The Federal Power Commission (FPC) has decided to rely on area
rate proceedings to establish just and reasonable rates for
producer sales under §§ 4 and 5 of the Natural Gas Act. Pending
completion of those proceedings the FPC has rested interim producer
regulation on § 7. Under that section, natural gas may be sold only
pursuant to an FPC certificate of public convenience and necessity,
which, under § 7(e), may be conditioned "in such manner as the
public convenience and necessity may require." In
Atlantic Rfg.
Co. v. Public Serv. Comm'n (CATCO
), 360 U.
S. 378, this Court held that the FPC should use its § 7
conditioning power to prevent large initial contract price
advances, pending the determination under §§ 4 and 5 of just and
reasonable rates, which would become effective only prospectively.
The FPC thereafter began to use its conditioning power to determine
maximum initial prices at which sales could occur, basing these
"in-line" prices upon current prices in the area of the proposed
sale but excluding current prices which for various reasons were
"suspect." In
United Gas Improvement Co. v. Callery Properties,
Inc., 382 U. S. 223,
this Court generally approved this regulatory approach, holding
that the FPC might properly refuse to hear cost evidence in such
"in-line" price proceedings, and that,
Page 391 U. S. 10
when issuance of permanent certificates was held erroneous on
judicial review, the FPC might, on remand, impose new certificate
conditions for refunds of amounts previously collected above the
subsequently determined in-line price. On September 28, 1960, the
FPC began its post-
CATCO regulation of sales in Texas
Railroad Commission Districts 2, 3, and 4, the three Texas Gulf
Coast districts which are involved in these proceedings, by issuing
its General Policy Statement, announcing a guideline ceiling price
for new sales in each district of 18� per Mcf. On March 23, 1964,
at the conclusion of the District 4 (
Amerada) proceeding,
the FPC determined an in-line price of 16� per Mcf for sales
contracted after the issuance of the Policy Statement. The FPC
relied primarily on a comparison of prices in contracts entered
into since the Policy Statement and during the preceding two years.
The FPC noted that 82% of post-Policy Statement sales were at 16�
or more per Mcf. It gave "some measure of weight" to its 18� Policy
Statement guideline price. Some weight was also accorded to prices
under temporary certificates because only 1.4% of the gas in
the
brk:
area was moving under permanent certificates, though the FPC was
mindful that the temporary prices were "suspect," and took their
unreliability into account when it rejected the 17.2� average
contract price. The FPC's conditional certification of proposed
sales in District 4 was appealed to the Court of Appeals for the
Tenth Circuit. That court upheld the FPC's price line against
contentions by certain consumers and distributors (the "seaboard
interests") that the 16� price was too high and that, in fixing
that price, the FPC erred in taking account of prices at which gas
had been sold under temporary certificates. On September 22, 1965,
the FPC issued its in-line price orders in the District 2
(
Sinclair) and District 3 (
Hawkins) proceedings
reaffirming an earlier established price of 16� for the pre-Policy
Statement period in District 3, and for the later period fixing a
16� price in District 2 and 17� in District 3. In fixing the 16�
District 2 price the FPC gave full weight to the permanently
certificated prices at which about 40% of the gas in the area was
then moving; some but "not undue" force to the temporary prices at
which 60% of the gas currently flowed; accorded "some weight" to
the original, unconditioned prices in the area and to the 16�
volumetric median and 15.29� volumetric weighted average prices for
post-Policy Statement sales, and recognized that 53% of the gas in
the area was moving at prices at or below 16�. In fixing the 16�
District 3 price, the FPC gave full force to permanently
certificated sales of small volumes of gas below 16� and
comparatively large volumes
Page 391 U. S. 11
at 16� and 16.2�; considered the fact that a little less than
half the total volume of gas was sold at 16�. or less; gave "some
weight" to permanently certificated sales of very large volumes at
17.5� or above (even though those were regarded as "suspect"
prices), and apparently considered the weighted average price of
15.16� for all except the latter suspect sales. In fixing the 17�
District 3 price the FPC gave full weight to the permanently
certificated sales of moderate volumes of gas at 15� and 16.2�, a
small volume at 16.5�, and large volumes at 18�; gave "some weight"
to temporary prices; noted that the 17� price reflected the
weighted average of 16.17� for permanently certificated sales;
accorded some weight to original, unconditioned prices in the area,
and considered the fact that 43% of all permanently certificated
area sales were at or above 17�. The FPC's orders conditionally
certificating the proposed sales in Districts 2 and 3 were appealed
together to the Court of Appeals for the District of Columbia
Circuit, which sustained the seaboard interests' contention that
the post-Policy Statement prices for Districts 2 and 3 were too
high and that the FPC erred in considering temporary and
unconditioned prices. It rejected Superior Oil Company's contention
that the initial prices in District 3 for both pre- and post-Policy
Statement periods were too low, Superior having urged that the FPC
erroneously excluded from consideration nine large-volume sales at
20� per Mcf when it set the 16� price in District 3; that, in
fixing the initial prices, the FPC erroneously excluded a number of
1955-1956 sales at 17.5� to Coastal Transmission Company; that,
with respect to both time periods, the FPC erroneously failed to
consider prices embodied in settlement orders; that the FPC failed
to take enough notice of temporary prices and refused to consider
prices of intrastate sales, and that, for both periods, the FPC had
incorrectly relied on estimated, rather than actual
brk:
volumes of gas sold. The FPC did not expressly consider whether
any of the "in-line" prices it fixed were suitable when regarded as
refund floors,
i.e., a level below which the FPC may not
order refunds pursuant to § 4(e) of the Natural Gas Act. Most of
the producers in the District 4 proceeding had applied for and been
granted temporary certificates under § 7(c) of the Act, those
certificates authorizing them to sell gas at or below 18� per Mcf,
the then-guideline price. Eight certificates provided for refunds
should the eventual in-line price be lower than that charged under
the temporary certificate; the other certificates contained only
general cautionary language respecting further FPC action. The FPC
ultimately ordered the District 4 producers to refund sums
collected under the temporary
Page 391 U. S. 12
certificates in excess of the in-line rate. The Court of Appeals
for the Tenth Circuit held that the FPC lacked power to order
refunds of amounts collected under unconditioned temporary
certificates, reasoning that to permit such refunds would undermine
producer confidence and destroy stability. In the District 2 and
District 3 proceedings, the New York Public Service Commission
contended that there was no public need for the gas, and alleged
that several pipelines were already obligated by contract either to
take more gas than they could foreseeably use or to pay for it. The
FPC refused to give more than perfunctory consideration to this
"need" issue, which it concluded should be dealt with in pipeline,
rather than producer, proceedings. The Court of Appeals for the
District of Columbia Circuit held that the FPC erred in not meeting
the need issue in the producer certification proceeding.
Held:
1. The post-Policy Statement period initial price of 16� per Mcf
in District 4 was not based on impermissible factors, and was not
unreasonable. Pp.
391 U. S.
28-30.
(a) The FPC did not abuse its discretion in giving some weight
to the guideline and temporary prices (especially since 98.6% of
the gas was flowing under temporary certificates), since both those
types of prices, like permanently certificated prices, give some
indication of cost trends. P.
391 U. S. 29.
(b) The 16� price, which was at the lower end of the spectrum of
current prices considered by the FPC, was within the "zone of
reasonableness" within which the FPC has rate-setting discretion,
and satisfied the
CATCO mandate against abrupt price
rises. Pp.
391 U. S.
29-30.
2. The FPC did not abuse its discretion in establishing the
in-line prices in Districts 2 and 3. Pp.
391 U. S.
32-36.
(a) The FPC's consideration of temporary and unconditioned
contract prices was proper. P.
391 U. S. 32.
(b) The 16� and 17� initial prices were within the "zone of
reasonableness," and did not breach the
CATCO directive.
P.
391 U. S. 32.
(c) The FPC properly discounted the force of the 20� sales which
were out of line with respect to the post-
CATCO price
structure and which the FPC had reason to believe would have been
set aside on judicial review had it not been for a procedural
defect. P.
391 U. S. 34.
(d) The prices to Coastal Transmission Company (a pipeline
company which, at the time of the sales, did not have a
certificate
Page 391 U. S. 13
and was not yet in operation) were properly discounted by the
FPC, as those prices may have included a higher than normal
allowance for risk. Pp. 34-35.
(e) The FPC had discretion to disregard the prices embodied in
the settlement orders as not supplying independent evidence of
market trends. P.
391 U. S. 35.
(f) The FPC gave adequate consideration to temporary prices, and
it properly rejected evidence of intrastate prices as not covering
the entire area or being representative. P.
391 U. S. 35.
(g) Actual volumes of gas sold during 1962 and 1963 were not
known, and FPC's reliance on estimated volumes was therefore
justified. Pp.
391 U. S.
35-36.
3. An in-line price is a "refund floor" below which the FPC may
not order refunds under § 4(e) of the Natural Gas Act. Pp.
391 U. S.
22-24.
4. The in-line prices fixed here were not impermissibly high
when viewed as refund floors. Pp.
391 U. S.
36-40.
(a) Though it was regrettable that the FPC did not explicitly
consider whether or not the in-line prices it fixed were suitable
when regarded as refund floors, it was not obliged in this instance
to do so.
See Callery, supra. P.
391 U. S. 37.
(b) The 16� price in the District 4 proceeding was not beyond
the FPC's power when viewed as a refund floor, since it was near
the lower end of the price range suggested by the price evidence.
P.
391 U. S. 38.
(c) The 16� price in the District 2 proceeding and the 17� price
in the similar District 3 proceeding (neither of which is likely to
exceed the probable Texas Gulf Coast area rate) were within the
FPC's authority when viewed as refund floors; despite the
weaknesses in the FPC's opinion with respect to these aspects, it
is desirable to terminate this protracted and outmoded proceeding.
Pp.
391 U. S.
39-40.
5. In the exercise of its power to condition permanent
certificates under § 7(e), the FPC may require producers to refund
amounts collected under outstanding, unconditioned temporary
certificates in excess of the finally established in-line price.
Pp.
391 U. S.
43-45.
(a) Parties, at least those other than the producer itself, may
challenge a temporary certificate at the time a permanent
certificate is applied for, notwithstanding the time limits on
appeal set out in § 19(b) of the Act. Pp.
391 U. S.
43-44.
Page 391 U. S. 14
(b) To hold that refunds could not be ordered for the interim
period on the ground urged by the producers that a temporary
certificate creates vested rights which maybe altered only
prospectively would contravene the objectives of the Natural Gas
Act. P.
391 U. S. 44.
(c) When a producer, due to an emergency, has requested
permission to deliver gas before normal certification procedures
are completed, it is not unfair in return for that permission that,
when those procedures are terminated the producer's terms may be
retrospectively altered to conform to the public interest. Pp.
391 U. S.
44-45.
6. Neither the procedure followed nor the result reached by the
FPC in ordering refunds constituted an abuse of discretion because
of the particular circumstances of the
Amerada proceeding.
Pp.
391 U. S.
45-47.
7. The FPC did not abuse its discretion in deciding that the
question whether the gas to be sold is actually needed by the
public can be better dealt with in pipeline, rather than producer,
proceedings. Pp.
391 U. S.
47-52.
(a) Data about the purchasing pipeline's total gas supply, its
take-or-pay situation under outstanding sales contracts, the
purchasing pipeline's customers and the alternative uses for gas by
other pipelines which might buy it are not in the producers', but
in the pipelines', possession. P.
391 U. S. 49.
(b) The pipeline proceedings, supplemented by other forms of
regulation available to the FPC, will, so far as appears from the
present record, provide an adequate forum in which to confront both
the take-or-pay and end-use aspects of the need issue. Pp.
391 U. S.
50-52.
Nos. 60, 61, and 62, 370 F.2d 181, affirmed in part, reversed in
part; Nos. 80 and 97, 376 F.2d 578, and Nos. 111, 143, 144, and
231, 126 U.S.App.D.C. 26, 373 F.2d 816, reversed.
Page 391 U. S. 15
MR. JUSTICE HARLAN delivered the opinion of the Court.
These cases present questions arising out of the issuance by the
Federal Power Commission, pursuant to § 7 of the Natural Gas Act 52
Stat. 824, as amended, 15 U.S.C. § 717f, of "permanent"
certificates authorizing producers to sell natural gas to pipelines
for transportation and resale in interstate commerce.
Page 391 U. S. 16
An understanding of the issues requires some background. Section
7(c) of the Natural Gas Act provides that a natural gas company may
engage in a sale of natural gas subject to the Commission's
jurisdiction only if it has obtained from the Commission a
certificate of public convenience and necessity. Such a "permanent"
certificate may issue only after notice and hearing to interested
parties, although a proviso to § 7(c) enables the Commission in
cases of emergency to issue temporary certificates without notice
and hearing, pending the determination of an application for a
permanent certificate. Section 7(e) states that permanent
certificates are to be granted if, and only if, the Commission
finds that the proposed sale "is or will be required by the present
or future public convenience and necessity. . . ." That section
further provides that the Commission may attach to certificates
"such reasonable terms and conditions as the public convenience and
necessity may require."
Prior to 1954, the Commission construed the Natural Gas Act as
empowering it to regulate only sales of gas by pipelines, and not
sales by producers. This Court held to the contrary in
Phillips
Petroleum Co. v. Wisconsin, 347 U. S. 672.
Since then, the Commission has been engaged in a continuing effort
to adapt the provisions of the Act to regulation of producer sales.
The method finally resolved upon for determining the "just and
reasonable" rate at which § 4 of the Act requires that natural gas
be sold was to conduct a number of area rate proceedings, looking
to the establishment of maximum producer rates within each
producing area. This method of regulation has recently been
approved by us in the
Permian Basin Area Rate Cases,
390 U. S. 747.
Other area rate proceedings are underway, and they will eventually
encompass areas accounting for some 90% of all the gas sold in
interstate commerce.
See id. at
390 U. S. 758,
n. 18.
Page 391 U. S. 17
The decision to rely on area rate regulation as the means for
establishing just and reasonable rates under §§ 4 and 5 of the Act,
and its implementation, have thus far occupied more than a decade.
During this period, the Commission was obliged to rest interim
producer rate regulation on § 7. In the early years following this
Court's first
Phillips decision,
supra, the
Commission took a narrow view of its § 7 powers, and the field
price of natural gas began to soar. [
Footnote 1] Matters came to a head in the so-called
CATCO proceeding, in which the Commission certificated the
sale of the largest quantity of natural gas theretofore dedicated
to interstate commerce at a price above those then prevailing, on
the ground that, if it denied the certificate the refusal of
producers to dedicate the gas might result in an eventual shortage
in supply. This Court held in
Atlantic Rfg. Co. v. Public Serv.
Comm'n (CATCO), 360 U. S. 378,
that the Commission should have done more.
The Court began in
CATCO by stating that the Natural
Gas Act "was so framed as to afford consumers a complete, permanent
and effective bond of protection from excessive rates and charges."
360 U.S. at
360 U. S. 388.
The Court then noted that the Act required that all rates charged
be "just and reasonable." However, the Court stated that the
determination of just and reasonable rates under § § 4 and 5 was
proving to be inordinately time-consuming, and that, because those
rates became effective only prospectively, the consumer had no
protection from excess charges collected during the pendency of
those proceedings. The Court said:
"[T]he inordinate delay presently existing in the processing of
§ 5 proceedings requires a most careful scrutiny and responsible
reaction to initial price
Page 391 U. S. 18
proposals of producers under § 7. . . . The fact that prices
have leaped from one plateau to the higher levels of another . . .
[makes] price a consideration of prime importance. This is the more
important during this formative period, when the ground rules of
producer regulation are being evolved. . . . The Congress, in §
7(e), has authorized the Commission to condition certificates in
such manner as the public convenience and necessity may require.
Where the proposed price is not in keeping with the public interest
because it is out of line or because its approval might result in a
triggering of general price rises or an increase in the applicant's
existing rates by reason of 'favored nation' clauses or otherwise,
the Commission, in the exercise of its discretion, might attach
such conditions as it believes necessary."
360 U.S. at
360 U. S.
391.
After the
CATCO decision, the Commission, under the
scrutiny of the courts, began to work out a system for determining
the maximum initial prices at which gas should move, pursuant to
contracts of sale, during the interval preceding establishment of
just and reasonable rates. It based this "in-line" price upon
current prices for gas in the area of the proposed sale, taking
into account the possibility that the proposed rate might result in
other price rises due to most-favored-nation clauses. [
Footnote 2] The
Page 391 U. S. 19
Commission and courts generally excluded from consideration or
gave diminished weight to those current prices which were "suspect"
because they were embodied in permanent certificates still subject
to judicial review; because they were contained in temporary
certificates issued on the
ex parte representations of
producers; or because they had been certificated in proceedings
which occurred before this Court's
CATCO decision or in
proceedings from which representatives of East Coast consumers and
distributors (commonly referred to as the "seaboard interests") had
been erroneously excluded. [
Footnote 3] After some hesitation, [
Footnote 4] the Commission decided to bar
producers from presenting cost evidence at in-line price
proceedings, on the ground that its admission would make the
hearings too long drawn out. After determining the in-line price,
the Commission conditioned the permanent certificate to provide
that the producer could not initially sell the gas at a greater
price. The Commission also began to condition certificates so as to
limit the level to which the price might be raised, pursuant to
escalation clauses in the contract, during a given period or
pending completion of the relevant area rate proceeding. [
Footnote 5]
This Court generally approved this method of regulation in
United Gas Improvement Co. v. Callery Properties, Inc.,
382 U. S. 223.
There, the Court held that the Commission might properly refuse to
hear cost evidence in in-line proceedings, and that the Commission
might
Page 391 U. S. 20
impose moratoria on price increases above specified levels. The
Court also held in
Callery that, when issuance of
permanent certificates is held on judicial review to have been
erroneous, the Commission may, on remand, insert in the new
certificates conditions requiring refund of amounts collected under
the erroneously issued certificates in excess of the subsequently
determined in-line price.
The cases now before us originated in producer applications for
permanent certificates to sell gas produced in three Texas Railroad
Commission districts on the Texas Gulf Coast, under contracts
entered into between 1958 and 1963. The Commission's conditional
certification of proposed sales in District 4, 31 F.P.C. 623, was
appealed to the Court of Appeals for the Tenth Circuit. That Court
upheld the Commission's price line against challenges by both
producers and the seaboard interests, rejecting in particular the
charge of the seaboard interests that the Commission erred in
taking account of prices at which gas had been sold under temporary
certificates. 30 F.2d 181. In the same opinion, the Tenth Circuit
stated that the Commission had no power to order refunds of amounts
collected by producers in the past under temporary certificates
which contained no refund conditions and had not been appealed, and
it subsequently reiterated that view in reversing on appeal a
Commission decision, 36 F.P.C. 309, ordering the District 4
producers to make such refunds. 376 F.2d 578.
Orders of the Commission conditionally certificating the
proposed sales in Districts 2 and 3, 34 F.P.C. 897 and 930, were
appealed together to the Court of Appeals for the District of
Columbia Circuit. In a single opinion, that court held that, in the
circumstances of the cases before it, the Commission had erred in
giving weight to sales under temporary certificates when it set the
in-line prices. No issue as to refund power was raised in the
Page 391 U. S. 21
District of Columbia appeal, but the court did hold that the
Commission committed further error in reserving to pipeline
proceedings the question, raised by seaboard interests, of whether
there was a public need for the gas which was to be sold. 126
U.S.App.D.C. 26, 373 F.2d 816.
We granted certiorari and consolidated the cases for argument,
389 U.S. 811, to consider the following matters: (1) Did the
Commission err in determining the in-line prices here in issue? (2)
May the Commission order refunds of amounts collected under
unconditioned temporary certificates in excess of the eventually
determined in-line price? (3) Must the Commission, on request of
interested parties, decide in the certification proceeding itself
whether the gas to be sold is actually needed by the public, or may
it properly deal with that issue only in pipeline proceedings? For
reasons which follow, we affirm the decision of the Court of
Appeals for the Tenth Circuit and reverse that of the Court of
Appeals for the District of Columbia Circuit on the in-line price
question. We reverse the decision of the Tenth Circuit on the
refund issue and that of the District of Columbia Circuit on the
matter of "need." We uphold the orders of the Commission in
full.
I
The first issue is whether the Commission acted correctly in
setting the in-line prices here under review. In order adequately
to resolve that question, it is necessary to have a more precise
idea of the functions of in-line prices.
One function of an in-line price is that it serves as a
"ceiling" on the rate at which gas may be sold under the
certificate containing the price condition. However, its effect in
preventing contractually authorized price rises is legally limited,
for, under § 4 of the Act, a producer
Page 391 U. S. 22
is free, upon 30 days' notice to the Commission, to raise its
price to the extent that its contract permits, subject to the
Commission's power under § 4(e) to suspend the effectiveness of the
increase for a period of five months and to order refunds if the
increased rate turns out to be higher than the just and reasonable
rate thereafter found for the area. [
Footnote 6]
A second function of an in-line price is that it constitutes a
"floor" below which the Commission may not order refunds under §
4(e) of the Act. Section 4(e) states that, upon the filing of a § 4
rate increase, the Commission may, on its own authority, undertake
a hearing to determine whether the rate is just and reasonable,
simultaneously suspending the rate increase for up to five months.
If the suspension period expires before the completion of the
hearing, the Commission may,
"by order, require the natural gas company to furnish a bond . .
. to refund any amounts ordered by the Commission, to keep accurate
accounts in detail of all amounts received by reason of such
increase . . and, upon completion of the hearing and decision, to
[
sic] order such natural gas company to refund, with
interest, the portion of such increased rates or charges by its
decision found not justified. "
Page 391 U. S. 23
The Commission's practice has been that, when a producer files a
rate increase on a contract in an area where an area rate
proceeding is in progress, its application is consolidated into the
area rate proceeding, thereby rendering it subject to the refund
provision of § 4(e). [
Footnote
7]
It has sometimes been contended that, when a producer operating
under a nonreviewable permanent certificate increases its price
under § 4, the permanently certificated price is not a lower limit
on the refund power, and that, if the eventual just and reasonable
area rate is below the permanently certificated price, the
Commission may order a refund not merely of the price increase, but
of the entire difference between the increased rate and the just
and reasonable rate. [
Footnote
8] The Commission has never passed on this contention,
[
Footnote 9] and this Court has
twice rejected it in dictum. In
Sunray Mid-Continent Oil Co. v.
FPC, 364 U. S. 137,
364 U. S. 146,
the Court interpreted § 4(e) as meaning that
"the Commission is empowered to require the company to collect
the increment under bond and accounting, and refund it if it could
not make out its case for the increase."
In
Callery, supra, the Court stated that
"[t]he fixing of an initial 'in-line' price establishes a firm
price at which a producer may operate, pending determination of a
just and reasonable rate, without any contingent obligation to make
refunds should a just and reasonable rate turn out to be lower than
the 'in-line' price."
382 U.S. at
382 U. S.
227.
We adhere to the dicta in
Callery and
Sunray
Mid-Continent. That outcome comports better with the
Page 391 U. S. 24
language of § 4(e) than does the alternative. It is true that §
4(e), in terms, gives the Commission power to refund "the portion
of such increased rates or charges" found to be excessive, and does
not expressly limit the refund to the rate increase or increment.
However, the accounting provision, which appears earlier in the
same sentence, requires that the producer account only for the
"amounts received by reason of such increase." If it had been
intended that the refund obligation should extend to greater
amounts, the accounting requirement logically should have extended
to them also. Viewing the Act more broadly, there is another reason
why this interpretation of § 4(e) is preferable. It seems
incontestable that, if a producer consistently sells gas at the
price specified in a final, permanent certificate, and does not
attempt to increase its price, the Commission may not order it to
make refunds simply because the just and reasonable rate for its
area turns out to be below the in-line price. This would amount to
a reparation order, and this Court has repeatedly held that the
Commission has no reparation power. [
Footnote 10] It would be anomalous to treat an increased
price as a trigger for a refund obligation which would leave the
producer with a smaller net return than if it had never increased
its price at all. We therefore consider and hold that an initial
price which is authorized in a final, unconditioned permanent
certificate is a lower limit below which a refund cannot be ordered
under § 4(e).
Since an initial price and a refund floor conceivably may serve
significantly different ends, [
Footnote 11] we shall give
Page 391 U. S. 25
separate consideration to these two functions of the in-line
prices now under review. It is appropriate to begin with the
initial price function, because, in the proceedings before us, the
Commission apparently viewed the in-line prices it was setting
almost entirely as initial prices, and gave no explicit
consideration to their effects as refund floors. [
Footnote 12]
A
The thrust of this Court's
CATCO opinion was that the
Commission should use its § 7 conditioning power to prevent large
jumps in initial contract prices, pending the determination of just
and reasonable rates. At one time, the Commission apparently hoped
that, by receiving abridged cost evidence, it could establish
maximum initial prices which would be near approximations of the
just and reasonable rates which would later be established. The
Commission eventually concluded that this hope was ill-founded,
and, in
Callery, this Court approved the Commission's
exclusion of cost data from certification hearings.
See
382 U.S. at
382 U. S. 228
and n. 3.
In view of the Commission's decision to rely solely upon
contemporaneous contract prices in setting initial rates, there can
be no assurance that an initial price arrived at by the Commission
will bear any particular relationship to the just and reasonable
rate. Any such assurance would necessarily be based on a belief
that the current contract prices in an area approximate closely the
"true" market price -- the just and reasonable rate. Although there
is doubtless some relationship, and some economists have argued
that it is intimate, [
Footnote
13] such a belief would contradict the basic assumption that
has caused natural gas production to be subjected to regulation and
which must have underlain this Court's
CATCO decision
Page 391 U. S. 26
-- namely, that the purchasing pipeline, whose cost of purchase
is a current operating expense which the pipeline is entitled to
pass on to its customers as part of its rates, lacks sufficient
incentive to bargain prices down. [
Footnote 14]
One way in which the Commission might have fulfilled the
CATCO mandate to ensure that the lack of purchaser
bargaining incentive did not result in too drastic an interim price
rise would have been to freeze prices at their pre-
CATCO
levels. However, this would have resulted in locking into the price
structure some of the abrupt leaps in price which had occurred
prior to
CATCO, as well as risking the eventual erosion of
producer incentive through disregard of rising costs. Hence, it was
reasonable for the Commission to set initial prices by reference to
contemporary contract prices, which, though not an accurate
reflection of the "true" market price, were the only indirect
evidence available to the Commission of cost trends. And it was
also within the Commission's discretion to exclude, where possible,
those contract prices still subject to Commission and court review,
because those prices might reflect price jumps impermissible under
CATCO.
Thus, the initial price doctrine as it had developed by the time
of
Callery, see 382 U.S. at
382 U. S.
226-228, was a rational and permissible way of
implementing the
CATCO requirement. Turning to the
particular proceeding now under review, we hold that the methods
there used by the Commission were also acceptable ways of
determining initial prices.
On September 28, 1960, the Commission began its
post-
CATCO regulation of sales in the districts here
Page 391 U. S. 27
involved by issuing its Statement of General Policy No. 61-1, 24
F.P.C. 818. The Policy Statement announced the ceiling price at
which new sales would be certificated in each district. For each of
Texas Railroad Commission Districts 2, 3, and 4, the Policy
Statement ceiling was 18� per Mcf (thousand cubic feet) of gas.
With respect to District 4, the Commission on August 30, 1962,
determined an in-line price of 15� per Mcf for sales contracted
prior to September 28, 1960, the date of the Policy Statement. 28
F.P.C. 401. That decision is not in issue here. On the same date,
the Commission scheduled a proceeding, known as the
Amerada proceeding, to determine the in-line price for
sales contracted between September 28, 1960, and August 30, 1962.
28 F.P.C. 396.
On March 23, 1964, the Commission terminated the
Amerada proceeding by issuing the first of the orders here
under review. 31 F.P.C. 623. The Commission determined that the
in-line price for the period under study should be 16� per Mcf. In
reaching this conclusion, the Commission relied primarily on a
comparison of prices in contracts entered into during the two-year
life of the Policy Statement and the preceding two years, on the
ground that the in-line price should mirror the price at which
substantial quantities of gas were currently moving in interstate
commerce.
This desire to reflect current conditions also caused the
Commission to give some weight to prices under temporary
certificates, because only 1.4% of the gas in the area was
currently moving under permanent certificates. The Commission
recognized that these temporary prices were "suspect," and that
they largely consisted of the very prices whose "in-lineness" was
then being determined. However, the Commission decided that the
risk of considering such prices was overbalanced by the fact that
not to take them into account would be to ignore the
Page 391 U. S. 28
prices at which the great bulk of gas was then moving in
commerce. The Commission did take the unreliability of the
temporary prices into consideration when it refused to accept the
17.2� average contract price for all sales as the in-line price,
relying as well upon its belief that "the teachings of
CATCO require that we draw the line at the lowest
reasonable level." 31 F.P.C. at 637. The Commission also placed
"some measure of weight" on its Policy Statement guideline price
promulgated in 1960. The Commission further noted that 82% of the
gas sold under post-Policy Statement contracts moved at 16� or more
per Mcf, and stated that,
"[i]n the final analysis, our action in fixing the price at
which these sales should be certificated requires an exercise of
our informed judgment and utilization of the expertise developed in
the handling of thousands of producer certificate
applications."
31 F.P.C. at 636-637.
On appeal, the Tenth Circuit approved the Commission's partial
reliance upon temporary prices and upon its Policy Statement. 370
F.2d 181. That decision is challenged by the seaboard interests,
who claim that the Commission's reliance upon these "improper"
factors caused it to set too high a price for the post-Policy
Statement period.
We cannot conclude, given the extraordinary discretion which
necessarily attends such a finding as the Commission was required
to make, that the Commission took into account any impermissible
factors or that the resulting initial price was too high as a
matter of law. The seaboard interests apparently concede that
contract prices are relevant in fixing initial prices, for they do
not object to the Commission's consideration of permanently
certificated prices. They complain only of the weight given the
guideline and temporarily certificated prices. However, permanently
certificated prices are germane only because they provide some
indication of cost trends.
Page 391 U. S. 29
See supra at
391 U. S. 25-26.
Guideline and temporary prices may serve the same function.
The Commission's District 4 guideline price, though its exact
level was admittedly arbitrary, did place a "lid" on contract
prices in the area for the period. The guideline price was
therefore relevant to the determination of initial prices insofar
as contract prices in the area would have been higher but for the
guideline price, and to the extent that those higher prices would
have represented cost trends and not merely the absence of a free
market. The Commission evidently did not give the guideline price
great weight, since it set the initial rate some 2� lower. We think
that the weight given was justified.
Consideration of the temporary prices was also warranted because
they pointed to cost trends, especially in light of the fact that
98.6% of the gas was then flowing under temporary certificates.
Their use had an additional justification. In District 4, the
seaboard interests evidently challenged almost all applications for
permanent certificates at prices above 15� per Mcf, thereby greatly
delaying the issuance of permanent certificates at higher levels.
[
Footnote 15] Had the
Commission refused to consider any but permanently certificated
prices in setting the initial price, it would, in effect, have
allowed the seaboard interests to determine that price. We consider
that the Commission did not abuse its discretion in giving the
temporary prices some weight.
Finally, we hold that the ceiling price of 16� was within the
"zone of reasonableness" within which the courts may not set aside
rates adopted by the Commission,
see, e.g., FPC v. Natural Gas
Pipeline Co., 315 U. S. 575,
315 U. S.
585-586, and that it fulfilled the
CATCO
mandate not to allow abrupt price rises. The 16� price was at the
lower end of the spectrum of current prices
Page 391 U. S. 30
considered by the Commission, and it embodied only a 1� price
rise.
To determine the in-line prices in Texas Railroad Commission
Districts 2 and 3, for which the Policy Statement had also set a
ceiling price of 18� per Mcf for sales after September 28, 1960,
the Commission set two separate proceedings. The District 2 or
Sinclair proceeding, scheduled on March 25, 1964, involved
the establishment of in-line prices for sales under contracts
executed between May 12, 1958, and January 1, 1964. [
Footnote 16] The District 3 or
Hawkins proceeding, initiated on March 30, 1964, involved
sales under contracts executed between September 16, 1958, and
October 1, 1963.
See 31 F.P.C. 725. In both proceedings,
the Commission began by dividing all of the sales in question into
two groups, those contracted prior to the date of the Policy
Statement and those contracted afterward. The two proceedings were
terminated by two Commission orders of September 22, 1965,
determining in-line prices for each area during each period. 34
F.P.C. 897, 930.
In the District 2 or
Sinclair proceeding, the
Commission set an initial price of 15� per Mcf for the pre-Policy
Statement period and 16� for the later period. The 15� price is not
here in issue. The seaboard interests contend that the 16� price
was too high. In fixing the 16� price, the Commission took into
account five factors. First, it apparently gave full weight to the
permanently certificated prices at which about 40% of the gas in
the area was currently moving. Second, it gave some, but "not
undue," force to the temporary prices at which 60% of the gas
currently flowed. Third, it assigned "some weight" to the original,
unconditioned contract prices in the area, on the ground that those
prices "do show economic trends in the area." 34 F.P.C. at
Page 391 U. S. 31
937. Fourth, the Commission took into consideration the 16�
volumetric median price and the 15.29� volumetric weighted average
price of all permanently and temporarily certificated sales in the
area after the date of the Policy Statement. Fifth, it took into
account the fact that 53% of the gas in the area was presently
moving at prices at or below 16�.
In the District 3 or
Hawkins proceeding, the Commission
fixed an initial price of 17� per Mcf for the post-Policy Statement
period and reaffirmed an earlier-established 16� initial price for
previous sales. The seaboard interests attack the 17� price as too
high. Superior Oil Company asserts that both prices are too low. We
confine ourselves at present to the contention of the seaboard
interests. In arriving at the 17� price, the Commission considered
five factors. First, it gave full weight to the permanently
certificated sales of moderate volumes of gas at 15� and 16.2�, a
small volume at 16.5�, and large volumes at 18�. Second, it
accorded "some weight" to temporary prices. Third, it noted that
the 17� price "[reflects] the weighted average price of 16.17
cents" for permanently certificated sales. 34 F.P.C. at 903.
Fourth, it gave "some weight" to original, unconditioned contract
prices, for exactly the same reason as in
Sinclair.
See 34 F.P.C. at 902. Fifth, the Commission took into
consideration the fact that 43% of all permanently certificated
sales in the area were at prices at or above 17�.
On appeal, the Court of Appeals for the District of Columbia
Circuit sustained the challenge of the seaboard interests to both
the
Sinclair and
Hawkins post-Policy Statement
prices, holding that it was error for the Commission to give any
consideration to temporary and unconditioned contract prices. 126
U.S.App.D.C. 26, 373 F.2d 816. That decision is attacked by all of
the producer parties.
Page 391 U. S. 32
The producers assert that the Court of Appeals erred in holding
that the Commission should not have taken into account temporary
and unconditioned contract prices when it fixed the post-Policy
Statement prices for Districts 2 and 3. We sustain this contention.
It is true that, in Districts 2 and 3, a much larger percentage of
the gas was currently moving under permanent certificates than in
District 4. However, for reasons which appear in our discussion of
the District 4 proceedings,
see supra at
391 U. S. 28-29,
the temporary and unconditioned contract prices were nonetheless
germane as indicating cost trends. [
Footnote 17] The Commission acknowledged their relative
unreliability by according them only a diminished force. In these
circumstances, we cannot conclude that the Commission exceeded its
authority by giving them any weight at all.
Nor do we find any error in the Commission's selection of the
16� and 17� initial prices from the information before it. Although
these prices, and particularly the 17� price in
Hawkins,
ranged nearer the high end of the price spectrum than did the
District 4 price, we cannot say that either was so high as to fall
outside the "zone of reasonableness" within which the Commission
has rate-setting discretion.
See supra at
391 U. S. 29. And
since the initial prices decided upon were only 1 above those
previously prevailing, they did not breach the
CATCO
directive to avoid excessively large price increases.
The Superior Oil Company contends that the initial prices
established in District 3 for both the pre- and post-Policy
Statement periods were too low for a number of reasons, mainly
because the Commission excluded
Page 391 U. S. 33
from consideration certain relatively high prices at which gas
was presently being sold in the area. All of these challenges were
rejected by the Court of Appeals for the District of Columbia
Circuit.
The data considered by the Commission in setting the 17�
District 3 post-Policy Statement price have already been described.
See supra at
391 U. S. 31. In
establishing the 16� pre-Policy Statement price, the Commission
took into account four factors. First, it gave full force to
permanently certificated sales of small volumes of gas at prices
below 16� and of comparatively large volumes at 16� and 16.2�.
Second, it took into consideration the fact that 72% of all sales,
comprising "a little more than half" the total volume of gas,
occurred at prices of 16� or less. Third, the Commission gave "some
weight" to permanently certificated sales of very large volumes of
gas at 17.5� or above, even though it regarded those prices as
suspect. Fourth, the Commission apparently took into account the
weighted average price of 15.16� for all sales except the suspect
sales at 17.5� and above.
Superior's most strongly pressed contention is that the
Commission erred in allegedly failing to consider nine large-volume
sales at 20� per Mcf when it set the 16� initial price for the
pre-Policy Statement period. The Commission recognized in its
opinion that the inclusion of these sales at full strength would
have a "strong [upward] effect" upon the average of all prices for
the period. However, it concluded that the impact of the price
should be "discounted." The Commission noted that
"six of the nine sales were involved in
Trunkline Gas Co.,
et al., 21 FPC 704 . . . with respect to which [the New York
Public Service Commission's] petition for review was dismissed
because not timely."
34 F.P.C. at 902.
Page 391 U. S. 34
The Commission then quoted from an earlier decision,
Texaco
Seaboard Inc., 29 F.P.C. 593, 597, in which it discounted the
effect of the same sales on the ground that they
"would have been set aside, for failure to permit a proper party
to intervene, save for the procedural defect in the PSC review
action in the
Trunkline case."
The Commission went on to point out that two of the three
remaining 20� sales also had been certificated in proceedings from
which the exclusion of the New York Commission had been upheld on
the same procedural ground. [
Footnote 18]
We think that the Commission acted within its discretion in
discounting the force of these 20� sales. Those sales were out of
line with respect to the price structure which emerged after
CATCO, and the Commission had reason to believe that they
would have been set aside on judicial review had it not been for a
procedural defect. We do not think that the Commission was
compelled to give full weight to these prices.
Superior also contends that the initial prices established for
the pre-Policy Statement period were too low because the Commission
excluded from consideration a number of 1955-1956 sales at 17.5� to
Coastal Transmission Company. In justification for giving
discounted effect to these prices, the Commission again cited its
Texaco Seaboard decision, 29 F.P.C. 593, in which it also
discounted those sales. Among the justifications put forward in
Texaco Seaboard was the fact that Coastal was, at the time
of the sales, a new pipeline company, which neither had a
certificate nor was yet in operation, so that the prices may have
included a higher than normal allowance for risk. We think that
this factor
Page 391 U. S. 35
alone was sufficient to justify the Commission's exercise of
discretion in discounting these sales.
Superior next asserts that, with respect to both time periods,
the Commission erred in failing to take account of certain prices
embodied in settlement orders. It is conceded by Superior that all
of these settlements occurred at the then-prevailing guideline or
in-line prices enforced by the Commission. [
Footnote 19] We hold that the Hearing Examiner
and the Commission had discretion to disregard these sales, since
they did not supply independent evidence of market trends.
Superior further complains of the Commission's alleged failure
to take enough notice of temporary prices and its refusal to
consider prices of intrastate sales. The Commission did give some
consideration to temporary prices,
see supra at
391 U. S. 31,
391 U. S. 33,
and, for reasons which appear sufficiently from what has gone
before,
see supra at
391 U. S. 26, we
hold that it did not err in refusing to give them more weight. We
also hold that the Commission acted within its discretion when it
rejected evidence of intrastate prices submitted by the producers
on the ground that:
"these prices do not cover the entire area, nor is there
anything to show that they are representative so as to make them
comparable to the interstate arrays."
34 F.P.C. at 904.
Finally, Superior asserts that the Commission acted incorrectly
in relying on estimated, rather than actual, volumes of gas sold
during both periods. We find acceptable the Commission's
justification, which was that actual volumes were not known for the
years 1962 and 1963. Moreover, use of actual volumes would have
made no significant difference, since Superior agrees [
Footnote 20]
Page 391 U. S. 36
that the only result would have been to give enhanced force to
the 20� sales, which properly were given only slight weight.
[
Footnote 21]
B
We now turn to the question whether the price levels established
by the Commission in these proceedings were proper when regarded as
refund floors. This Court stated in
CATCO that the Natural
Gas Act "was so framed as to afford consumers a complete, permanent
and effective bond of protection from excessive rates and charges."
360 U.S. at
360 U. S. 388.
Since the Natural Gas Act nowhere refers to "in-line" prices, the
"excessive rates" referred to must be rates in excess of the just
and reasonable rate at which § 4(a) commands that all gas must
move. Logically, this would seem to imply that to assure the
"complete, permanent and effective bond of protection" referred to,
any rate permitted to be charged during the interim period before a
just and reasonable rate can be determined must be accompanied by a
condition rendering the producer liable for refunds down to the
just and reasonable rate, should that rate prove lower than the
initial rate specified in the certificate.
Despite this apparent logic, the Commission seems never to have
imposed a refund condition of this type, though it has occasionally
considered the function of an in-line price as a refund floor in
determining the level of
Page 391 U. S. 37
the price. [
Footnote 22]
The courts seem never to have suggested that the Commission impose
such conditions. In
Callery, supra, this Court without
dissent approved the Commission's imposition of an initial price
unaccompanied by any such refund condition. The
Callery
Court also held, over a single dissent, that, in compelling
producers to refund excess amounts charged under permanent
certificates later invalidated on judicial review,
"the Commission could properly measure the refund by the
difference between the rates charged and the 'in-line' rates to
which the original certificates should have been conditioned. The
Court of Appeals would delay the payment of the refund until the
'just and reasonable' rate could be determined. We have said
elsewhere that it is the duty of the Commission, 'where refunds are
found due, to direct their payment at the earliest possible moment
consistent with due process.'
Federal Power Comm'n v. Tennessee
Gas Transmission Co., 371 U. S. 145,
371 U. S.
155."
382 U.S. at
382 U. S.
230.
In view of the fact that an initial price and a refund floor
might be used to achieve distinct regulatory goals,
see
supra, n 11, it seems
regrettable that the Commission and courts apparently have never
entertained the possibility of separating these two aspects of an
"in-line price" in particular cases. However, we think that, in
light of
Callery and the other precedents ,the Commission
was not obliged in this instance to give explicit consideration to
the establishment of a distinct refund floor. The same factors are
present here as in
Callery. The need to speed refunds to
consumers and to assure producers of a firm price are identical. We
cannot say, therefore, that the Commission breached any duty in
failing expressly to consider whether the prices it fixed were
suitable when regarded as refund floors.
Page 391 U. S. 38
Although we have approved the in-line prices in these cases when
looked at as initial prices, we have yet to examine them in their
role as refund floors. Viewing them in that way, we hold that they
were not impermissibly high. In the District 4 or
Amerada
proceeding, the only disputed price is the 16� price for the
post-Policy Statement period. The Commission fixed that price at a
point near the lower end of the price range suggested by the price
evidence before it, stating:
"While there is evidence that points in the direction of a
higher price we believe the teachings of
CATCO require
that we draw the line at the lowest reasonable level."
31 F.P.C. at 637. We consider that the 16� price was not beyond
the Commission's power, when regarded as a refund floor.
In the District 2 or
Sinclair proceeding, the only
price assailed as too high is the 16� price for the post-Policy
Statement period. That price was nearer the high end of the
spectrum of suggested prices than was the price established in
District 4. The Commission did not enunciate the general principle
which motivated it in selecting the 16� price level. [
Footnote 23] Although it would have
been preferable for the Commission to have explained its reasoning,
we believe that the price was permissible when regarded as a refund
floor. The 16� price embodied an increase of only 1� per Mcf over
the previously prevailing price. Such evidence as is now
available
Page 391 U. S. 39
indicates that the 16� price probably will not exceed the just
and reasonable price which will be established for the Texas Gulf
Coast in a pending area rate proceeding. [
Footnote 24] In addition, we are not unmoved by the
obvious desirability of bringing to a close this already prolonged
proceeding, which belongs to an era of regulation apparently now
ended. [
Footnote 25] We
therefore hold that, despite the weaknesses in the Commission's
opinion, the price established was within the Commission's
authority when seen as a refund floor.
In the District 3 or
Hawkins case, the only price
challenged as excessive is the 17� price for the post-Policy
Statement period. The District 3 proceeding was similar to that, in
District 2 (
Sinclair). The price decided upon was again
nearer the high end of the suggested range than that in District 4;
again, the Commission did not articulate the general principles
which motivated it. [
Footnote
26] The District 3 price is even more vulnerable to attack than
that in District 2, because it is 1� higher, and therefore more
likely to be above the just and reasonable
Page 391 U. S. 40
rate for the Texas Gulf Coast. Yet similar considerations lead
us to approve it as being within the Commission's broad discretion.
The 17� price represented only a 1� increase over the previous
District 3 price. The fragmentary evidence now available about the
forthcoming just and reasonable rate indicates that it will be only
slightly, if at all, below 17�. [
Footnote 27] It is again desirable that a prolonged and
outmoded proceeding be brought finally to a close. Hence, we are
constrained to hold that the 17� District 3 price was not excessive
as a matter of law, when looked at as a refund floor.
The next major issue is whether the Commission acted within its
powers when it ordered the producers in the District 4 or
Amerada proceeding to refund amounts previously collected
under unconditioned temporary certificates, to the extent that the
prices charged under those certificates exceeded the eventual
in-line price.
Section 7(c) of the Natural Gas Act, 15 U.S.C. § 717f(c),
contains a proviso which permits the Commission to
"issue a temporary certificate in cases of emergency, to assure
maintenance of adequate service or to serve particular customers,
without notice or hearing, pending the determination of an
application for a certificate."
Most of the producers involved in the Amerada proceeding applied
for and were granted such temporary certificates, authorizing them
to sell gas at or below the then-guideline price of 18� per Mcf.
The "emergency" which most of these producers cited to justify the
issuance of the certificates was an economic emergency which
threatened them with loss of all or part of their gas supply unless
deliveries
Page 391 U. S. 41
could begin. [
Footnote
28] Eight of the certificates contained a condition specifying
that, should the eventual in-line price be lower than that charged
under the certificate, a refund of the difference might be ordered.
The other certificates did not include an express refund condition,
although they did contain general cautionary language respecting
further Commission action. [
Footnote 29]
The history of the refund orders now under review is as follows.
When seaboard interests proposed the retroactive imposition of
refunds in virtually identical circumstances in the 1962
Skelly
Oil Company proceeding, the Commission decided not to order
refunds because
"the producers here have been operating . . . pursuant to
effective temporary certificates containing no price condition, the
validity of which [has] never been challenged on appeal."
28 F.P.C. 401, 413. In denying rehearing in
Skelly, the
Commission amplified its reasons, stating that, because there was
in the temporary certificates no explicit language to warn the
producers of the possibility of a refund,
"to proceed now and order the producers to make refunds would
not be equitable, regardless of any ultimate right we may have to
order such refunds."
28 F.P.C. 1065, 1069. While
Skelly was pending on
appeal in the District of Columbia Circuit, the seaboard interests
moved the Commission to insert prospective refund conditions in the
temporary certificates of producers in the
Amerada
proceeding now before us. In denying that request, the Commission
stated that, because the producers
Page 391 U. S. 42
had relied on the absence of refund conditions when they
dedicated their gas to interstate commerce, to impose prospective
refund conditions would "so denature the value of a Commission
authorization as to place any reliance upon our actions in this
area in serious jeopardy." 29 F.P.C. at 225.
The Court of Appeals for the District of Columbia Circuit held
on appeal in
Skelly, 117 U.S.App.D.C. 287, 329 F.2d 242,
not only that the Commission had power to order retroactive refunds
but that, in the
Skelly proceeding itself, it should
subject the question to "a broader and more penetrating analysis."
117 U.S.App.D.C. at 295, 329 F.2d at 250. In its subsequent in-line
price decision in
Amerada, the Commission noted that, in
Skelly, the Court of Appeals had made it clear that the
refund power did not depend upon the presence of express refund
conditions, but upon equitable considerations. Since the hearings
before the Commission in
Amerada had taken place prior to
the decision on appeal in
Skelly, the Commission deferred
decision of the refund question in
Amerada, so that the
parties might submit further briefs.
See 31 F.P.C. at
638-639. After full briefing of the refund issue, the Commission
ordered the
Amerada producers to refund all sums collected
under the temporary certificates in excess of the in-line rate,
with the exception of amounts expended for royalties and production
taxes prior to the date of the decision on appeal in
Skelly and in reasonable reliance upon the Commission's
orders. 36 F.P.C. 309.
On appeal of the Commission's
Amerada order setting the
in-line price and deferring the refund question, the Court of
Appeals for the Tenth Circuit noted the issuance of the subsequent
Commission order compelling refunds and held that the refund issue
was ripe for judicial review. Relying in part upon its earlier
decision in
Sunray Mid-Continent Oil Co. v. FPC, 270 F.2d
404,
Page 391 U. S. 43
the Tenth Circuit held that the Commission lacked power to order
refunds of amounts collected under unconditioned temporary
certificates. 370 F.2d 181. It reasoned that to permit such refunds
would undermine producer confidence and destroy stability. When the
Commission's refund orders were themselves appealed, the Tenth
Circuit reaffirmed its position in a per curiam opinion. 376 F.2d
578.
B
We consider that, in so holding, the Tenth Circuit erred. The
producers' initial contention in support of the opinion below is
that temporary certificates are appealable orders, and that under §
19(b) of the Natural Gas Act, 15 U.S.C. § 717r(b), review must be
sought within 60 days of the issuance of the certificate and not,
as here, at the time of application for a permanent certificate. We
find this argument unpersuasive. Temporary certificates normally
are issued
ex parte, upon receipt of an application from a
producer in the form of a letter. [
Footnote 30] This procedure is authorized by a proviso to
§ 7(e) of the Act, quoted
supra at
391 U. S. 40,
which permits the Commission to issue temporary certificates
without any notice to potentially interested persons. [
Footnote 31] Hence, no one but the
producer recipient may be aware of the issuance of a temporary
certificate within the appeal period.
Moreover, to hold that a temporary certificate must be
challenged immediately or not at all, as the producers suggest,
might encourage appeals which would impair the usefulness of
temporary certificates. Temporary certificates are intended to
permit immediate delivery of gas in emergencies. To delay the
issuance of the certificate
Page 391 U. S. 44
and the flow of the gas until the completion of judicial review
which might consume months or years would severely hamper the
performance of this function. We therefore hold that parties, at
least those other than the producer itself, [
Footnote 32] may challenge a temporary
certificate at the time a permanent certificate is applied for.
The producers' second argument is that a temporary certificate
is a "final" order creating vested rights, and that it may be
altered only prospectively. This contention is related to the last,
and has much the same flaw. To encourage early attack on temporary
certificates would diminish their utility. Yet to discourage prompt
challenges and simultaneously to hold that refunds could not be
ordered for the interim period would in large part frustrate the
objectives of the Natural Gas Act by allowing producers to operate
for long intervals [
Footnote
33] on the basis of their own representations and with only
minimal regulation by the Commission.
The producers' third contention, which coincides with the
rationale of the Tenth Circuit below and in its previous decision
in
Sunray Mid-Continent, supra, is that temporary
certificates must be retroactively unmodifiable in order that
producers may be assured of a firm price at which to operate. We
cannot accept this reasoning. When a producer has requested
permission to begin delivery of gas prior to completion of normal
certification procedures, due to an emergency, we think it not
unfair that, in return for that permission, it accept the risk
that, at the termination of those procedures the terms proposed
Page 391 U. S. 45
by it may be retrospectively altered to conform to the public
interest.
We are strengthened in that view by this Court's decision in
Callery, supra. The Court there held that, when a
permanent certificate, containing no refund condition, is held on
judicial review to have embodied too high an in-line price, the
Commission may, on remand, condition the new permanent certificate
to require refund of the excessive charges received under the old.
If the producer expectations created by a permanent certificate may
thus be overridden by the public interest, then the surely lesser
reliance induced by an "unconditioned" temporary certificate issued
on the producer's own representations should not bar a later refund
requirement. For all of these reasons, we hold that, in the
exercise of its power to condition permanent certificates under §
7(e), the Commission may require producers to refund amounts
collected under outstanding, unconditioned temporary certificates
in excess of the finally established in-line price. [
Footnote 34]
C
It remains to be considered whether the Commission was precluded
from exercising its refund power in the particular circumstances of
the
Amerada proceeding. [
Footnote 35] The background and nature of the
Amerada refund
Page 391 U. S. 46
orders have already been described. We conclude that neither the
procedure followed nor the result reached by the Commission in
imposing the
Amerada refunds amounted to an abuse of
discretion.
The producers assert that they were entitled to an irrevocable
assurance of price in order that they might rationally decide
whether to dedicate their gas to interstate commerce, and so that
they might plan their budgets during the lives of the temporary
certificates. However, we believe that such generally worded
arguments are foreclosed by our decision upholding the Commission's
refund power, for, in the course of that decision, we rejected the
producers' claim that they were legally entitled to an assurance of
a firm price at which to operate.
See supra at
391 U. S.
44-45.
The producers further contend that the Commission's repeated
indications that it would not order refunds,
see supra at
391 U. S. 41-42,
made the ordering of refunds inequitable in this instance, in that
the Commission's pronouncements caused the producers to place
unusual reliance upon the prices authorized by the temporary
certificates. However, this kind of reliance is precisely what the
Commission gave the producers an opportunity to prove on
re-briefing. We cannot say that the Commission exceeded its
discretion in finding that the producers did not show such reliance
as to deprive the Commission entirely of refund power in this case.
We note further that the Commission did give consideration to
individual pleas for relief from the refund obligation, due to
alleged hardship, [
Footnote
36] and that, in other proceedings the Commission has
Page 391 U. S. 47
granted such relief. [
Footnote 37] Therefore, although it is regrettable that
the road which led to these refund requirements could not have been
straighter, [
Footnote 38] we
hold that the Commission did not exceed its authority.
III
The third and last major issue is whether the Commission erred
in failing to make a reasoned finding that there was a public need
for the gas certificated in the District 2 and District 3
(
Sinclair and
Hawkins) proceedings. In those
proceedings, the New York Public Service Commission asserted that
there was no public need for the gas, alleging in particular that
several of the purchasing pipelines were already obligated under
"take or pay" provisions of existing contracts either to take more
gas than they could foreseeably use or to pay for it. [
Footnote 39]
In both proceedings, the Commission refused to give more than
perfunctory consideration to the issue of "need." Its stated
justification was that the need question should be dealt with in
pipeline, rather than producer, proceedings. The Court of Appeals
for the District of Columbia Circuit held that the Commission erred
in declining to come to grips with the need issue in the course of
producer certification. 126 U.S.App.D.C. 26, 373 F.2d 816. That
court held that the Commission should have directed itself not only
to the "take or pay" positions of the purchasing pipelines, but to
the question whether those
Page 391 U. S. 48
pipelines proposed to sell the gas to customers who would use it
in an "economically
inferior' way."
The Commission regulates pipelines in a number of different
ways. When a pipeline must expand its facilities significantly in
order to take on new supplies of gas, it is required by § 7(c) of
the Natural Gas Act, 15 U.S.C. § 717f(c), to obtain a certificate
of public convenience and necessity, which may be issued only after
notice and hearing. In these certification proceedings, the
Commission considers many matters, including the needs of the
pipeline's customers and its gas supply. [
Footnote 40] The Commission also grants pipelines
so-called "budget" authority to spend limited amounts on
gas-purchasing facilities on an annual basis, without further
Commission approval. [
Footnote
41] This authority is granted only after notice and opportunity
for objection. [
Footnote 42]
In addition, the Commission requires periodic reports from all
pipelines, [
Footnote 43] and
collects and publishes material on the supply of gas, including
data on the pipelines' "take or pay" positions. [
Footnote 44]
Page 391 U. S. 49
We think that the Commission did not abuse its discretion in
deciding that the need issue, in both its "take or pay" and end use
[
Footnote 45] aspects, can
be better dealt with in such pipeline proceedings than in producer
proceedings. In the first place, the requisite information is more
readily available in pipeline proceedings. To resolve the "take or
pay" issue, it is necessary to have information about the total gas
supply of the purchasing pipeline, its outstanding sales contracts,
and its "take or pay" situation under those contracts. These data
normally will be in the possession of the pipeline, but not of the
producer. Decision of the end use question must be based on
information not only about the customers of the purchasing
pipeline, but about the alternative uses to which the gas might be
put by other pipelines which might buy it. This information will be
known collectively by a number of pipelines; an individual producer
cannot even know what customer of the purchasing pipeline will
receive the gas it supplies. [
Footnote 46] Although it might be possible for the
Commission to require the relevant pipeline or pipelines to furnish
all this information in each producer certification proceeding,
[
Footnote 47] that procedure
would be cumbersome, and would
Page 391 U. S. 50
lengthen the producer proceedings, which we have previously
commended the Commission for endeavoring to shorten. [
Footnote 48]
In the second place, there is reason to believe that the
pipeline proceedings, supplemented by other forms of regulation
available to the Commission, will provide an adequate forum in
which to confront both aspects of the need issue. Turning first to
the "take or pay" question, we note that the Commission has evinced
a continuing concern about it. The current adverse "take or pay"
positions of some pipelines, stressed by the seaboard interests in
these proceedings, apparently were due in some part to a pre-1964
Commission requirement that each pipeline maintain a twelve-year
supply of gas in order to assure adequate reserves. In 1964, this
requirement was made more flexible. [
Footnote 49] The Commission in 1965 ordered pipelines to
submit more detailed reports on their contractual "take or pay"
provisions. [
Footnote 50]
And in 1967, at the termination of a rulemaking proceeding begun in
1961, the Commission prescribed by rule that contractual "take or
pay" provisions must allow the purchasing pipeline at least five
years in which to take gas previously paid for without making
additional payments. [
Footnote
51]
Thus, the Commission itself has taken steps to alleviate "take
or pay" problems. Persons who want the Commission to take
additional action have adequate opportunity to present their views
during the Commission's rulemaking [
Footnote 52] or pipeline proceedings. If a pipeline must
build substantial new facilities to handle the gas in question,
Page 391 U. S. 51
then interested persons may express their objections in the
certification proceeding. [
Footnote 53] Those who believe that a pipeline which
seeks "budget" authority is in such a "take or pay" position that
it should not be allowed to acquire new gas may ask that the
authority be denied or conditioned. Although some gas may be taken
by pipelines through existing facilities, without even "budget"
authority, [
Footnote 54]
these opportunities for a hearing seem sufficient to protect the
public interest.
The Commission has undertaken to assure that gas is not devoted
to wasteful end uses, and this Court has upheld its exercise of
such authority.
See FPC v. Transcontinental Gas Pipe Line
Corp., 365 U. S. 1. The
Commission has dealt with this question primarily in pipeline
certification proceedings. [
Footnote 55] This does not seem inappropriate, since any
new use of significant amounts of gas will normally entail the
erection of substantial new pipeline facilities, requiring
certification. Persons who anticipate that a pipeline which is
seeking "budget" authority will devote the gas to inferior end uses
may request that the authority be withheld or limited. We believe
that these opportunities for objection are adequate to protect the
public interest in conservation of gas.
Of course, our approval of the Commission's decision to deal
with the need question in pipeline proceedings does not imply that
the Commission may neglect its statutory
Page 391 U. S. 52
duty to assure that sales of gas are required by the public
"necessity." [
Footnote 56]
This statutory obligation implies that, when interested parties
assert that the Commission has permitted or is about to permit the
sale of significant quantities of unneeded gas, then the Commission
must supply an adequate forum in which to hear their contentions.
We hold only that, so far as appears from the record before us,
pipeline proceedings can serve as such a forum. If subsequent
events should demonstrate that existing pipeline proceedings are
inadequate, then the Commission must provide new arenas for
objection.
For the foregoing reasons, we affirm the decision of the Court
of Appeals for the Tenth Circuit and reverse that of the Court of
Appeals for the District of Columbia Circuit on the in-line price
issue. We reverse the decision of the Tenth Circuit on the question
of refunds and that of the District of Columbia Circuit on the
matter of need.
It so ordered.
MR. JUSTICE MARSHALL took no part in the consideration or
decision of these cases.
* Together with No. 61,
United Gas Improvement Co. v. Sunray
DX Oil Co. et al., No. 62,
Brooklyn Union Gas Co. et al.
v. Federal Power Commission et al., No. 80,
Federal Power
Commission v. Standard Oil Co. of Texas, a Division of Chevron Oil
Co., et al., and No. 97,
United Gas Improvement Co. v.
Sunray DX Oil Co., also on certiorari to the same court, No.
111,
Shell Oil Co. v. Public Service Commission of New
York, No. 143,
Skelly Oil Co. et al. v. Public Service
Commission of New York et al., No. 144,
Federal Power
Commission v. Public Service Commission of New York et al.,
and No. 231,
Superior Oil Co. v. Federal Power Commission et
al., on certiorari to the United States Court of Appeals for
the District of Columbia Circuit.
[
Footnote 1]
See generally Johnson, Producer Rate Regulation in
Natural Gas Certification Proceedings:
CATCO in Context,
62 Col.L.Rev. 773, 782-788 (1962).
[
Footnote 2]
See, e.g., United Gas Improvement Co. v. FPC, 283 F.2d
817;
Public Serv. Comm'n v. FPC, 109 U.S.App.D.C. 292, 287
F.2d 146;
United Gas Improvement Co. v. FPC, 287 F.2d 159;
United Gas Improvement Co. v. FPC, 290 F.2d 133 and 147;
California Oil Co., W. Div. v. FPC, 315 F.2d 652.
A two-party most favored nation clause assures a producer that
he will receive the highest price currently being paid by his
purchaser to any producer in the same area. A three-party most
favored nation clause guarantees a producer the highest price
presently being paid to any producer in the area by any purchaser.
See, e.g., Pure Oil Co., 25 F.P.C. 383.
[
Footnote 3]
See, e.g., United Gas Improvement Co. v. FPC, 283 F.2d
817;
United Gas Improvement Co. v. FPC, 287 F.2d 159;
Texaco Seaboard Inc., 29 F.P.C. 593;
Hassie Hunt Trust
(Operator), 30 F.P.C. 1438,
aff'd sub nom. Continental Oil
Co. v. FPC, 378 F.2d 510.
[
Footnote 4]
See United Gas Improvement Co. v. Callery Properties,
Inc., 382 U. S. 223,
382 U. S. 228,
n. 3.
[
Footnote 5]
See, e.g., Placid Oil Co., 30 F.P.C. 283. In 1961, the
Commission, by rule, prospectively limited the forms of the
escalation clauses themselves.
See infra, n 6.
[
Footnote 6]
In the cases before us, the Commission did utilize its auxiliary
power,
see supra at
391 U. S. 19-20,
to limit the amount of such § 4 increases, but the producers
remained free after six months (
i.e., 30 days' notice plus
five months' suspension) to raise their prices at least 10%, if
their contracts permitted. In 1961, after many of the contracts in
these cases had been entered into, the Commission issued a rule
which prospectively limited the types of escalation clauses which
might be included in contracts.
See Order No. 232, 25
F.P.C. 379. This order was modified by Order No. 242, 27 F.P.C.
339.
See also 18 CFR § 154.93;
FPC. v. Texaco
Inc., 377 U. S. 33,
377 U. S.
42-44.
[
Footnote 7]
See, e.g., 30 F.P.C. 1354, 1357.
[
Footnote 8]
See, e.g., 2 Joint Initial Staff Brief,
Hugoton-Anadarko-Texas Gulf Coast Area Rate Proceedings, F.P.C.
Docket Nos. AR 64-1 and AR 64-2, at 486-488.
[
Footnote 9]
The Commission specifically reserved decision of this question
in its decision in the Permian Basin area rate proceeding.
See 34 F.P.C. 1068, 1074-1075.
[
Footnote 10]
See, e.g., FPC v. Hope Natural Gas Co., 320 U.
S. 591,
320 U. S. 618;
Montana-Dakota Utils. Co. v. Northwestern Public Serv.
Co., 341 U. S. 246,
341 U. S.
254.
[
Footnote 11]
For example, in some situations a relatively high initial price
might be thought desirable to encourage producers to develop new
reserves but a lower refund floor might be deemed necessary to
protect consumers.
[
Footnote 12]
See 31 F.P.C. at 629-637; 34 F.P.C. at 900-904,
933-938.
[
Footnote 13]
See, e.g., M. Adelman, The Supply and Price of Natural
Gas 25 (1962).
[
Footnote 14]
See, e.g., Permian Basin Area Rate Cases, 390 U.S. at
390 U. S.
792-795; E. Newner, The Natural Gas Industry 148-177,
209-290 (1960).
[
Footnote 15]
See Brief for Sunray DX Oil Company
et al. 11,
23-26.
[
Footnote 16]
See 4 Joint Appendix 128.
[
Footnote 17]
The seaboard interest.s apparently followed the same course in
Districts 2 and 3 as in District 4, challenging all applications
for permanent certificates at prices above 15� per Mcf.
See Brief for Shell Oil Company
et al. 8,
19-21.
[
Footnote 18]
See 34 F.P.C. at 902, n. 3. It appears that the last of
the sales was also in this category.
See ibid.; 3 Joint
Appendix 131, 136, n. d;
Astral Oil Co., 22 F.P.C. 658 and
858.
[
Footnote 19]
See Brief for the Superior Oil Company 36, n. 48.
[
Footnote 20]
See id. at 390.
[
Footnote 21]
Superior also claims that the Commission abused its discretion
by considering sales at prices below 14� in fixing the initial
rates for both periods, even though it had excluded such sales in
previous District 3 in-line proceedings. Superior did not mention
this point in its petition for rehearing before the Commission.
See 3 Joint Appendix 314(i); Exceptions of the Superior
Oil Company to the Decision of the Hearing Examiner,
In the
Matter of H.L. Hawkins & H.L. Hawkins, Jr. (Operator),
F.P.C. Docket No. G-18077. Hence, the question is not properly
before us.
See Natural Gas Act § 19(b), 15 U.S.C. §
717r(b).
[
Footnote 22]
See, e.g., Texaco Seaboard Inc., 29 F.P.C. 593,
599.
[
Footnote 23]
The Hearing Examiner, who also arrived at a 16� price,
apparently relied upon a general standard different from that used
by the Commission in the District 4 or
Amerada
proceedings,
supra. Quoting from the Commission's opinions
in
Texaco-Seaboard Inc., 27 F.P.C. 482, 485, and
Hassie Hunt Trust (Operator), 30 F.P.C. 1438, 1445, the
Examiner said:
"' . . . the price line does not accord with the highest price
or prices permanently authorized but falls between the highest
group of prices and the median price.'"
34 F.P.C. at 952.
[
Footnote 24]
The Commission staff has recommended a just and reasonable rate
of 16.8� per Mcf for new gas well gas sold in the Texas Gulf Coast
under contracts dated after December 31, 1960, and delivered at a
central point.
See 2 Joint Initial Staff Brief,
Hugoton-Anadarko-Texas Gulf Coast Area Rate Proceedings, F.P.C.
Docket Nos. AR 64-1 and AR 64-2, at 375. The suggested just and
reasonable rate for post-1960 new gas well gas delivered at the
wellhead is 16.4� per Mcf.
Ibid. About 90% of Texas Gulf
Coast gas is centrally delivered.
See id. at 390-391.
[
Footnote 25]
During oral argument, counsel for the Commission stated that the
Commission has suspended all contested in-line price proceedings
pending completion of the area rate proceedings for the areas
involved. The just and reasonable rates determined in those
proceedings apparently will automatically become the in-line prices
for those areas.
Cf. Permian Basin Area Rate Cases, 390
U.S. at
390 U. S. 22, n.
114.
[
Footnote 26]
The Hearing Examiner was equally unspecific.
See 34
F.P.C. at 914
et seq.
[
Footnote 27]
See supra, n.
391 U.S.
9fn24|>24
[
Footnote 28]
See Brief for the Federal Power Commission 49, n.
37.
[
Footnote 29]
The certificates contained provisions to the effect that:
"This acceptance for filing shall not be construed as
constituting approval of any rate . . . ; nor shall such acceptance
be deemed as recognition of any claimed contractual right or
obligation . . . , and such acceptance is without prejudice to any
findings or orders which may be made in the final disposition of
this proceeding. . . ."
See, e.g., 1 Joint Appendix 71-72.
[
Footnote 30]
See, e.g., 1 Joint Appendix 78-81; 18 CFR § 157.17.
[
Footnote 31]
Counsel for the Commission stated on oral argument that, in the
early 1960's, the Commission, on its own initiative, did begin to
make information about issuance of temporary certificates available
to the public at its office.
[
Footnote 32]
The Court of Appeals for the Fifth Circuit has held that the
producer itself must challenge the certificate within 60 days after
it is issued.
Texaco, Inc. v. FPC, 290 F.2d 149. There is
no occasion for us to pass on the correctness of that decision.
[
Footnote 33]
Some of the producers involved in the
Amerada
proceeding delivered gas under temporary certificates for more than
2 1/2 years.
E.g., compare 1 Joint Appendix 71
with
id. at 166.
[
Footnote 34]
No party has contended that the refunds should have been based
on the eventual just and reasonable rate, and we think it clear
that the Commission did not exceed its authority in founding them
on the in-line price.
See supra at
391 U. S. 36-37;
United Gas Improvement Co. v. Callery Properties, Inc.,
382 U. S. 223,
382 U. S.
230.
[
Footnote 35]
Because the Court of Appeals held that the Commission lacked
power to require refunds, it did not pass on the producers'
contentions that the refunds actually ordered were inequitable.
Those contentions were presented to this Court in the producers'
reply brief. Although we normally do not review orders of
administrative agencies in the first instance,
see, e.g., FPC
v. United Gas Pipe Line Co., 386 U. S. 237,
386 U. S. 247,
we consider it appropriate in this instance to resolve this
question without remand to the court below for initial
consideration, in order that this extended proceeding may at last
come to an end.
Compare, e.g., Permian Basin Area Rate
Cases, 390 U.S. at
390 U. S. 822,
n. 114;
Chicago & N.W. R. Co. v. Atchison, T. & S.F. R.
Co., 387 U. S. 326,
387 U. S.
355-356.
[
Footnote 36]
See 36 F.P.C. 962 (memorandum opinion and order
confirming Amerada order requiring refunds).
[
Footnote 37]
See Turnbull & Zoch Drilling Co., 36 F.P.C. 164,
166-167.
[
Footnote 38]
Cf. 1 Joint Appendix 159-162 (unreported opinions of
Commissioners Morgan and Ross concurring in the Commission's Feb.
5, 1963, denial of prospective refund conditions in
Amerada).
[
Footnote 39]
A contractual "take or pay" provision obligates a pipeline, over
a stated period, to take an average amount of gas or to pay for it.
A "make-up" period is also specified, during which the pipeline may
take the gas previously paid for without further payments. The
"prepayments" for gas not yet taken usually are capitalized and
included in the pipeline's rate base.
[
Footnote 40]
See, e.g., Transwestern Pipeline Co., 36 F.P.C. 176,
191-199;
Transcontinental Gas Pipe Line Corp., F.P.C.
Docket No. CP 65-181 (Phase II), Opinion No. 532, Nov. 6, 1967.
See also FPC v. Transcontinental Gas Pipe Line Corp.,
365 U. S. 1.
[
Footnote 41]
At present, "budget" authority permits a pipeline to expend on
gas purchasing facilities the lesser of $5,000,000 or 1.5% of its
existing plant investment, with the total cost of any single gas
purchase project not to exceed the lesser of $500,000 or 25% of the
total budget amount.
See 18 CFR § 157.7(b).
[
Footnote 42]
See id., § 157.9
et seq. Annual reports must
be made to the Commission describing the prior year's construction.
Id., § 157.7(b)(3).
[
Footnote 43]
See id., § 260.7.
[
Footnote 44]
See Federal Power Commission, Annual Reports,
1963-1967; Federal Power Commission, The Gas Supplies of Interstate
Natural Gas Pipeline Companies, Calendar Years 1963 and 1964
(February 1966); Federal Power Commission, The Gas Supplies of
Interstate Natural Gas Pipeline Companies, Calendar Years 1964 and
1965 (August 1967).
[
Footnote 45]
The producers assert that the end use aspect of the need issue
is not properly before us because the New York Public Service
Commission failed to raise the issue in its petition for rehearing
before the Commission, as required by § 19(b) of the Natural Gas
Act, 15 U.S.C. § 717r(b). Since the Court of Appeals did rule on
the end use question, and since we hold in favor of the producers
on all parts of the need issue, we think it appropriate to reach
the question without passing upon the producers' procedural
claim.
[
Footnote 46]
See California v. Lo-Vaca Gathering Co., 379 U.
S. 366,
379 U. S.
369-370;
Mississippi River Fuel Corp. v. FPC,
102 U.S.App.D.C. 238, 252 F.2d 619, 623-625.
[
Footnote 47]
The Commission elsewhere has conceded that the administrative
burden of such a procedure would not be unbearable.
See
Memorandum for the Federal Power Commission in
Austral Oil Co.
v FPC, No. 504, October Term, 1967, at 5-6.
[
Footnote 48]
See FPC v. Hunt, 376 U. S. 515,
376 U. S. 527;
United Gas Improvement Co. v. Callery Properties, Inc.,
382 U. S. 223,
382 U. S. 228,
n. 3.
[
Footnote 49]
See Order No. 279, 31 F.P.C. 750.
[
Footnote 50]
See Order No. 301, 34 F.P.C. 76.
[
Footnote 51]
See Order No. 334, 37 F.P.C. 110.
[
Footnote 52]
See 18 CFR § 1.3 (notice requirement for substantive
rulemaking proceedings).
[
Footnote 53]
The seaboard interests apparently achieved considerable success
in a pipeline certification proceeding which grew out of the
Sinclair proceeding now under review.
See Lone Star
Gas Co., 36 F.P.C. 497;
Lone Star Gas Co., F.P.C.
Docket No. CP 65-118, Order Vacating Certificates, Sept. 15,
1967.
[
Footnote 54]
Counsel for the Commission estimated on oral argument that 25%
of the gas involved in the
Sinclair and
Hawkins
proceedings could be attached at existing facilities.
[
Footnote 55]
See supra at
391 U. S. 48 and
n. 40.
[
Footnote 56]
The Commission has attempted to fulfill this duty by regulating
both the "take or pay" and end use aspects of the need question.
See supra at
391 U. S. 48,
391 U. S. 50,
391 U. S. 51.