Respondent was the successful bidder on an invitation for bids
to construct military housing. It received a letter of
acceptability which provided that, unless the contract were closed
in a specified time, the Air Force could cancel the bid, which
decision, under a disputes clause, was final unless appealed to the
Board of Contract Appeals within 30 days. A disagreement arose, the
contract was not closed, and the bid was cancelled. Respondent
appealed to the Board of Contract Appeals, which dismissed the
appeal as untimely without considering the merits of the case.
Respondent then filed suit in the Court of Claims to recover its
bid deposit and for damages. That court held that the appeal to the
Board was timely, and that the Board erred in not reaching the
merits. The court then remanded the case to its trial commissioner
to make a record and consider the merits. The Government challenged
this procedure.
Held: The Court of Claims should have returned the
dispute to the Board for consideration of the merits, in accordance
with the contractual agreement of the parties.
United State v.
Carlo Bianchi & Co., 373 U. S. 709,
373 U. S.
717-718. Pp.
384 U. S.
428-433.
170 Ct.Cl. 688, 345 F.2d 808, reversed.
MR. JUSTICE WHITE delivered the opinion of the Court.
In
United States v. Carlo Bianchi & Co.,
373 U. S. 709, we
held that, aside from questions of fraud, a reviewing
Page 384 U. S. 425
courts is limited to the administrative record made below in
determining the finality to be given departmental decisions and
findings made by a Board of Contract Appeals pursuant to a standard
government disputes clause. In the present case, we are called upon
to decide whether the reviewing court or the Board of Contract
Appeals should make the original record on an issue which the Board
did not resolve because it erroneously dismissed the appeal before
it as untimely.
The question is framed by the following facts. The Department of
the Air Force issued an invitation for bids for the construction of
a military housing project at Topsham Air Force Station, Maine. The
invitation included a tentative minimum wage schedule which the
contractor would have to meet. It also advised that the wage
schedule would be finally redetermined by the Secretary of Labor
not more than 90 days prior to the commencement of construction,
and that the Federal Housing Commissioner would then adjust the
contract price to reflect any changes made in the wage schedules.
[
Footnote 1] In addition, the
successful bidder was required to complete certain preparatory acts
in order to close the contract and to post a $25,000 deposit to
ensure the closing of the contract. Respondent, Anthony Grace &
Sons, Inc., was the low acceptable bidder, and a letter of
acceptability was sent to it. That letter reminded
Page 384 U. S. 426
respondent that failure to close the contract within a specified
number of days was sufficient justification to warrant the
Department of the Air Force in cancelling the bid and letter of
acceptability, in retaining the deposit for liquidated damages and
in determining additional liability for actual damages. A disputes
clause in the letter of acceptability made such decision by the
Department of the Air Force final unless, within 30 days from the
receipt of the decision, respondent appealed to the Armed Services
Board of Contract. Appeals, whose decision would be final and
conclusive unless fraudulent or capricious or arbitrary, or so
grossly erroneous as necessarily to imply bad faith, or not
supported by substantial evidence. [
Footnote 2] After receiving subsequent wage schedules from
the Secretary of Labor, respondent concluded that certain work was
being placed in higher wage categories than was provided in the
specifications which accompanied the bid invitation. On the basis
of this alleged deviation from the original specifications,
respondent asked
Page 384 U. S. 427
first the Housing Commissioner and then the Department of the
Air Force to raise the contract price. These requests were refused,
and respondent then notified the Air Force that it would be unable
to complete the closing until this matter was cleared up. In the
ensuing exchange of letters, the contracting officer informed
respondent that its bid and the letter of acceptability were being
canceled and its deposit was being retained. Pursuant to the
disputes clause, respondent appealed this decision to the Armed
Services Board of Contract Appeals, which dismissed the appeal as
out of time without considering the merits of the case. Respondent
then sued in the Court of Claims to recover its deposit and for
damages resulting from the Government's alleged wrongful
cancellation. That court concluded that the appeal to the Board was
timely, and that the Board had erred in not reaching the merits of
the case. With Judges Davis and Laramore dissenting, the court then
decided to remand the case to its own trial commissioner, rather
than to the Board of Contract Appeals, to make a record and
consider the case on its merits. The Government asked us to grant
certiorari to consider whether this was in violation of the
principles announced in the Wunderlich Act [
Footnote 3] and
United States v. Carlo Bianchi
& Co., supra. We granted certiorari, 382 U.S. 901, and we
now reverse.
Page 384 U. S. 428
This question was anticipated in
Bianchi, supra, where
we considered what a reviewing court should do when the
administrative record is defective or inadequate, or reveals the
commission of a prejudicial error. Two suggestions were given:
"
First, there would undoubtedly be situations in which
the court would be warranted, on the basis of the administrative
record, in granting judgment for the contractor without the need
for further administrative action.
Second, in situations
where the court believed that the existing record did not warrant
such a course, but that the departmental determination could not be
sustained under the standards laid down by Congress, we see no
reason why the court could not stay its own proceedings pending
some further action before the agency involved.
Cf.
Pennsylvania R. Co. v. United States, 363 U. S.
202. Such a stay would certainly be justified where the
department had failed to make adequate provision for a record that
could be subjected to judicial scrutiny, for it was clearly part of
the legislative purpose to achieve uniformity in this respect."
373 U.S.
373 U. S. 709,
717-718. The policy reflected in this language, which requires
utilization of the administrative procedures contractually
bargained for, was clearly intended by Congress,
see
H.R.Rep.No.1380, 83d Cong., 2d Sess. (1954);
United States v.
Carlo Bianchi & Co., supra, at
373 U. S.
715-718, and it has been consistently reflected in a
long line of decisions by this Court.
See United States v.
Wunderlich, 342 U. S. 98;
Page 384 U. S. 429
United States v. Moorman, 338 U.
S. 457;
United States v. Joseph A. Holpuch Co.,
328 U. S. 234;
United States v. Blair, 321 U. S. 730;
United States v. Callahan Walker Construction Co.,
317 U. S. 56;
Kihlberg v. United States, 97 U. S.
398. Preeminently, this policy is grounded on a respect
for the parties' rights to contract and to provide for their own
remedies.
See United States v. Utah Construction & Mining
Co., 384 U. S. 394;
United States v. Moorman, supra, at
338 U. S.
461-462. But, beyond that, there is also a belief that
resort to administrative procedures is an expeditious way to settle
disputes, conducive to speed and economy. [
Footnote 4]
United States v. Blair, supra, at
321 U. S. 735.
Such procedures also facilitate a department's supervisory control
over contracting officers, and perhaps enhance the possibility of
harmonious agreement.
Ibid. Further, reliance upon a few
expert agencies to make the records and initially to pass on the
merits of the claims properly presented to them will lead to
greater uniformity in the important business of fairly interpreting
government contracts.
There can be no doubt that the dispute here over the decision by
the Department of the Air Force to cancel respondent's commitments
under the bid and letter of acceptability and to retain the deposit
is one which the parties contractually provided should be heard and
decided by the administrative process. Barring some compelling
policy reason to disregard this provision, the contractor should be
held to its contractual agreement even at this stage in the
litigation.
It is true that this Court has said on several occasions that
the parties will not be required to exhaust the administrative
Page 384 U. S. 430
procedure if it is shown by clear evidence that such procedure
is "inadequate or unavailable."
United States v. Joseph A.
Holpuch Co., supra, at
328 U. S. 240;
United States v. Blair, supra, at
321 U. S.
736-737. It may be that the contracting officer,
H.
B. Zachry Co. v. United States, 344 F.2d 352, 170 Ct.Cl. 115,
or the Board of Contract Appeals,
Southeastern Oil Florida,
Inc. v. United States, 115 F. Supp. 198,
127
Ct.Cl. 480, so clearly reveals an unwillingness to act and to
comply with the administrative procedures in the contract that the
contractor or supplier is justified in concluding that those
procedures have thereby become "unavailable." Similarly, there may
be occasions when the lack of authority of either the contracting
officer or the administrative appeals board is so apparent that the
contractor or supplier may justifiably conclude that further
administrative relief is "unavailable." [
Footnote 5] But these circumstances are clearly the
exceptions, rather than the rule, and the inadequacy or
unavailability of administrative relief must clearly appear before
a party is permitted to circumvent his own contractual agreement.
When the Board fails to reach and decide an issue because it
disposes of the appeal on another ground -- here, the untimeliness
of the appeal -- which the Court of Claims later rejects, there is
no sound reason to presume that the Board will not promptly and
fairly deal with the merits of the undecided issue if it is given
the chance to do so. [
Footnote
6]
Page 384 U. S. 431
The Court of Claims in this case attempted to justify bypassing
the Board of Contract Appeals because it felt the dispute could be
resolved more speedily if its Trial Commissioner made the record
and initially passed on the merits. The dissenting judges question
the factual accuracy of the premises. [
Footnote 7] Even if the premises were sound, however, this
argument falls substantially short of establishing that the
administrative route is inadequate or unavailable. [
Footnote 8]
Nor is it persuasive to say that the administrative remedy is
inadequate in this case because the Board of Contract Appeals
considers itself unable to review wage determinations by the
Secretary of Labor or the corresponding bid adjustments by the
Federal Housing Commissioner. The necessity of determining the
validity
Page 384 U. S. 432
of these determinations and adjustments is speculative, at best.
The issue involved here is whether the Department of the Air Force
was justified in cancelling respondent's commitments, retaining its
deposit, and itemizing certain damages. This raises questions
concerning the propriety of respondent's failure to press forward
to close the contract regardless of an outstanding wage dispute.
And this, in turn, requires an analysis of the original bid
invitation and accompanying specifications, the custom and usage of
the trade, and the subsequent conduct of both parties to this
dispute. Obviously there are factual issues to be resolved, and
that task is initially for the Board, not the Court. [
Footnote 9]
Another argument advanced by the Court of Claims is that it
lacks authority to remand the case, and the Board may refuse to
consider it again. At this stage of the proceedings, this fear may
be dismissed as a hypothetical one. There will be time enough
later, if this fear ever materializes, to consider whether the
reviewing court would then be authorized to make its own record. In
this regard, it should be noted that, in
Bianchi, supra,
we suggested one way of dealing with this problem:
"And in any case in which the department failed to remedy the
particular substantive or procedural defect or inadequacy, the
sanction of judgment for
Page 384 U. S. 433
the contractor would always be available to the Court."
373 U. S. 373 U.S.
709,
373 U. S. 718.
See also Interstate Commerce Comm'n v. Atlantic Coast Line R.
Co., 383 U. S. 576,
383 U. S. 601.
[
Footnote 10]
Reversed.
[
Footnote 1]
See the Davis-Bacon Act, 46 Stat. 1494, as amended, 40
U.S.C. § 276a (1964 ed.). No provision was made in the bid
invitation or letter of acceptability for review of the
determinations of the Secretary of Labor or the Housing
Commissioner. The Armed Services Board of Contract Appeals has held
that, in these circumstances, it is without jurisdiction to review
such determinations.
Len Co. & Associates, 1962 B.C.A.
� 3498, 17,854 (ASBCA). This Court has indicated that, as to the
wage standards set by the Secretary of Labor, there is no judicial
review.
United States v. Binghamton Construction Co.,
347 U. S. 171,
347 U. S.
177.
[
Footnote 2]
This clause, which varies somewhat from the standard disputes
clause, reads as follows:
"Failure to perform all obligations prior to the time prescribed
for closing will be just cause for cancelling all commitments
undertaken with you in connection with the housing project and for
the recovery under your bid security of liquidated damages in the
sum of $25,000, together with actual damages to the Department,
such actual damages to be itemized and determined by the
Contracting Officer, whose decision will be reduced to writing and
furnished to you by mail or otherwise. Such decision shall be final
and conclusive unless, within 30 days from the receipt thereof, you
appeal in writing to the head of the Department or his duly
authorized representative, and his decision shall, unless
determined by a court of competent jurisdiction to have been
fraudulent or capricious or arbitrary, or so grossly erroneous as
necessarily to imply bad faith, or not supported by substantial
evidence, be final and conclusive. In connection with any appeal
under this paragraph, you will be afforded an opportunity to be
heard and to offer evidence in support of your appeal."
[
Footnote 3]
The Wunderlich Act, 68 Stat. 81, 41 U.S.C. §§ 321�322,
provides:
"That no provision of any contract entered into by the United
States, relating to the finality or conclusiveness of any decision
of the head of any department or agency or his duly authorized
representative or board in a dispute involving a question arising
under such contract, shall be pleaded in any suit now filed or to
be filed as limiting judicial review of any such decision to cases
where fraud by such official or his said representative or board is
alleged:
Provided, however, that any such decision shall
be final and conclusive unless the same is fradulent [
sic]
or capricious or arbitrary or so grossly erroneous as necessarily
to imply bad faith, or is not supported by substantial
evidence."
"SEC. 2. No Government contract shall contain a provision making
final on a question of law the decision of any administrative
official, representative, or board."
[
Footnote 4]
See Hearing before the Subcommittee for Special
Investigations of the House Committee on Armed Services on H.R.Res.
No. 67, Inquiry Into the Administration and Operation of the Armed
Services Board of Contract Appeals, 85th Cong., 2d Sess., 794-795
(1958).
[
Footnote 5]
See United States v. Utah Construction & Mining Co.,
supra; C. J. Langenfelder & Son, Inc. v. United States,
341 F.2d 600, 169 Ct.Cl. 465.
[
Footnote 6]
We see no reason, in this regard, to distinguish between
theories of liability not considered below and the issue of
damages, which may not initially have been considered if the Board
found no liability. If, because of the disposition of the case on
appeal, any of these issues becomes important, the Board should be
given an opportunity to consider them first. The rule we announce
necessarily disapproves of such cases as
Stein Bros. Mfg. Co.
v. United States, 337 F.2d 861, 162 Ct.Cl. 802, and
WPC
Enterprises, Inc. v. United States, 323 F.2d 874, 163 Ct.Cl.
1, in which the Court of Claims retained the issue of damages after
it reversed the Board's finding of no liability.
[
Footnote 7]
Brief for the Government, p. 20, n. 14, indicates that it may
actually take longer for the Court for Claims to dispose of a case
than it would for the boards.
[
Footnote 8]
To the extent that the Court of Claims may have been worried
about duplicity of evidentiary hearings,
see United States v.
Carlo Bianchi, supra, at
373 U. S. 717,
it partially answered itself in
Morrison-Knudsen Co. v. United
States, 345 F.2d 833, 170 Ct.Cl. 757, decided the same day.
There, the Court of Claims held that, when the Board of Contract
Appeals has jurisdiction to consider a certain issue and to award
full relief and it makes a record on the factual matters underlying
that issue, judicial review of those factual findings, for whatever
purposes, shall be limited to the record made by the Board. We
hold, in
United States v. Utah Construction & Mining Co.,
supra, that factual findings made by a board pursuant to a
claim properly before it, if they otherwise satisfy the standards
of the Wunderlich Act, shall not be relitigated even in a court
action for relief that is not available under the contract. Hence,
there will be only one evidentiary hearing.
[
Footnote 9]
The Board below observed,
"The parties are in complete agreement that it was and is their
mutual interpretation that in the event a timely appeal is taken
thereunder the 'disputes paragraph' of the Letter of Acceptability
confers jurisdiction on the Board to review a decision relating to
cancellation of commitments, withholding of bid security, and
itemization and determination of actual damages."
Both the Court of Claims and the Trial Commissioner observed
that there were "unresolved issues of fact" underlying the issues
in this case. 345 F.2d 808, 810, 170 Ct.Cl. 688, 691.
[
Footnote 10]
There is analogy for the rule we announce today in other areas
of administrative law.
See, e.g., Securities and Exchange Comm.
v. Chenery Corp., 318 U. S. 80, and
Connecticut Light & Power Co. v. Federal Power Comm.,
324 U. S. 515,
where this Court ordered the cases remanded to the agencies for
further findings and consideration rather than itself curing the
inadequacies of the records below.
See generally Davis,
Administrative Law Treatise, §§ 16.01, 20.06 (1958). The same
general rule also applies in the area of labor arbitration. In
United Steelworkers of America v. Enterprise Wheel & Car
Corp., 363 U. S. 593, the
arbitrator had failed to determine the amount of back pay to which
reinstated employees would be entitled and this Court ordered the
matter remanded to the arbitrator for resolution of this issue. The
Court observed there that it was the arbitrator's determination
"which was bargained for." Much the same thing can be said here,
although of course the findings and conclusions of the Board of
Contract Appeals do not have the same finality on review.
See
also International Association of Machinists v. Crown Cork and Seal
Co., 300 F.2d 127.