Under the proviso to Article 9 of the Standard Form of
Government Construction Contract, which provides that the
contractor shall not be charged with liquidated damages because of
delays due to unforeseeable causes, including floods, the remission
of liquidated damages is not warranted where the "flood" was not
unforeseeable, but was due to conditions normally to be expected.
P.
318 U. S.
122.
97 Ct.Cls. 689 reversed.
Certiorari, 317 U.S. 615, to review a judgment against the
United States in a suit upon a contract.
MR. JUSTICE MURPHY delivered the opinion of the Court.
We are asked to decide whether the proviso to Article 9 of the
Standard Form of Government Construction Contract [
Footnote 1] which provides that a contractor
shall not be
Page 318 U. S. 121
charged with liquidated damages because of delays due to
unforeseeable causes beyond the control and without the fault of
the contractor, including floods, requires the remission of
liquidated damages for delay caused by high water found to have
been customary and foreseeable by the contracting officer.
Respondent brought this suit in the Court of Claims to recover
the sum of $3,900 which was deducted from the contract price as
liquidated damages for delay in the completion of a contract for
the construction of levees on the Mississippi River. The contract
was not completed until 290 days after the date set, and liquidated
damages in the amount of $5,800 (figured at the contract rate of
$20 for each day of delay) were originally assessed. Respondent
protested, and, upon consideration, the contracting officer found
that respondent had been delayed a total of 278 days by high water,
183 days of which were due to conditions normally to be expected
and 95 of which were unforeseeable. He recommended that liquidated
damages in the amount of $1,900 (representing 95 days of
unforeseeable delay at $20 per day) be remitted, and that the
balance of $3,900 be retained. Payment was made on this basis.
[
Footnote 2]
Page 318 U. S. 122
The Court of Claims held that liquidated damages should not have
been assessed for any of the 278 days of delay caused by high
water, because the high water was a "flood," and, under the
proviso, all floods were unforeseeable
per se.
Accordingly, it gave judgment in respondent's favor in the sum of
$3,660. [
Footnote 3] No
findings were made as to whether any of the high water was in fact
foreseeable. We granted certiorari because the case presents an
important question in the interpretation of the Standard Form of
Government Construction Contract.
We believe that the construction adopted below is contrary to
the purpose and sense of the proviso, and may easily produce
unreasonable results. The purpose of the proviso is to remove
uncertainty and needless litigation by defining with some
particularity the otherwise hazy area of unforeseeable events which
might excuse nonperformance within the contract period. Thus,
contractors know they are not to be penalized for unexpected
impediments to prompt performance, and, since their bids can be
based on foreseeable and probable, rather than possible,
hindrances, the Government secures the benefit of lower bids and an
enlarged selection of bidders.
To avoid a narrow construction of the term "unforeseeable
causes" limiting it perhaps to acts of God, the proviso sets forth
some illustrations of unforeseeable interferences. These it
describes as
"including, but not restricted to, acts of God, or of the public
enemy, acts of the Government, fires, floods, epidemics, quarantine
restrictions, strikes, freight embargoes, and unusually severe
weather, or delays of subcontractors due to such causes."
The purpose of the proviso to protect the contractor against the
unexpected, and its grammatical sense both
Page 318 U. S. 123
militate against holding that the listed events are always to be
regarded as unforeseeable, no matter what the attendant
circumstances are. Rather, the adjective "unforeseeable" must
modify each event set out in the "including" phrase. Otherwise,
absurd results are produced, as was well pointed out by Judge
Madden, dissenting below:
". . . Not every fire or quarantine or strike or freight embargo
should be an excuse for delay under the proviso. The contract might
be one to excavate for a building in an area where a coal mine had
been on fire for years, well known to everybody, including the
contractor, and where a large element of the contract price was
attributable to this known difficulty. A quarantine or freight
embargo may have been in effect for many years as a permanent
policy of the controlling government. A strike may be an old and
chronic one whose settlement within an early period is not
expected. In any of these situations, there could be no possible
reason why the contractor, who, of course, anticipated these
obstacles in his estimate of time and cost, should have his time
extended because of them."
"The same is true of high water or 'floods.' The normally
expected high water in a stream over the course of a year, being
foreseeable, is not an 'unforeseeable' cause of delay. Here,
plaintiff's vice-president testified that, in making its bid,
plaintiff took into consideration the fact that there would be high
water and that, when there was, work on the levee would stop. . . .
[
Footnote 4]"
A logical application of the decision below would even excuse
delays from the causes listed although they were within the
control, or caused by the fault, of the contractor, and this
despite the proviso's requirement that the events be "beyond the
control and without the fault or negligence
Page 318 U. S. 124
of the contractor." If fire is always an excuse, a contractor is
free to use inflammable materials in a tinder-box factory and
escape any damages for delay due to a resulting fire. Any
contractor could shut his eyes to the extremest probability that
any of the listed events might occur, submit a low bid, and then
take his own good time to finish the work free of the compulsion of
mounting damages, thus making the time fixed for completion
practically meaningless and depriving the Government of all
recompense for the delay.
We intimate no opinion on whether the high water amounted to a
"flood" within the meaning of the proviso. Whether high water or
flood, the sense of the proviso requires it to be unforeseeable
before remission of liquidated damages for delay is warranted. The
contracting officer found that 183 days of delay caused by high
water were due to conditions normally to be expected. No appeal
appears to have been taken from his decision to the head of the
department, and it is not clear whether his findings were
communicated to respondent so that it might have appealed. The
Court of Claims did not determine whether respondent was concluded
by the findings of the contracting officer under the second proviso
to Article 9, [
Footnote 5] and,
not having made this threshold determination, of course, made no
findings itself as to foreseeability. We think these matters should
be determined in the first instance by the Court of Claims.
Accordingly,
Page 318 U. S. 125
the judgment is reversed and the cause remanded with
instructions to determine whether respondent is concluded by the
findings of the contracting officer, and, if not, for a finding by
the court whether the 183 days of high water or any part of that
time were in fact foreseeable.
Reversed.
[
Footnote 1]
In general, Article 9 gives the Government the option of
terminating the contractor's right to proceed, or of allowing him
to proceed subject to liquidated damages if he fails to proceed
with diligence or to complete the work in time. The full text of
the proviso is:
". . .
Provided, That the right of the contractor to
proceed shall not be terminated or the contractor charged with
liquidated damages because of any delays in the completion of the
work due to unforeseeable causes beyond the control and without the
fault or negligence of the contractor, including, but not
restricted to, acts of God, or of the public enemy, acts of the
Government, fires, floods, epidemics, quarantine restrictions,
strikes, freight embargoes, and unusually severe weather or delays
of subcontractors due to such causes. . . ."
[
Footnote 2]
The contracting officer found that the remaining delay of 12
days (the difference between the total delay of 290 days and the
278 days due to high water) was not excusable, as claimed by
respondent, on account of the Government's failure to secure a
necessary right of way, or on account of the requirement by the
contracting officer that respondent build a tie-in levee. On these
points, the court below sustained the conclusions of the
contracting officer. Respondent has not appealed, and this phase of
the case is not before us.
[
Footnote 3]
97 Ct.Cls. 689.
[
Footnote 4]
97 Ct.Cls. 701, 702.
[
Footnote 5]
The second proviso to Article 9 immediately follows the
unforeseeability proviso, and states:
"
Provided further, That the contractor shall, within
ten days from the beginning of any such delay, notify the
contracting officer in writing of the causes of delay, who shall
ascertain the facts and the extent of the delay, and his findings
of facts thereon shall be final and conclusive on the parties
thereto, subject only to appeal, within thirty days, by the
contractor to the head of the department concerned, whose decision
on such appeal as to the facts of delay shall be final and
conclusive on the parties hereto."