General Motors Corp. v. United States, 496 U.S. 530 (1990)

Argued: March 21, 1990
Decided: June 14, 1990
Syllabus

U.S. Supreme Court

General Motors Corp. v. United States, 496 U.S. 530 (1990)

General Motors Corp. v. United States

No. 89-369

Argued March 21, 1990

Decided June 14, 1990

496 U.S. 530

Syllabus

The Clean Air Act was amended in 1970 to deal with a perceived national air pollution emergency. The amendments required that the Administrator of the Environmental Protection Agency (EPA) promulgate national ambient air quality standards (NAAQS) within 30 days, and that each State thereafter submit a state implementation plan (SIP) within nine months. Section 110(a)(2) of the Act required the Administrator to approve a SIP within four months of its submission if the SIP met various substantive requirements. Section 110(a)(3) authorizes a State to propose a SIP revision, and requires the Administrator to approve that revision if he determines, among other things, that it "meets the requirements of [§ 110(a)(2)]." In 1980, EPA approved Massachusetts' proposed SIP governing certain emissions from automobile painting operations. The SIP permitted petitioner General Motors Corporation (GMC) -- whose automobile plant's painting operation is a source of ozone -- to meet emissions limits in stages, but required full compliance by December 31, 1985. In June, 1985, GMC sought an extension of that deadline until summer, 1987. Massachusetts approved the revision and submitted it to EPA on the day before the existing SIP's deadline, but EPA did not reject it until September, 1988. In the meantime, EPA sent GMC a notice of violation of the existing SIP and filed an enforcement action in the District Court. In May, 1988, the District Court entered summary judgment for GMC, holding that § 110(a)(3) imposed a 4-month time limit on EPA review of a SIP revision, and that EPA was therefore barred from enforcing the existing SIP from the end of the 4-month period until it finally acted on the revision. Although agreeing that the Act imposed a 4-month deadline, the Court of Appeals reversed, concluding that the failure to meet that deadline did not preclude EPA from enforcing the existing SIP.

Held:

1. EPA is not required to act on a proposed SIP revision within four months. Since § 110(a)(2)'s 4-month requirement was enacted as one of a series of deadlines designed to assure quick implementation of pollution control requirements, that section refers only to the action required on the original SIP, and not to a revision. Moreover, in the absence of an express requirement that the Administrator process a proposed revision within four months, this Court is not free to read such a

Page 496 U. S. 531

limitation into § 110(a)(3). That section incorporates only the substantive, but not the procedural, requirements of § 110(a)(2). Nor does § 110(g) -- which authorizes a State Governor, in certain circumstances, temporarily to suspend a SIP for which the State has submitted a proposed revision when the Administrator has not taken action "within the required four-month period" -- impose a 4-month limitation on EPA. That section does not require the Administrator to do anything, and its incorporation of the mistaken presupposition that some "four-month period" is "required" does not impose a general requirement on EPA. Pp. 496 U. S. 536-539.

2. Although subject to the Administrative Procedure Act's requirement that agencies conclude matters "within a reasonable time," EPA is not barred from bringing suit to enforce an existing SIP if it unreasonably delays action on a proposed revision. This Court will not infer an enforcement bar in the absence of a specific provision in the Clean Air Act suggesting that Congress intended to create one. In fact, that Act plainly states that EPA may bring an enforcement action whenever a person is in violation of any "applicable implementation plan" requirement, § 113(b)(2), and there is little doubt that the existing SIP remains the "applicable implementation plan" even after the State has submitted a proposed revision. See, e.g., Train v. Natural Resources Defense Council, Inc., 421 U. S. 60, 421 U. S. 92. It is significant that Congress explicitly enacted an enforcement bar elsewhere in the Act, see § 113(d)(10), but failed to do so in the section at issue, and that it provided other, less drastic, remedies when EPA delays action on a SIP revision, see §§ 304(a)(2), 113(b). Pp. 496 U. S. 539-542.

876 F.2d 1060, affirmed.

BLACKMUN, J., delivered the opinion for a unanimous Court.

Page 496 U. S. 532


Opinions

U.S. Supreme Court

General Motors Corp. v. United States, 496 U.S. 530 (1990) General Motors Corp. v. United States

No. 89-369

Argued March 21, 1990

Decided June 14, 1990

496 U.S. 530

CERTIORARI TO THE UNITED STATES COURT OF APPEALS FOR

THE FIRST CIRCUIT

Syllabus

The Clean Air Act was amended in 1970 to deal with a perceived national air pollution emergency. The amendments required that the Administrator of the Environmental Protection Agency (EPA) promulgate national ambient air quality standards (NAAQS) within 30 days, and that each State thereafter submit a state implementation plan (SIP) within nine months. Section 110(a)(2) of the Act required the Administrator to approve a SIP within four months of its submission if the SIP met various substantive requirements. Section 110(a)(3) authorizes a State to propose a SIP revision, and requires the Administrator to approve that revision if he determines, among other things, that it "meets the requirements of [§ 110(a)(2)]." In 1980, EPA approved Massachusetts' proposed SIP governing certain emissions from automobile painting operations. The SIP permitted petitioner General Motors Corporation (GMC) -- whose automobile plant's painting operation is a source of ozone -- to meet emissions limits in stages, but required full compliance by December 31, 1985. In June, 1985, GMC sought an extension of that deadline until summer, 1987. Massachusetts approved the revision and submitted it to EPA on the day before the existing SIP's deadline, but EPA did not reject it until September, 1988. In the meantime, EPA sent GMC a notice of violation of the existing SIP and filed an enforcement action in the District Court. In May, 1988, the District Court entered summary judgment for GMC, holding that § 110(a)(3) imposed a 4-month time limit on EPA review of a SIP revision, and that EPA was therefore barred from enforcing the existing SIP from the end of the 4-month period until it finally acted on the revision. Although agreeing that the Act imposed a 4-month deadline, the Court of Appeals reversed, concluding that the failure to meet that deadline did not preclude EPA from enforcing the existing SIP.

Held:

1. EPA is not required to act on a proposed SIP revision within four months. Since § 110(a)(2)'s 4-month requirement was enacted as one of a series of deadlines designed to assure quick implementation of pollution control requirements, that section refers only to the action required on the original SIP, and not to a revision. Moreover, in the absence of an express requirement that the Administrator process a proposed revision within four months, this Court is not free to read such a

Page 496 U. S. 531

limitation into § 110(a)(3). That section incorporates only the substantive, but not the procedural, requirements of § 110(a)(2). Nor does § 110(g) -- which authorizes a State Governor, in certain circumstances, temporarily to suspend a SIP for which the State has submitted a proposed revision when the Administrator has not taken action "within the required four-month period" -- impose a 4-month limitation on EPA. That section does not require the Administrator to do anything, and its incorporation of the mistaken presupposition that some "four-month period" is "required" does not impose a general requirement on EPA. Pp. 496 U. S. 536-539.

2. Although subject to the Administrative Procedure Act's requirement that agencies conclude matters "within a reasonable time," EPA is not barred from bringing suit to enforce an existing SIP if it unreasonably delays action on a proposed revision. This Court will not infer an enforcement bar in the absence of a specific provision in the Clean Air Act suggesting that Congress intended to create one. In fact, that Act plainly states that EPA may bring an enforcement action whenever a person is in violation of any "applicable implementation plan" requirement, § 113(b)(2), and there is little doubt that the existing SIP remains the "applicable implementation plan" even after the State has submitted a proposed revision. See, e.g., Train v. Natural Resources Defense Council, Inc., 421 U. S. 60, 421 U. S. 92. It is significant that Congress explicitly enacted an enforcement bar elsewhere in the Act, see § 113(d)(10), but failed to do so in the section at issue, and that it provided other, less drastic, remedies when EPA delays action on a SIP revision, see §§ 304(a)(2), 113(b). Pp. 496 U. S. 539-542.

876 F.2d 1060, affirmed.

BLACKMUN, J., delivered the opinion for a unanimous Court.

Page 496 U. S. 532

JUSTICE BLACKMUN delivered the opinion of the Court.

This case concerns a Clean Air Act enforcement action by the Environmental Protection Agency (EPA) against petitioner General Motors Corporation (GMC). We are asked to decide whether the 4-month time limit on EPA review of an original state implementation plan (SIP) also applies to its review of a SIP revision, and whether, if EPA fails to complete its review of a SIP revision in a timely manner, EPA is prevented from enforcing an existing SIP.

I What is known as the Clean Air Act, 77 Stat. 392, became law on December 17, 1963. Twenty years ago, Congress enacted the Clean Air Amendments of 1970, 84 Stat. 1676, a comprehensive national program that made the States and the Federal Government partners in the struggle against air pollution. The threats to human health were regarded as urgent, and the 1970 Amendments were designed to result in the expeditious establishment of programs to deal with the problem. The amendments specified a detailed timetable for

Page 496 U. S. 533

federal and state action to accomplish this objective. They required the EPA Administrator, within 30 days of the passage of the amendments, to promulgate national ambient air quality standards (NAAQS). § 109(a)(1), 42 U.S.C. § 7409(a)(1) (1982 ed.). Within nine months thereafter, each State was to submit a SIP to implement, maintain, and enforce the NAAQS. § 110(a)(1), 42 U.S.C. § 7410(a)(1) (1982 ed.). As the final step in this start-up phase of the program, EPA was to act on a proposed SIP within four months:

"The Administrator shall, within four months after the date required for submission of a plan under paragraph (1), approve or disapprove such plan or any portion thereof."

§ 110(a)(2), as amended, 42 U.S.C. § 7410(a)(2) (1982 ed.). The Administrator was directed to approve the SIP if he determined that it was adopted after reasonable notice and hearing and that it met various substantive requirements, including emissions limitations, devices for monitoring air quality data, and enforcement mechanisms.

The integrated timetable established by the 1970 amendments reflected the urgency of establishing air pollution controls. But the amendments also recognized that local needs and control strategies could evolve over time, and that SIP's would have to change as well. The States therefore were authorized to propose SIP revisions, and the EPA Administrator was directed to approve any such proposed revision

"if he determines that it meets the requirements of paragraph (2) and has been adopted by the State after reasonable notice and public hearings."

§ 110(a)(3), 42 U.S.C. § 7410(a)(3)(A) (1982 ed.).

The 1970 Amendments also specified certain enforcement mechanisms. The Act empowered EPA to order compliance with an applicable implementation plan, § 113(a), 42 U.S.C. § 7413(a) (1982 ed.), and to seek injunctive relief against a source violating the plan or an EPA order, § 113(b), as amended, 42 U.S.C. § 7413(b) (1982 ed.). In addition, Congress prescribed criminal penalties for knowing violations of

Page 496 U. S. 534

plans and orders, § 113(c), 42 U.S.C. § 7413(c) (1982 ed.), and authorized citizen suits for injunctions against violators, in the absence of Government enforcement, § 304, as amended, 42 U.S.C. § 7604(1982ed.).

Congress further amended the Clean Air Act by the Clean Air Act Amendments of 1977. 91 Stat. 685. It added to the Act the concept of a "nonattainment area" -- an area where air quality falls short of the NAAQS. § 171(2), 42 U.S.C. § 7501(2) (1982 ed.). The deadline for attainment of the primary NAAQS in a nonattainment area was December 31, 1982. § 172(a)(1), 42 U.S.C. § 7502(a)(1) (1982 ed.). Further extensions were permitted for "photochemical oxidants" (ozone) or carbon monoxide, but only if the State demonstrated that attainment was not possible before 1983 "despite the implementation of all reasonably available measures," and that attainment would be achieved "as expeditiously as practicable, but not later than December 31, 1987." § 172(a)(2), 42 U.S.C. § 7502(a)(2) (1982 ed.).

II A

The entire Commonwealth of Massachusetts is a nonattainment area for NAAQS with respect to ozone. See 40 CFR § 81.322, p. 126 (1989). Petitioner GMC owns and operates an automobile assembly plant in Framingham, Mass. The plant's painting operation is a source of volatile organic compounds that contribute to ozone. In 1980, EPA approved Massachusetts' proposed nonattainment area SIP governing volatile organic compound emissions from automobile painting operations. The SIP permitted GMC to meet emissions limits in stages, but required full compliance by December 31, 1985. In 1981, EPA published a policy statement suggesting that new technology in automobile painting operations might justify deferral of industry compliance until 1986 or 1987. 46 Fed.Reg. 51386. Three years later, in November, 1984, GMC sought an extension from the

Page 496 U. S. 535

December 31, 1985, compliance date imposed by the existing SIP, not for the new technology, but rather for additional time to install emission controls on its existing lines. App. 38. In June, 1985, GMC proposed converting to the new technology, and requested a summer, 1987, deadline. Id. at 41. The Commonwealth approved the revision and submitted the proposal to EPA on December 30, 1985, one day before the existing SIP compliance deadline. Id. at 50.

GMC began construction of a new painting facility but continued to operate its existing plant. On August 14, 1986, EPA sent GMC a notice of violation, informing GMC that it was in violation of the applicable SIP. Id. at 75. Approximately one year later, on August 17, 1987, respondent filed an enforcement action under § 113(b) of the Act, 42 U.S.C. § 7413(b) (1982 ed.), alleging violations of the existing SIP's 1985 deadline. On September 4, 1988, the agency made its final decision to reject the revision. 53 Fed.Reg. 36011.

B

The District Court construed § 110(a)(3) as imposing a 4-month time limit on EPA review of a SIP revision, App. 123-124, and concluded that, when EPA failed to complete its review within four months, it was barred from enforcing the existing SIP during the interval between the end of the 4-month period and the time EPA finally acted on the revision, id. at 125. Because EPA had not issued a notice of noncompliance until well after the 4-month period had elapsed, and, at the time of the court's ruling, had yet to make a final decision on the Commonwealth's SIP revision, summary judgment was entered for GMC.

The Court of Appeals for the First Circuit reversed that judgment and remanded the case for further proceedings. 876 F.2d 1060 (1989). The Court of Appeals agreed with the District Court that the Act imposed a 4-month deadline on EPA review of a SIP revision, but concluded that the failure

Page 496 U. S. 536

to meet that deadline did not preclude EPA from enforcing the existing SIP.

Reasoning that an enforcement bar was too drastic a remedy for agency delay, the court concluded that the appropriate remedies for agency inaction were those provided by the Act itself: a suit to compel agency action under § 304(a)(2), 42 U.S.C. § 7604(a)(2) (1982 ed.), or a request pursuant to § 113(b), 42 U.S.C. § 7413(b) (1982 ed.), for reduction or elimination of penalties during the period in which unreasonable agency delay resulted in prejudice. 876 F.2d at 1067-1068. We granted certiorari because of a disagreement among the Circuits as to whether EPA is barred from enforcing an existing SIP if the agency fails to take action on a proposed SIP revision within four months. [Footnote 1] 493 U.S. 991 (1989).

III To assure that some form of pollution control requirements were put in place quickly, the 1970 Amendments established a series of deadlines. One of these was the requirement that EPA act on a proposed SIP within four months after the State submits its plan. § 110(a)(2), 42 U.S.C. § 7410(a)(2) (1982 ed.). Specifically, the provision requires EPA to act within "four months after the date required for submission of a plan." This seems to us to refer only to the action required on the original SIP. Section 110(a)(2), by its terms, therefore does not impose such a time restraint on EPA review of a SIP revision.

Petitioner nevertheless claims that § 110(a)(3) requires EPA to act on a proposed SIP revision within four months. That provision requires the Administrator to approve

"any revision of an implementation plan . . . if he determines that it meets the requirements of paragraph (2) [§ 110(a)(2)] and has been adopted by the State after reasonable notice and

Page 496 U. S. 537

public hearings."

Petitioner contends that the reference to § 110(a)(2) was intended to incorporate both the substantive and the procedural requirements of that provision. Brief for Petitioner 13.

We are not persuaded. The Administrator is to approve the proposed revision if he determines that "it" -- that is, the revision -- meets the substantive requirements imposed on a SIP by § 110(a)(2). There is no requirement that "he" -- that is, the Administrator -- meet the deadline of that section. Petitioner's reading, moreover, makes nonsense of the further requirement in § 110(a)(3) that the Administrator find that the proposed revision "has been adopted by the State after reasonable notice and public hearings." If, as petitioner contends, § 110(a)(3) incorporates the procedural provisions of § 110(a)(2), it surely incorporates § 110(a)(2)'s requirement that the Administrator find that the SIP was adopted after reasonable notice and hearing. The separate mention in § 110(a)(3) of the notice and hearing requirement demonstrates that it does not simply incorporate every direction of § 110(a)(2); and since § 110(a)(3) does not separately require the Administrator to process a proposed revision within four months, we are not free to read that limitation into the statute.

This suffices to dispose of petitioner's contention, but if additional support is needed, it is available. The statute elsewhere explicitly imposes upon the Administrator deadlines of the kind that petitioner would insert into § 110(a)(3). Indeed, the very next provision of the Act contains just such an express time restraint on EPA approval of a SIP revision. See § 110(a)(3)(B) (with respect to certain SIP revisions for fuel-burning stationary sources, "[t]he Administrator shall approve or disapprove any revision no later than three months after its submission"). For other examples of explicit deadlines in the Clean Air Act, see § 110(c)(1) (6-month deadline for imposition of federal implementation "plan (or revision thereof)"); § 113(d)(2) (90-day deadline for review of

Page 496 U. S. 538

state-issued delayed compliance order). Since the statutory language does not expressly impose a 4-month deadline and Congress expressly included other deadlines in the statute, it seems likely that Congress acted intentionally in omitting the 4-month deadline in § 110(a)(3)(A). See Russello v. United States, 464 U. S. 16, 464 U. S. 23 (1983) ("[W]here Congress includes particular language in one section of a statute, but omits it in another section of the same Act, it is generally presumed that Congress acts intentionally and purposely in the disparate inclusion or exclusion,'" quoting United States v. Wong Kim Bo, 472 F.2d 720, 722 (CA5 1972)).

Petitioner's final contention is that § 110(g) imposes a 4-month limitation on EPA's action on a proposed SIP revision. That section provides:

"(1) In the case of any State which has adopted and submitted to the Administrator a proposed plan revision which the State determines -- "

"(A) meets the requirements of this section, and"

"(B) is necessary (i) to prevent the closing for one year or more of any source of air pollution, and (ii) to prevent substantial increases in unemployment which would result from such closing, and which the Administrator has not approved or disapproved under this section within the required four-month period, the Governor may issue a temporary emergency suspension of the part of the applicable implementation plan for such State which is proposed to be revised with respect to such source. . . ."

"(2) A temporary emergency suspension issued by a Governor under this subsection shall remain in effect for a maximum of four months. . . ."

(Emphasis added.) According to petitioner, § 110(g), on its own terms, "require[s]" the Administrator to process a proposed revision within a "four-month period." Reply Brief for Petitioner 7.

This is petitioner's strongest claim, but we are constrained to reject it. Section 110(g) does not, by its terms, require

Page 496 U. S. 539

the Administrator to take any action. It merely authorizes the Governor to suspend the existing SIP if certain action has occurred. True, it presupposes that some "four-month period" is "required," but the incorporation of that mistaken presupposition does not, of itself, create a general requirement that the Administrator process all proposed revisions within four months. [Footnote 2] Whatever may be the correct interpretation of § 110(g)'s "required four-month period," we do not think this passing mention can be inflated into a requirement that the Administrator process each and every proposed revision within four months.

IV Although the 4-month deadline does not apply, EPA remains subject to the Administrative Procedure Act's (APA's) statutory requirements of timeliness. The APA requires agencies to conclude matters "within a reasonable time," 5 U.S.C. § 555(b), and provides a remedy for agency action "unreasonably delayed," 5 U.S.C. § 706(1). The Government concedes, as we think it must, that its action on a proposed SIP revision is subject to that mandate. Brief for United States 19-20.

Petitioner's main claim is that any delay over four months is categorically unreasonable because it violates EPA's statutory

Page 496 U. S. 540

duty to process a revision within that period. We have rejected that claim above, but we nevertheless must consider petitioner's alternative contention that EPA may not bring an action to enforce an existing SIP if it unreasonably delays in acting on the proposed revision. Without deciding whether the delay in this case was unreasonable, we now address this claim. Because the statute does not reveal any congressional intent to bar enforcement of an existing SIP if EPA delays unreasonably in acting on a proposed SIP revision, we agree with the Court of Appeals that such an enforcement action is not barred.

The language of the Clean Air Act plainly states that EPA may bring an action for penalties or injunctive relief whenever a person is in violation of any requirement of an "applicable implementation plan." § 113(b)(2), 42 U.S.C. § 7413(b)(2) (1982 ed.). There can be little or no doubt that the existing SIP remains the "applicable implementation plan" even after the State has submitted a proposed revision. The statute states:

"For purposes of this chapter, an applicable implementation plan is the implementation plan, or most recent revision thereof, which has been approved under [§ 110(a), 42 U.S.C. § 7410(a) (1982 ed.),] or promulgated under [110(c), 42 U.S.C. § 7410(c) (1982 ed.),] and which implements the requirements of this section."

§ 110(d), 42 U.S.C. § 7410(d) (1982 ed.). Both this Court and the Courts of Appeals have recognized that the approved SIP is the applicable implementation plan during the time a SIP revision proposal is pending. See, e.g., Train v. Natural Resources Defense Council, Inc., 421 U. S. 60, 421 U. S. 92 (1975); United States v. Alcan Foil Products Division of Alcan Aluminum Corp., 889 F.2d 1513, 1519 (CA6 1989), cert. pending, No. 89-1104; United States v. Wheeling-Pittsburgh Steel Corp., 818 F.2d 1077, 1084 (CA3 1987); Duquesne Light Co. v. EPA, 225 U.S.App.D.C. 290, 305, 698 F.2d 456, 471 (1983). The commentators agree with this conclusion. See D. Currie, Air Pollution: Federal Law and Analysis § 8.07,

Page 496 U. S. 541

n. 14 (Supp.1990); 1 W. Rodgers, Environmental Law: Air and Water § 3.39(c) (1986 and Supp.1988).

There is nothing in the statute that limits EPA's authority to enforce the "applicable implementation plan" solely to those cases where EPA has not unreasonably delayed action on a proposed SIP revision. Moreover, we find it significant that Congress expressly enacted an enforcement bar elsewhere in the statute. See § 113(d)(10); 42 U.S.C. § 7413(d)(10) (1982 ed.) ("During the period of the order . . . no Federal enforcement action pursuant to this section and no action under section 304 of this Act shall be pursued against such owner. . . ."). The fact that Congress explicitly enacted an enforcement bar similar to the one proposed by petitioner in one section of the statute, but failed to do so in the section at issue in this case, reinforces our refusal to import such a bar here. See Russello v. United States, 464 U.S. at 464 U. S. 23. [Footnote 3]

We note that other statutory remedies are available when EPA delays action on a SIP revision. [Footnote 4] Although these statutory remedies may not appear to be so strong a deterrent to EPA delay as would an enforcement bar, these are the remedies that Congress has provided in the statute. [Footnote 5] Cf. 476 U. S. S. 542� v. Pierce County,@ 476 U. S. 253, 476 U. S. 260 (1986) ("We would be most reluctant to conclude that every failure of an agency to observe a procedural requirement voids subsequent agency action, especially when important public rights are at stake. When, as here, there are less drastic remedies available for failure to meet a statutory deadline, courts should not assume that Congress intended the agency to lose its power to act" (footnote omitted)). In the absence of a specific provision suggesting that Congress intended to create an enforcement bar, we decline to infer one.

The judgment of the Court of Appeals is affirmed.

It is so ordered.

[Footnote 1]

See, e.g., American Cyanamid Co. v. EPA, 810 F.2d 493 (CA5 1987); Duquesne Light Co. v. EPA, 225 U.S.App.D.C. 290, 698 F.2d 456 (1983).

[Footnote 2]

Even supposing, moreover, that § 110(g) does create some new requirement, it is not at all clear that the requirement is a general obligation on the part of the Administrator to process every proposed revision within four months. That section says only that the Governor may suspend the SIP if the State has submitted a proposed revision which, among other things, "the Administrator has not approved or disapproved under this section within the required four-month period." The "required four-month period" simply could impose a waiting period on the Governor; before he suspends the existing SIP, he must give the Administrator four months to consider the proposed revision. The Administrator is not always obliged to process a proposed revision within four months, although he may be constrained to act on certain proposals in that period if he wants to prevent the Governor from exercising his prerogative under § 110(g).

[Footnote 3]

Our conclusion is further supported by the language of § 110(g), 42 U.S.C. § 7410(g) (1982 ed.), discussed above. Section 110(g) grants certain authority to a State's Governor to suspend the existing SIP after four months. As the Court of Appeals discerned, 876 F.2d 1060, 1069, n. 6 (CA1 1989), there would have been no reason for Congress to add that section if the existing SIP automatically became unenforceable after some period of EPA delay. The existence of this explicit exception indicates that in all other circumstances the existing SIP remains in effect.

[Footnote 4]

As the Court of Appeals observed, the statutory remedies for EPA inaction include a suit to compel agency action under § 304(a)(2), 42 U.S.C. § 7604(a)(2) (1982 ed.), and a request pursuant to § 113(b), 42 U.S.C. § 7413(b) (1982 ed.), for reduction or elimination of penalties during any period in which unreasonable agency delay results in prejudice. 876 F.2d at 1067-1068.

[Footnote 5]

The Commonwealth of Massachusetts, the State whose interests are involved here, in a brief joined by 12 other States, asserts that its interest is better served by preserving EPA's ability to enforce the Act. See Brief for Massachusetts et al. as Amici Curiae 10-12.