and to deem performance on the
day last named as equivalent to performance on the day specified in
the written agreement, and that the work was fully performed within
the extended time.
Objection was made by the defendant to this testimony upon the
ground, that the written agreement declared on was a special
promise for the debt, default, or misdoings of another, and that
the alleged waiver, substitution, and extension, not being in
writing, were within the statute of frauds, and the court sustained
the objection, and excluded the testimony. To which ruling of the
court the plaintiff excepted.
He then proposed to proceed upon the common counts, and offered
evidence accordingly. After reading the agreement set up in the
special counts, he introduced three deeds, each dated November 17,
1854, purporting to convey certain parcels of real estate therein
described. They were each given by the railroad company to the
defendant, to indemnify him for the liability he assumed in the
before-mentioned written agreement with the plaintiff. Estimating
the value of the real estate so conveyed by the considerations
expressed in the respective deeds, it amounted in the aggregate to
the sum of thirteen thousand five hundred dollars.
He also introduced a memorandum agreement between the defendant
and the railroad company, whereby the former leased to the latter
ten hundred and fifty tons of railroad iron, to be laid down by the
company and used on their railroad. By the terms of the last-named
agreement, the railroad iron
Page 63 U. S. 38
was estimated at the value of sixty-eight thousand four hundred
dollars; and the company agreed to pay the defendant, for the use
of the iron, five thousand dollars per month, the first payment to
be made on the first day of March then next, and so upon the first
day of each succeeding month, until the whole sum was paid, with
interest on the same from a given day -- the defendant agreeing, if
there was no default of the payments, when the whole was paid, to
sell and deliver the iron to the company for the estimated value,
including the interest.
To secure these payments together with the interest, the
railroad company, by the same instrument, assigned and set over to
the defendant the proceeds of the railroad, to an amount equal to
the estimated value of the iron, with the interest, and authorized
and required the superintendent of the road to retain in his own
hands, out of the proceeds, a sum sufficient to pay the amount to
the defendant, in the manner and at the times specified in the
agreement.
Emerson's contract with the railroad company was also
introduced, and makes a part of the record. It bears date on the
seventeenth day of December, 1853, and provides, on the one part,
that the plaintiff shall build and complete, sufficient for the
passage of an engine over the same by the first day of May then
next, all the bridging, as then laid out and determined upon by the
engineer, from the wharf, near the foot of Summer street, in
Boston, to Dorchester shore, and to complete the same as soon
thereafter as might be reasonably practicable. On the other part,
the agreement prescribes the compensation to be paid by the
railroad company to the plaintiff, for building and completing the
respective works therein designated and described, stipulating that
eighty-five percent upon the estimated value of the materials
furnished, and seventy-five percent upon the estimated value of the
labor performed, should be paid monthly, as the work was done, and
that the balance should be paid by the company upon the completion
and acceptance of the whole work.
Parties to the suit are by law competent witnesses in the courts
of Massachusetts, and under that law the plaintiff was examined in
this case.
Page 63 U. S. 39
He also called and examined five other witnesses. From this
parol testimony, it appears that securities were put into the hands
of the defendant, deemed by him and the company adequate, at the
time, to indemnify him against his contract with the plaintiff.
Those securities, two of the witnesses say, consisted of real
estate, and the bonds of the company for seventeen thousand
dollars, secured by a mortgage upon the load. In respect to the
real estate, it is to be observed that the deeds of conveyance bear
date three days after the date of the contract; but the presumption
from the circumstances is a reasonable one, that they were given in
pursuance of the arrangement made at the time the contract was
executed. It also appeared that the company failed in July, 1854,
and that it was actually insolvent at the date of these
transactions.
Prior to the date of the agreement of the 14th of November,
1854, the plaintiff had stopped work under his contract with the
company, and refused to continue it. As soon as the contract with
the defendant was made, he resumed the work on the bridges, and
finished them about the middle of December, 1854; but the rails
were not all laid by the company until the twenty-first day of the
same month.
At the date of the contract between these parties, the defendant
was a large stockholder in the corporation, and holder of the bonds
of the company, which were secured by a mortgage of the road to
trustees. During the progress of the work under the contract
between these parties, and before the day therein named for the
completion of the work, the officers of the company, or some of
them, repeatedly stated to the plaintiff, in the presence of the
defendant, and without objection on his part, that all the company
wanted was that the plaintiff should keep out of the way of the
track-layers.
Three of the directors, including the defendant, on the
twenty-fourth day of November, 1854, called on the plaintiff while
he was at work on one of the bridges, and inquired of him if he
could complete it by the fourth day of the then next month, stating
to him the reason why it was desirable that he should do so -- and
by working nights and Sundays he completed it, according to their
request.
Page 63 U. S. 40
Several witnesses state -- and among the number the one who laid
the rails for the company -- that the track-layers were not delayed
by the plaintiff, and the plaintiff testified that the defendant
never objected because the bridges were not completed by the day
specified in the written agreement. On being recalled, he further
testified that he paid, for work done and materials furnished after
that day, the sum of eleven thousand one hundred and fifty-seven
dollars and eighty-four cents, and that he had not received a
dollar for it from any source.
Thereupon the presiding justice ruled and instructed the jury
that, upon this testimony, the plaintiff was not entitled to
recover on the common counts, and directed the jury to return their
verdict for the defendant. Accordingly, the jury found that the
defendant never promised, and the plaintiff excepted to the rulings
and instructions of the court.
Several questions were discussed at the bar, which, in the view
we have taken of the case, it will not be necessary to decide.
Both of the exceptions to the rulings and instructions of the
court necessarily involve the construction of the contract between
these parties; but the question presented is widely different from
the one considered and decided by this Court on the former record.
On that occasion, the single question of any importance was,
whether, by the true construction of the contract, it was agreed
and understood between the parties to the instrument that the
completion of the work at the time therein prescribed was a
condition on which the obligation of the defendant to give the
notes was to depend.
Contrary to the ruling of the circuit judge, this Court held
that the covenants of the respective parties were dependent, that
time was of the essence of the contract, and remanded the cause for
a new trial.
That rule of construction, beyond doubt, is the law of the
contract, and no attempt has been made to evade or question it on
either side in this controversy. But the question now presented is
of a very different character.
It is insisted by the plaintiff that the promise of the
defendant
Page 63 U. S. 41
was an original undertaking, on a good and valid consideration,
moving between the parties to the instrument. On the part of the
defendant, it is insisted that his undertaking was a special
promise for the debt, default, or misdoings, of another, and so
within the statute of frauds.
If the theory of the plaintiff be correct, then it would seem to
follow that the rulings and instructions of the circuit court were
erroneous. Verbal agreements between the parties to a written
contract, made before or at the time of the execution of the
contract, are in general inadmissible to vary its terms, or to
affect its construction. All such verbal agreements are considered
as merged in the written contract. But oral agreements subsequently
made, on a new and valuable consideration and before the breach of
the contract, in cases falling within the general rules of the
common law, and not within the statute of frauds, stand upon a
different footing. Such subsequent oral agreements, not falling
within the exception mentioned, may have the effect to enlarge the
time of performance specified in the contract, or may vary any
other of its terms, or may waive and discharge it altogether. On
this point, the authorities are numerous and decisive, of which the
following are examples:
Goss v. Nugent, 5 Barn. & Ad.
65;
Nelson v. Boynton, 3 Met. 402. Speaking of the
exceptions to the general rule, that parol evidence is not
admissible to contradict or vary the terms of a written instrument,
Mr. Greenleaf says:
"Neither is the rule infringed by the admission of oral evidence
to prove a new and distinct agreement upon a new consideration,
whether it be a substitute for the old one, or in addition to and
beyond it; and if subsequent, and involving the same subject
matter, it is immaterial whether the new agreement be entirely
oral, or whether it refers to and partially or totally adopts the
provisions of the former contract in writing, provided the old
agreement be rescinded and abandoned."
1 Green. Ev. 303. But the rule, so far as it is applicable to
this case, is better stated by Lord Denman, in
Goss v.
Nugent, 5 Barn. & Ad. 665, wherein he says:
"After the agreement has been reduced into writing, it is
competent to the parties, in cases falling within
Page 63 U. S. 42
the general rules of the common law, at any time before the
breach of it by a new contract, not in writing, either altogether
to waive, dissolve, or annul, the former agreement, or in any
manner to add to or subtract from or vary or qualify the terms of
it, and thus to make a new contract."
That rule was afterwards qualified by the same learned judge in
a particular not essential to the present inquiry; and with that
qualification it appears to be the rule constantly applied by the
English courts, in cases not within the statute of frauds, to the
present time.
Harvey v. Grabham, 5 Ad. & El. 61; 1
Phil.Ev., Cow. & Hill's ed., 563, n. 987;
Munroe v.
Perkins, 9 Pick. 298;
Snow v. Inhabitants of Ware, 13
Met. 42;
Vicary v. Moore, 2 Watts 451;
Cummings v.
Arnold, 3 Met. 489;
Fleming v. Gilbert, 3 Johns.
528.
On the other hand, assuming the theory of the defendant to be
correct, that, by the true construction of the contract, his
undertaking was a special promise for the debt, default, or
misdoings, of the railroad company, then perhaps the better opinion
is, according to the weight of authority, that a written contract
within the statute of frauds cannot be varied by any subsequent
agreement of the parties, unless such new agreement is also in
writing.
Marshall v. Lynn, 6 Mee. & Wels. 109;
Goss v. Nugent, 5 Barn. & Ad. 58;
Harvey v.
Grabham, 5 Ad. & El. 61;
Stowell v. Robinson, 3
Bing.N.C. 927;
Stead v. Dowber, 10 Ad. & El. 57;
Emmet v. Dewhurst, 8 Eng.L. & Eq. 88;
Hasbrouk v.
Tappan, 15 Johnson's 200;
Blood v. Goodrich, 9 Wen.
68;
Stevens v. Cooper, 1 Johnson's Ch. 429;
Clark v.
Russel, 3 Dall. 415. Decided cases, however, are
referred to, from the Massachusetts reports, which evidently wear a
different aspect, and it is contended by the counsel for the
plaintiff that the principle adopted in those cases constitutes the
rule of decision in this case; but it is unnecessary to determine
that point at the present time, as we are of the opinion that the
promise of the defendant contained in the written agreement was an
original undertaking, on a good and valid consideration moving
between the parties to the instrument.
Nelson v. Boynton,
3 Met. 396;
Stearns v. Hall, 9 Cush. 31.
Page 63 U. S. 43
Cases in which the guaranty or promise is collateral to the
principal contract, but is made at the same time, and becomes an
essential ground of the credit given to the principal debtor, are,
in general, within the statute of frauds. Other cases arise which
also fall within the statute, where the collateral agreement is
subsequent to the execution of the debt, and was not the inducement
to it, on the ground that the subsisting liability was the
foundation of the promise on the part of the defendant, without any
other direct and separate consideration moving between the parties.
But whenever the main purpose and object of the promissor is not to
answer for another, but to subserve some pecuniary or business
purpose of his own, involving either a benefit to himself, or
damage to the other contracting party, his promise is not within
the statute, although it may be in form a promise to pay the debt
of another, and although the performance of it may incidentally
have the effect of extinguishing that liability.
Nelson v.
Boynton, 3 Met. 400;
Leonard v. Vredenburg, 8 Johns.
39;
Farley v. Cleveland, 4 Cow. 432;
Alger v.
Scoville, 1 Gray 391;
Williams v. Leper, 3 But. 1886;
Castling v. Aubert, 2 East. 325; 2 Parsons on Con. 306.
Nothing is better settled than the rule, that if there is a benefit
to the defendant, and a loss to the plaintiff, consequential upon
and directly resulting from the defendant's promise in behalf of
the plaintiff, there is a sufficient consideration moving from the
plaintiff to enable the latter to maintain an action upon the
promise to recover compensation. 2 Addison on Con. 1002, and cases
cited. Other authorities state the proposition much stronger,
authorizing the conclusion that benefit to the party by whom the
promise is made, or to a third person at his instance, or damage
sustained at the instance of the party promising, by the party in
whose favor the promise is made, is sufficient to constitute a good
and valid consideration on which to maintain an action.
Violet v.
Patton, 5 Cranch 150; Chitt. on Con. 28;
Townsley v.
Sumrall, 2 Pet. 182.
Apply these principles to the terms of the written agreement, in
view of the attending circumstances and the subject matter, and it
is quite clear that the promise of the defendant
Page 63 U. S. 44
was an original undertaking on a good and valid consideration
moving from the plaintiff at the time the instrument was executed.
On its face it purports to be a contract between the parties, for
their own benefit; one agreeing to do certain work, and furnish
certain materials, and the other agreeing to pay therefor a
stipulated compensation. Their promises are mutual, and in one
respect dependent. In consideration that the plaintiff engaged to
do the work and furnish the materials by a given day, the
defendant, on his part, agreed, among other things, when the work
was completed, to give the plaintiff the five notes therein
described. Reference was made to the contract of the plaintiff with
the railroad company in the first instance, as descriptive of the
work to be done, and of the materials to be furnished; and in the
second instance, doubtless for the reason that, as a part of the
transaction, the company had placed, or agreed to place, securities
in the hands of the defendant, to indemnify him for the liability
he thereby assumed to the plaintiff. Part of those securities were
delivered over to the defendant at the time, and the residue as
soon thereafter as the conveyances could conveniently be made. But
when we consider the attending circumstances, the presumption is
much stronger that the arrangement was one mainly, if not entirely,
for the individual benefit of the defendant.
Prior to that date, the railroad company had failed, and was
utterly insolvent, owning nothing, it seems, except the securities
transferred to the defendant for his indemnity in this transaction,
and the franchise of the road. Unlike what was exhibited in the
former record, it now appears that the defendant had large
interests of his own, separate from his relation to the company as
a stockholder, which were to be promoted by the arrangement. He had
leased to the company railroad iron for the use of the road,
amounting in value to the sum of sixty-eight thousand dollars, and,
as a security for payment, held an assignment of the proceeds of
the road to that amount, with interest, which was to be paid in
monthly installments of five thousand. Now unless the bridges were
completed and the road put in a condition for use, there would be
no proceeds,
Page 63 U. S. 45
and as he had already taken into his possession all the
available means of the company to secure himself for this new
liability, should the road not be completed, the company could not
pay for the iron.
In this view of the subject, it is manifest that the arrangement
was one mainly to promote the individual interest of the defendant.
Damage also resulted to the plaintiff, as is obvious from the whole
transaction. Under his contract with the company, they had
stipulated to pay him monthly eighty-five percent upon the
estimated value of the materials furnished, and seventy-five
percent upon the estimated value of the labor performed as the work
was done. Failing to receive those monthly payments from the
company, the plaintiff, as he had a right to do, stopped the works,
and refused to proceed, in consequence of the failure of the
company to make the monthly payments. To remedy this difficulty,
and insure the completion of the bridges so as to render the road
available for use, this arrangement was made by the defendant. It
was not an arrangement to pay a subsisting indebtedness, but only
for work to be done and materials to be furnished; monthly payments
were discontinued, and the plaintiff was induced, with an advance
of forty-four hundred dollars, to resume and complete the work at
his own expense. Without detailing more of the evidence, as
exhibited in the statement of the case, it will be sufficient to
say that, in view of all the attending circumstances, we think it
is clear that the promise of the defendant was an original
undertaking upon a good and valid consideration moving between the
parties to the written agreement.
For these reasons, we think the plaintiff had a right to proceed
upon the common counts, and that it was error in the presiding
justice to direct a verdict for the defendant. It is also contended
by the plaintiff that the effect of the indemnity given by the
railroad company to the defendant was to take the contract out of
the statute of frauds, but we do not find it necessary to determine
that question at the present time.
The judgment of the circuit court is therefore reversed,
with costs, and the cause remanded with directions to issue a new
venire.