Appellants, seven railroads, applied to the Interstate Commerce
Commission (IDD) for authority to provide direct service to the
Lake Calumet Harbor Port, which is being developed by the Chicago
Regional Port District as a major deep water port facility for
traffic via the St. Lawrence Seaway. The Port area is now served
directly by only Rock Island, which, along with the nearest rail
facility, Nickel Plate (later merged into the Norfolk &
Western), intervened in opposition to the proposed expansion of
rail service. The application sought approval of trackage extension
as well as an unexecuted agreement between appellants and the Port
District for operations within the Port area. After a full hearing,
the Hearing Examiner recommended approval of appellants' entire
project. The ICC adopted the recommendations, but ruled that t he
applicants should file supplemental applications covering Port area
operations as provided in the proposed lease with the Port
District. The supplemental applications covering the lease were
filed, an exclusive operating clause to which the ICC had objected
having been eliminated. The ICC, finding that the public
convenience and necessity required the additional services applied
for by appellants, approved the applications, as supplemented,
without a further hearing which the Rock Island and Nickel Plate
had requested, the ICC having concluded that the previous hearing
record was adequate to support the entire project. A second
supplemental application was later filed clarifying the rental
provision which, in the ICC's view, required no further hearing as
requested by those railroads. The Rock Island and Nickel Plate sued
to enjoin the ICC's orders, which a three-judge
Page 385 U. S. 58
District Court set aside as not supported by sufficient
evidence. The District Court also found that due process required
that Rock Island and Nickel Plate be granted a hearing on the
rental provisions. The court ordered a hearing on all the
issues.
Held:
1. The ICC's action granting appellant railroads' applications
to provide additional services was supported by "substantial
evidence" on the record viewed as a whole as to the Port's future
potential and the need for providing competitive rail service at
the outset of the Port's development. It was not the District
Court's function to substitute its own conclusions for those which
the ICC had fairly drawn from its findings. Pp.
385 U. S.
65-69.
2. During the proceedings before the Hearing Examiner and the
ICC, the operations of the appellants within the Port area were
fully considered as an integral part of their overall plan, and the
District Court had no basis for concluding that due process
required a new hearing on the issues. Pp. 70-75.
241 F. Supp. 974 reversed and remanded.
MR. JUSTICE CLARK delivered the opinion of the Court.
This is an appeal from the judgment of a three-judge District
Court, 241 F. Supp. 974, setting aside orders of the Interstate
Commerce Commission, 307 I.C.C. 493, 312 I.C.C. 277, 317 I.C.C.
502, which granted the
Page 385 U. S. 59
applications of seven railroads [
Footnote 1] to provide additional rail service to the Lake
Calumet Harbor Port near the southern limits of Chicago, Illinois.
The service was to be provided through the construction of a single
line of track into the Chicago Regional Port District for the joint
use of the seven railroads. At present, the port is served directly
by only one railroad, appellee Chicago, Rock Island and Pacific
Railroad Company (Rock Island). Appellee New York, Chicago and St.
Louis Railroad Company (Nickel Plate), [
Footnote 2] has facilities on the east side of Lake
Calumet which has been reserved for future commercial development,
but at present its facilities do not reach the port. The court,
with one judge dissenting, rejected, as not having "ample support"
in the record, the findings of the Commission that the public
convenience and necessity required the additional service applied
for by the seven roads. It further found, unanimously, that the
requirements of due process were violated by the Commission in its
refusal to give Rock Island and Nickel Plate a hearing before
approving a nonexclusive agreement, subsequently executed between
the applicant roads and the Port District, covering the use of the
latter's facilities. The court ordered a new hearing on all the
issues, one judge concluding that such hearing should be limited to
the subsequently executed nonexclusive use agreement. We noted
probable jurisdiction, 382 U.S. 913, and reverse the judgment.
Page 385 U. S. 60
I
BACKGROUND OF LAKE CALUMET HARBOR PORT
Lake Calumet Harbor Port is one of seven facilities within the
Port of Chicago available for the handling of waterborne freight.
It is a shallow lake approximately two miles in length and covers
approximately 1,250 acres. It is accessible by water from Lake
Michigan via the Calumet River into the heart of the Chicago
switching district, a distance of some six miles.
As early as 1880, one of the Pullman companies constructed
trackage that first brought rail service to Lake Calumet. Pullman
reserved some 300 to 500 acres for the development of a harbor, and
later donated some acreage to the United States for the development
of a turning basin. Comprehensive plans for dredging Lake Calumet
harbor and the filling of submerged lands were prepared in 1916 by
an engineer for the City of Chicago. In 1917, Pullman waived
riparian rights to some four miles of Lake Calumet shoreline to the
City of Chicago, and, in 1935, gave additional land to the United
States for the purpose of widening the Calumet River.
In 1947, the Illinois Central, an appellant here, attempted to
enter the port area. Pullman and two of the seven appellants here,
New York Central and the Belt Railway Company of Chicago, opposed
the application, which was addressed to the Illinois Commerce
Commission. In 1949, during the pendency of the proceeding, Rock
Island acquired the common stock and certain industrial property of
Pullman for $2,200,000. Rock Island then entered the proceedings in
opposition to Illinois Central. The application of the latter was
approved by the Illinois Commerce Commission, but the Circuit Court
of Cook County rejected it, and the Supreme Court of Illinois
affirmed in 1953.
Chicago, R.I.
Page 385 U. S. 61
& P.R. Co. v. Illinois Commerce Commission ex rel.
Illinois Central R. Co., 414 Ill. 134,
111 N.E.2d
136.
The Interstate Commerce Commission, in approving the acquisition
of Pullman by Rock Island -- over the objections of Illinois
Central and the Belt Railway Company, each of which also sought to
acquire Pullman or a portion of its trackage on the lake -- imposed
certain conditions on Rock Island designed to guarantee fair
practices, assure nondiscriminatory handling of the traffic of
other railroads to and from the lake, and guarantee the mutuality
of traffic and operating relationships theretofore existing between
Pullman and the other roads. Rock Island, however, continued to be
the only line providing direct service to the port.
The Chicago Regional Port District was created as a municipal
corporation by the State of Illinois in 1951. Its purpose was the
development of Lake Calumet into a major deep water port facility
for both domestic and import-export traffic via the St. Lawrence
Seaway. In 1954, the Port District declared by resolution that the
public's, as well as the port's, interest required that its
trackage be accessible to as many railroads as possible. In 1955,
the Port District acquired the lake and some adjoining property
from the City of Chicago, and began dredging the lake and
constructing port facilities at its southern end; it also built 14
miles of railroad yard "hold" tracks in the port, docks, two
6,500,000-bushel grain elevators, three transit sheds occupying
300,000 square feet of space, a back-up warehouse with 200,000
square feet of space, and streets. These facilities cost
$24,000,000 and were paid for by the sale of Port District revenue
bonds. By contract with the Port District, the Rock Island operates
over the trackage of the Port District and also serves the Calumet
Harbor Terminals, Inc., a private harbor facility. No other
railroads reach the port on their own tracks. The Nickel
Page 385 U. S. 62
Plate is the nearest rail facility. As previously noted, it has
trackage on the east side of the lake which has been reserved for
future development by the Port District. Any railroad wishing to
service the port must use the facilities of Rock Island.
II
THE APPLICATIONS BEFORE THE COMMISSION
On October 22, 1956, the appellants Illinois Central Railroad
Company and the Pennsylvania Railroad Company, requested authority
from the Commission under the provisions of 49 U.S.C. § 1(18) to
construct 1.431 miles of new track that would connect their lines
to the present trackage of an affiliate of Illinois Central that
passes near Lake Calumet's southwestern shore. Similar applications
were subsequently filed by the Chicago South Shore and South Bend
Railroad, the Belt Railway Company of Chicago, the Michigan Central
Railroad Company, the New York Central Railroad Company, and the
Indiana Harbor Belt Railroad Company. All of the applicants sought
to operate directly to and from the Lake Calumet port, rather than
use the facilities of the Rock Island. The latter, as well as the
Nickel Plate, requested and was given leave to intervene, as were
other parties. [
Footnote 3] The
Rock Island and Nickel Plate were the only objectors, the remaining
intervenors all supporting the applications.
The original applications of the seven railroads did not
specifically request authority from the Commission to operate over
the Port District's tracks. It appears that appellants were under
the impression that formal Commission authority was not necessary
because of the
Page 385 U. S. 63
fact that Rock Island was currently operating without it.
Nevertheless, the applications covered the entire plan of
operations proposed by appellants, including activity within the
Port District as well as an unexecuted agreement covering the
leasing of the Port District facilities which was attached to the
application as an exhibit. This lease was before the Hearing
Examiner during the 12-day joint hearing he conducted, and was the
subject of testimony and consideration. The appellants advised, and
the Hearing Examiner concluded, that the appellants sought approval
to operate within the Port District, as well as authority for the
track extension. Accordingly, the Hearing Examiner recommended to
the Commission that the entire project of the appellants be
approved.
On October 5, 1959, the Commission adopted the Hearing
Examiner's recommendations, but ruled that the applicants should
file supplemental applications covering their proposed operations
within the Port District as provided in the proposed lease with the
District. The Commission discussed the lease and indicated that it
was satisfactory. It did, however, feel that the exclusive right of
operation clause should be eliminated. The Commission also ruled
that Rock Island's service to Calumet Harbor Terminals, Inc., was
not to be disrupted, and that every industry located at Lake
Calumet Harbor was to have direct rail service not only from the
applicants, but the Rock Island and Nickel Plate, if they so
elected.
In April, 1960, the appellants, pursuant to the Commission's
requirement, filed supplemental applications for specific authority
to operate within the Port District. The proposed lease covered by
these applications eliminated the exclusionary provisions to which
the Commission had objected. Despite the request of Rock Island and
Nickel Plate for a hearing on the new lease, the Commission
Page 385 U. S. 64
found that the "technical deficiency" existing in appellants'
original applications had been corrected by the filing of their
supplemental applications; that the record of the previous hearing
was adequate to support approval of the entire proposal of the
appellants; and the applications, as supplemented, were
approved.
In June, 1961, however, the appellants and the Port District
found it necessary to amend their operating agreement, and
appellants filed a second supplemental application asking for
approval of the same. This agreement modified the one previously
approved by the Commission. The old agreement had provided for a 5%
annual rental for the use of the Port District's rail facilities
based upon the valuation of the latter, but not to exceed $2 per
car, loaded or empty, including locomotives. The new agreement
provided for a flat charge of $2 for each loaded freight car; it
also specifically eliminated industry-owned tracks within the Port
District from the agreement, and provided that it did not affect
the right of Rock Island to operate in the Port District, nor grant
any exclusive privilege to the appellants. The Commission, after
once again denying appellees' request for a hearing, approved this
final agreement on November 26, 1962. The Commission found that the
changes merely clarified the rights and responsibilities of the
parties. As to the rentals, it found that
"rentals generally may be considered reasonable where, as here,
the facts of record disclose that nonaffiliated parties, after
bargaining at arm's length, have entered into an agreement under
which increased service will be offered to the public, all parties
to the agreement will benefit financially, and the interveners"
ability to continue to serve the public will not be impaired.
[
Footnote 4]
Page 385 U. S. 65
III
PROCEEDINGS IN THE DISTRICT COURT
The Rock Island and Nickel Plate then filed this suit seeking to
enjoin the Commission's orders and the three-judge District Court
vacated the orders on the grounds we have stated.
The court found that it was faced with two basic problems: (1)
whether there was "substantial evidence" to support the order of
the Commission, and (2) whether the refusal of the Commission to
have a hearing on the lease agreement between the applicants and
the Port District denied Rock Island and Nickel Plate due process
of law.
With respect to the first problem, the court found "substantial
support" for some of the "important findings" of the Commission.
However, it found that the record did not "offer ample support" for
certain of its conclusions. These conclusions appeared to have been
drawn by the Commission from the prior findings which the court had
found to have "substantial support" in the record.
On the supplemental application for authority to operate within
the Port District, the court held there was insufficient evidence
to support the order of approval, that the rental under the final
contract was materially different from the provisions of the
original plan, and bound the Rock Island and Nickel Plate to
operate under the same condition without affording them the right
of a hearing. By a divided court, it ordered a complete rehearing
on all issues. We cannot agree with either the findings of the
District Court or with its disposition of the case.
IV
APPLICABLE STANDARD ON REVIEW
At the outset, the Commission and the appellant railroads
contend that the court did not apply the correct standards in
reviewing the Commission's action. As we
Page 385 U. S. 66
have noted, the court did reject certain "conclusions" of the
Commission, as above indicated, with respect to the public
convenience and necessity for additional rail service to Lake
Calumet port on the ground that they did not have "ample support"
in the record. The test on judicial review is, of course, whether
the action of the Commission is supported by "substantial evidence"
on the record viewed as a whole, 5 U.S.C. § 1009(e)(5). Substantial
evidence is
"enough to justify, if the trial were to a jury, a refusal to
direct a verdict when the conclusion sought to be drawn from it is
one of fact for the jury."
Labor Board v. Columbian Enameling & Stamping Co.,
306 U. S. 292,
306 U. S. 300
(1939). A careful reading of the opinion leads us to conclude that
the court was applying the test of substantiality. Indeed, at four
separate places in the opinion, it uses the term "substantial
evidence" as being the necessary requirement. As unfortunate as it
is that the "ample support" language crept into the decision, we do
not believe that the court was creating a "novel formulation," but
rather inadvertently used the "ample support" terminology merely to
meet the same language in the dissent referring to the conclusions
of the Commission.
We have concluded that the court erred in setting aside the
conclusions of the Commission. The Act authorizes the issuance of
certificates such as the ones sought here when the Commission finds
that the future public convenience and necessity will require
additional railroad service. 49 U.S.C. § 1(18). This Court has
repeatedly held that, if a railroad, voluntarily proposing the
extension of its lines, can show that its proposal
"either presently or in the reasonably near future will be
self-sustaining, or so nearly so as not unduly to burden interstate
commerce, the Commission may issue a certificate authorizing the
proposed line,"
Interstate Commerce Commission
v. Oregon-Wash. R. & Nav. Co.,
Page 385 U. S. 67
288 U. S. 14,
288 U. S. 37
(1933). The Commission, however,
"must be convinced that the proposed venture will not drain the
railroad's resources and disable it from performing those duties of
public service under which it then rested, with consequent
detriment to the public in the matter of service and rates."
Ibid. Also see Texas & P. R. Co. v. Gulf, C.
& S. F. R. Co., 270 U. S. 266,
270 U. S. 277
(1926);
Chesapeake & O. Ry. Co. v. United States,
283 U. S. 35,
283 U. S. 42
(1931). Rock Island and Nickel Plate contend that the "evidence [of
appellants] adduced before the Commission was so totally devoid of
factual possibility as to be no evidence at all." As we read it,
the evidence as to the future possibilities of the port was
somewhat conflicting. The Commission, in keeping with its duty,
resolved this conflict. Indeed, the findings of the Commission,
which were upheld by the District Court, completely refute the Rock
Island and Nickel Plate claims. Among the findings approved by the
court [
Footnote 5] are the
following: the port was "the major deepwater port facility of the
port of Chicago," with "unparalleled access" to barge, rail, lake
steamer, and motor transportation and "complete access to ocean
transportation" in the immediate future, with 71,490,510 tons of
water-borne traffic in 1955 and with "material increases" [
Footnote 6] in tonnages predicted for
the future from
Page 385 U. S. 68
among an estimated 600 to 900 vessels coming to the Chicago port
each season, that "will necessitate a substantially broadened
railroad service into and out of the Lake Calumet port";
appellants' combined yard capacity was 61,601 cars, more than 12
times that presently available at the port; appellants' routing
would be "more direct," entail less handling, expedite shipments,
and be less expensive than the present operation of Rock Island;
and, finally, it was
"imperative . . . that, at the very beginning of this new era of
development, a plan and system for handling the transportation
needs of the port be established which will assure the type of
service that is expected and will provide for steady progress and
expansion."
We believe that these findings, in the light of others not
overturned by the District Court, are sufficient to sustain the
Commission's action in issuing the certificates.
Moreover, we believe that the District Court erred in striking
down the conclusions of the Commission. These conclusions [
Footnote 7] included: consideration of
the whole record warranted the finding that the applications should
be granted; granting them would result in greater rail competition,
better service, greater car supply, and lower rates for the
industries served by the port; appellants would be "on a par" with
the Rock Island in solicitation of grain traffic, and, by having
control of their cars, they could return empties in a fast shuttle
service to country elevators without interchange with Rock Island;
the time has come when additional freight service is required for
the future development of the Port District; better service can be
given through elimination of delays, by single-line hauls or more
direct hauls; a single trunkline railroad
Page 385 U. S. 69
service would be detrimental and a hindrance to the development
of the harbor, and, although the port is served by some 100 common
carrier trucklines, the Rock Island is the only railroad presently
serving the port; the future convenience and necessity must be
given "a higher value" than the present convenience and necessity;
the proposed construction, either presently or in the reasonably
near future, is necessary to meet a public need, and will be
reasonably profitable; and, finally, considering the expansion
program at the port and the increased rail traffic to be made
available, the Commission is "of the opinion that the additional
service . . . is warranted." As we have said, these conclusions
were largely based upon previous Commission findings which the
District Court approved. The Commission's function is to draw such
reasonable conclusions from its findings as in its discretion are
appropriate. As we said in
Consolo v. Federal Maritime
Comm'n, 383 U. S. 607,
383 U. S. 620
(1966),
"the possibility of drawing two inconsistent conclusions from
the evidence does not prevent an administrative agency's finding
from being supported by substantial evidence."
It is not for the court to strike down conclusions that are
reasonably drawn from the evidence and findings in the case. Its
duty is to determine whether the evidence supporting the
Commission's findings is substantial,
Universal Camera Corp. v.
Labor Board, 340 U. S. 474
(1951). Having found that there was substantial support in the
record for the Commission's findings as to the port's future
potential and the necessity of providing competitive rail service
at the outset of the port's development, it was not the District
Court's function to substitute its own conclusions for those which
the Commission had fairly drawn from such findings. Its agreement
with the controlling subsidiary findings required the District
Court to sustain the Commission's conclusions.
Page 385 U. S. 70
The court also erred, we believe, in ordering a new hearing on
the issues. It found that the Commission's order issuing a
certificate of public convenience and necessity to operate within
the Port District was not supported by sufficient evidence, and
violated due process in that a hearing was not afforded the
appellees thereon.
As we view the original applications of the appellants, they
proposed
"to extend their operations to serve the Lake Calumet Harbor
District near Chicago, in Cook County, Illinois . . . future
industries, elevators, warehouses, docks, and piers in the Calumet
Harbor Port area."
The prayer was that
"your Commission issue a certificate of public convenience and
necessity authorizing the construction and operation for which
authority is herein sought. [
Footnote 8]"
The proceeding came on for a hearing before the Hearing Examiner
on September 30, 1957, and counsel for the Rock Island stated for
the record that his understanding was
"the issue in this case is that all applications are for the
purpose of handling
import and export business only
to
and from the Port District Harbor of Chicago. . . ."
(Emphasis supplied.) And counsel for the appellants stated that
the plan was
"to handle interstate business to and from the area over which
the port has jurisdiction. We have no such limitation at all as to
import or export trade."
Likewise, the "Return to Questionnaire" executed by appellants
stated:
"The line proposed to be constructed and operated will receive
material revenue from freight traffic to be handled to and from
industries, elevators, warehouses, docks, and piers presently
operating in the Calumet Harbor Port area, in addition to those
facilities to be constructed with the
Page 385 U. S. 71
further development of the area. [
Footnote 9]"
To make it crystal clear, paragraph 10 of the same answer to the
questionnaire stated:
"The Lake Calumet Port District, which the proposed line will
serve is currently served by the Chicago, Rock Island and Pacific
Railroad Company by virtue of its acquisition of the Pullman
Railroad Company, through purchase of capital stock, and lease by
the former of the railroad property of the latter approved and
authorized by the Commission in Finance Docket No. 16252,
Pullman Railroad Company Control, decided November 17,
1949."
The other applications had similar allegations, and the other
appellants' questionnaire returns contained like statements.
Moreover, the answers filed on May 16, 1957, by Rock Island and
Pullman to the applications addressed themselves solely to the
proposition that
"applicant's extension of its line of railroad and operations
through trackage rights to serve territory [the Port District]
heretofore served exclusively and adequately by petitioners cannot
be supported by public convenience and necessity, could mean only a
duplication of rail service, and would create unsound and
uneconomic conditions in transportation."
As we read the record before the Hearing Examiner, the case was
tried on the theory that the applications included the proposed
operations within the Port District. During the presentation of
appellants' evidence, objection was made to the introduction of the
proposed lease between appellants and the Port District on the
ground that it was beyond the scope of the application. The Hearing
Examiner overruled the objection. The testimony of virtually all of
the appellants' witnesses was
Page 385 U. S. 72
directed to some phase of the operations of the Port District.
It should also be noted that the appellees sought to rebut this
testimony in voluminous detail. For example, 40 pages of the record
detail the testimony of Mr. R. C. Davidson, a witness for Rock
Island. His testimony is devoted to Rock Island's operation in the
United States, with specific reference to the Port District. It
compares Rock Island's operation in the Port District with that
proposed by the appellants, and answers in detail the statistics of
the appellants as to charges, rates, switching problems, etc.,
involved in operations within the Port District. Page after page of
prepared statistics on the costs, profits, etc., of the proposed
operation were included in the testimony, together with forecasts
as to the impact of the same, if permitted, on Rock Island's
operations. Another witness for Rock Island, Professor Marvin L.
Fair, testified for some 15 pages on the potential of the Port
District. His research was in great depth, and included comparisons
with other Great Lakes ports; estimated traffic of the Port
District, including iron ore, grain, and general cargo; physical
conditions of navigation at the port; the effect of tolls; the
capacity of the Welland Canal (in the St. Lawrence Seaway) and its
impact on the port; the efficiency of the port facilities;
established movement of exports and imports; the effect of
political, military, and economic conditions at home and abroad,
and the adequacy of Rock Island's service.
The record establishes beyond a doubt that the appellants were.
in fact. seeking Commission approval of the entire project. Their
offering of the unexecuted proposed contract into evidence is one
of many indications of this fact. The Hearing Examiner specifically
noted, at the time the contract was received in evidence, that its
approval by the Commission was necessary in order for the
appellants to serve the Port District as they proposed. It would
indeed have been a futile act for the appellants
Page 385 U. S. 73
to seek and attain approval to extend their lines to the Port
District, but not be able to enter it!
It is true that appellees objected to the introduction of the
proposed agreement because they felt, and rightly so, that the
application which the appellants had submitted was not technically
broad enough for the authority they sought. The Hearing Examiner
overruled them, and they were obliged to -- and did -- offer their
evidence on the matter. When the question came before the
Commission for decision, it ruled that the applications were
technically deficient, and permitted the parties to correct the
same through the filing of supplemental applications. At no time
did the Commission find that the proposal to operate within the
Port District had not been adequately explored and examined.
Rather, a careful reading of the Commission's entire opinion leads
us to the opposite conclusion. At every stage of the proceedings
before the Hearing Examiner and also before the Commission,
operations of the appellants within the Port District were
considered an integral part of the overall plan which they
submitted.
The ruling of the Commission that the supplemental applications
should be considered in "conjunction with the original application"
did not, in our view, deprive appellees of due process of law. When
appellees requested a full hearing on the supplemental
applications, the grounds they alleged were that they were
adequately serving the port; that they were prepared to spend
further sums of money in the construction of facilities to serve
it; that they were entitled to retain the traffic of the Port
District; that there was no adequate reason for extension of the
railroad lines of appellants into territory heretofore served
exclusively by appellees; and that the extension of the railroad
lines of appellants was not justified by public convenience and
necessity. As the Commission itself found,
"Examination of the record discloses
Page 385 U. S. 74
that these are the same arguments and contentions that were set
forth in protestants' original briefs, exceptions to the examiner's
proposed report, in their petitions for reconsideration, and in
their oral arguments."
Illinois Central R. Co. Construction and Trackage, 312
I.C.C. 277, 280.
The changes in the proposed lease agreement which the Commission
approved without a further hearing involved the removal of the
"exclusive right to operate within the Port" clause, which that
document had given the appellants, and the formula for determining
the annual rental to be charged by the Port District. As to the
former, it can hardly be maintained that this worked a hardship or
detriment upon the appellees. The removal of the clause, in fact,
made certain that appellees were not precluded from continuing
their present operations. As to the rental clause, it will be
remembered that the original proposed agreement provided for 5%
annual rental based on the value of the land and tracks, but not to
exceed $2 per car. This was changed in the first supplemental
application to a charge of not to exceed $2 per revenue car or
locomotive. The final contract merely provided for a charge of $2
for each revenue car, which was much more favorable to the
appellants than either of the former clauses. Moreover, the final
charge compared favorably to other per-car rates previously
approved by the Commission. In the light of these considerations,
as well as the fact that appellees were invited and refused to sit
in on the negotiation of the contract; had ample opportunity and
did present their evidence as to the reasonableness of the charge
for the use of Port District property; were, and are, in nowise
bound by the contract; and, finally, in view of the insignificance
of the changes in the final agreement compared with the former
ones, we are led to conclude that appellees were not entitled to
another hearing.
Page 385 U. S. 75
Appellees also insist that a new hearing be held so that
evidence of "present conditions" could be presented to the
Commission, rather than "speculation." It is true that this case
has been pending for 10 years, but this, rather than being a reason
for holding additional hearings, operates to the contrary. We have
concluded that the orders of the Commission were proper under the
circumstances. We have found substantial support for its actions.
Accordingly, it is our view that this matter be concluded.
The judgment is therefore reversed, and the case is remanded to
the District Court with directions to sustain the Commission's
orders.
It is so ordered.
* Together with No. 17,
Calumet Harbor Terminals, Inc., et
al. v. Norfolk & Western Railway Co et al, and No. 20,
United States et al. v. Norfolk & Western Railway Co. et
al., also on appeal from the same court.
[
Footnote 1]
Illinois Central Railroad Company; Pennsylvania Railroad
Company; Chicago South Shore and South Bend Railroad; Belt Railway
Company of Chicago; the New York Central Railroad Company; and the
Indiana Harbor Belt Railroad Company. The Michigan Central Railroad
Company sought additional trackage approval, but had not signed a
proposed lease with the Port District, as the other appellants
had.
[
Footnote 2]
The Nickel Plate has merged into the Norfolk and Western Railway
Company since this proceeding began.
[
Footnote 3]
Others included: the Secretary of Agriculture, the Port
District, the Chicago Board of Trade, the Chicago Association of
Commerce and Industry, and two private companies operating on the
lake, Calumet Harbor Terminals, Inc., and North Pier Terminal
Company.
[
Footnote 4]
317 I.C.C. 502, 505.
[
Footnote 5]
Norfolk & Western R. Co. v. United States, 241 F.
Supp. 974, 977.
[
Footnote 6]
The testimony was that rail traffic to and from the port in 1960
would be 27,000 carloads, which could easily increase to 76,500
carloads in 1962, 115,000 carloads in 1968, and anywhere from
250,000 to 350,000 carloads a year when both sides of the lake are
completed. There was also much testimony as to grain shipments. The
seven States of Indiana, Illinois, Iowa, Missouri, Kansas,
Nebraska, and Colorado in 1956 produced 43% of all the wheat and
51% of the corn grown in the United States. The existing disparity
in rates will divert much grain from Atlantic and Gulf ports for
movement via Chicago and the St. Lawrence Seaway. Service to the
port by one railroad does not appear adequate, since the railroads
serving the midwest grain-producing States terminate in Chicago and
have extensive switching and classification yards which could be
utilized.
[
Footnote 7]
241 F. Supp. 974, 979.
[
Footnote 8]
Application of Illinois Central, Pennsylvania, and Chicago South
Shore and South Bend railroads filed October 19, 1956, with the
Interstate Commerce Commission.
[
Footnote 9]
Return of Illinois Central, Pennsylvania, and the Chicago South
Shore and South Bend, R. 17.
MR. JUSTICE BLACK, dissenting.
The District Court set aside an order of the Interstate Commerce
Commission on the ground that the evidence failed to support its
findings of fact. I dissent from the Court's reversal of that
holding. In
Universal Camera Corp. v. Labor Board,
340 U. S. 474,
340 U. S. 488,
it was said that
"Congress has merely made it clear that a reviewing court is not
barred from setting aside a Board decision when it cannot
conscientiously find that the evidence supporting that decision is
substantial when viewed in the light that the record in its
entirety furnishes, including the body of evidence opposed to the
Board's view."
In the case here, the District Court found that it could not
conscientiously support the Commission's findings, and I would
affirm its judgment, adhering to the principles so firmly announced
in
Universal Camera, supra.