Under a Government contract for the installation of equipment in
a building, the contractor agreed to complete the work within the
time allowed under another contract, with another contractor, for
the construction of the building. The building contract provided
for completion within 250 days after notice, but permitted changes
in the specifications to be made in the event of discovery of
subsurface conditions materially different from those shown in the
drawings or indicated in the specifications. Shortly after notice
to begin had been given, work under the building contract was
suspended pending the making of such a permitted change.
Held:
1. A delay resulting from such a permitted change did not
constitute a breach by the Government of the equipment contract. P.
317 U. S.
64.
The Government was not bound to have the building ready for the
work of the equipment contractor at a particular time.
2. The equipment contractor was not entitled to recover
consequential damages for delay thus resulting; for such a delay,
extension of the time for completion was an "equitable adjustment"
under the contract. P.
317 U. S.
66.
95 Ct.Cls. 84, reversed.
Page 317 U. S. 62
MR. JUSTICE BLACK delivered the opinion of the Court.
We granted certiorari to review a judgment against the United
States by the Court of Claims, 95 Ct.Cls. 84, interpreting a widely
used standard form construction contract in a manner alleged to be
in conflict with this Court's interpretation of an analogous
contract in
Crook Co., Inc. v. United States, 270 U. S.
4.
Respondent agreed to install plumbing, heating, and electrical
equipment in a Veterans' Home to be erected at Togus, Maine, while
another contractor was to do the general work of preparing the site
and constructing the building. Respondent agreed, for a stipulated
price, to begin work upon notice to proceed and to finish by the
time the work had been completed by the principal contractor. If
respondent failed to complete the work within the time thus set,
the government was entitled to terminate the contract or to require
the payment of liquidated damages. The length of time allowed the
principal contractor under his contract, subject to certain
qualifications discussed below, was 250 days, and it was into this
schedule that respondent was to coordinate his own activity.
Page 317 U. S. 63
The government gave notice to the general contractor to begin
work on May 9, 1932. On May 12, respondent was notified to begin,
and, early in June, its superintendent arrived in Maine with tools
and equipment. Upon his arrival, he found that the general
contractor had been stopped by the government because of the
unexpected discovery of an unsuitable soil condition. It became
necessary to change the site of the building and to alter the
specifications, and, because of the delay attendant upon preparing
a new foundation, respondent was unable to begin work until
October. As a consequence, overhead expenses accumulated during the
period of delay, and much of the work which respondent's employees
otherwise would have done either during warm weather or after the
building was enclosed was done outside in cold weather.
Because of the delay, and pursuant to the adjustment clauses of
the contract, the government extended the time of performance by
respondent, and, because of structural changes, it readjusted the
amount due. It increased payments to the principal contractor,
reduced the payment to respondent by about $1,000 because of
construction economics under the new plans, and waived any claim to
liquidated damages for the period of the extension. The hospital
was completed some months after it would have been finished had it
not been for the change of plan.
The respondent was paid the full amount agreed on for the work
it did. It then sued for about $25,000 for damages alleged to have
been suffered due to delay for which the government was
responsible. The Court of Claims held the government was liable for
damages resulting solely from delay, but found that $13,600 of the
alleged loss was due to respondent's own faulty estimate and
financial conditions, and that $3,000 of it was caused by
respondent's and the principal contractor's delays. Respondent
sought no review of denial of this part of its
Page 317 U. S. 64
claim. However, the court concluded that the balance claimed,
$9,349, arose from overhead costs during the summer of 1932, when
the new foundation was being prepared, and from a decrease in labor
effectiveness resulting because much of the work had to be done
outside in cold weather. The judgment rendered under this
conclusion is what we have before us.
The chief issues of the case are whether the delay in commencing
the construction was a breach of contract by the government;
whether, regardless of the answer to that question, respondent was
entitled to an equitable adjustment for damages resulting from the
delay, in addition to the extension of time already granted, and
whether respondent is barred from any recovery because he failed to
appeal certain decisions affecting his contract to the chief
officer of the department. Under the view we take of the first two
of these questions, it is unnecessary to answer the third.
I. The government contends, as it did in the
Crook
case,
supra, that the change in specifications resulting
in delay was not a breach of the contract, but in accordance with
its terms; that the extent of its obligation for permitted changes
was fixed by the contract, and that, for delay, the government was
required to do no more than grant an extension of time. Put another
way, the government concedes that, if an alteration of plan
required respondent to use an extra 50 tons of steel, the
government would be liable for the value of the steel and the cost
of installation; but it argues that, under the terms of this
contract, an extension of time should be accepted as full equitable
adjustment for all damages caused by the fact that the work was
done at the later period made necessary by the permitted change.
Essentially, it repeats the doctrine of
Chouteau v. United
States, 95 U. S. 61,
95 U. S. 68:
"For the reasonable cost and expenses of the changes made in the
construction, payment was to be made; but, for any increase
Page 317 U. S. 65
in the cost of the work not changed, no provision was made."
We agree with this view. We do not think the terms of the
contract bound the government to have the contemplated structure
ready for respondent at a fixed time. Provisions of the contract
showed that the dates were tentative, and subject to modification
by the government. The contractor was absolved from payment of
prescribed liquidated damages for delay if it resulted from a
number of causes, including "acts of Government" and "unusually
severe weather." The government reserved the right to make changes
which might interrupt the work, and even to suspend any portion of
the construction if it were deemed necessary. Respondent was
required to adjust its work to that of the general contractor, so
that delay by the general contractor would necessarily delay
respondent's work. Under these circumstances, it seems appropriate
to repeat what was said in the
Crook case -- that,
"When such a situation was displayed by the contract, it was not
to be expected that the Government should bind itself to a fixed
time for the work to come to an end, and there is not a word in the
instrument by which it did so, unless an undertaking contrary to
what seems to us the implication is implied."
Crook Co. v. United States, supra, 270 U. S. 6.
Decisions of this Court prior to the
Crook case also make
it clear that contracts such as this do not bind the government to
have the property ready for work by a contractor at a particular
time.
Wells Bros. Co. v. United States, 254 U. S.
83,
254 U. S. 86;
Chouteau v. United States, supra; cf. United States v.
Smith, 94 U. S. 214,
94 U. S.
217.
As pointed out, the delay here resulted from a change in
specifications made necessary by discovery of soil unsuitable for
foundation purposes. The government having reserved the right to
make such changes upon discovery of
"subsurface and (or) latent conditions at the
Page 317 U. S. 66
site materially differing from those shown on the drawings or
indicated by the specifications,"
delays incident to the permitted changes cannot amount to a
breach of contract. If there are rights to recover damages where
the government exercises its reserved power to delay, they must be
found in the particular provisions fixing the rights of the
parties.
II. Two of the Judges of the Court of Claims thought
consequential damages resulting from delay were recoverable under
paragraphs 4 and 3 of the contract. These paragraphs
* deal with closely
related problems. Article 3, entitled "Changes," governs the
procedure under which the government may alter the specifications
of the contract for general causes. Article 4, entitled "Changed
Conditions," governs the procedure under which the government may
alter the contract to meet unanticipated physical conditions.
Article 4 incorporates by reference
Page 317 U. S. 67
the same machinery of adjustments as that specified in article
3. Both clauses essentially provide that, if changes are made
affecting an increase or decrease of cost or affecting the length
of time of performance, and equitable adjustment shall be made.
Clearly, questions of interpretation in clauses so similar
should, if possible, be resolved in the same fashion in each of
them. Clause 4 was added to the standard form contract since clause
3, and we therefore turn first to decisions interpreting the latter
clause. The Court of Claims, relying on principles announced in the
Chouteau, Wells, and
Crook cases,
supra,
has uniformly held that the "increase or decrease of cost" language
in Sec. 3 and in similar clauses is not broad enough to include
damages for delay; that
"It was never contemplated . . . that delays incident to changes
would subject the Government to damage beyond that involved in the
changes themselves."
Moran Bros. Co. v. United States, 61 Ct.Cls. 73, 102,
and, for the same view,
see McCord v. United States, 9
Ct.Cls. 155, 169;
Swift et al. v. United States, 14
Ct.Cls. 208, 231;
Griffiths v. United States, 74 Ct.Cls.
245, 255.
Were this a matter of first impression, we would again come to
the same conclusion regarding this clause. It seems wholly
reasonable that "an increase or decrease in the amount due" should
be met with an alteration of price, and that "an increase or
decrease . . . in the time required" should be met with alteration
of the time allowed; for "increase or decrease of cost" plainly
applies to the changes in cost due to the structural changes
required by the altered specification and not to consequential
damages which might flow from delay taken care of in the
"difference in time" provision. The provision as to time serves the
large purpose of removing from persons in the position of
respondent liability for "delay" beyond the stipulated date for
which they might otherwise have
Page 317 U. S. 68
their contract terminated, or might be required to pay
liquidated damages without fault.
Despite the similarity of the two clauses, a minority of the
court below has, in this instance, concluded that they may be
distinguished, and that respondent is entitled to damages for delay
under clause 4. In supporting this view, respondents here rely
primarily on
Rust Engineering Co. v. United States, 86
Ct.Cls. 461, 475, where the court below distinguishes the two
clauses by saying that the type of change contemplated in clause 4
is more basic than that under clause 3, and that, therefore,
different liabilities should attach:
"The changes made necessary by reason of the conditions
encountered in excavating for the foundation of the building were
not reasonable changes within the scope of the drawings and
specifications as contemplated in Art. 3 of the contract, but
represented important changes based upon changed conditions which
were unknown and materially different from those shown on the
drawings or indicated in the specifications. Such changes were
therefore clearly not within the contemplation of either party to
the contract at the time it was made. . . ."
And see Sobel v. United States, 88 Ct.Cls. 149,
165.
No such strained distinction between paragraphs 3 and 4 can
stand. It does not help to argue that the changes made under clause
4 "are not within the contemplation of either party," since the
changes made under clause 3 are also not contemplated in advance.
Both clauses deal with changes made necessary by new plans or new
discoveries made subsequent to the signing of the contract. For
delays incident to such unanticipated changes, the contractor was
under either section to be granted a "compensating extension of
time."
Wells Bros. Co. v. United States, supra,
254 U. S.
86.
In this case, there were two consequences of the discovery that
the Home could not be built as originally planned. One was an
alteration of specifications, which resulted in slight cut in
respondent's outlay and in his compensation. The other was the
delay itself, and, for this, the time necessary to perform the
contract was equitably adjusted by extension, thereby relieving
respondent of liquidated damages which could otherwise have been
imposed. Under the terms of the contract, it is entitled to no
more.
Reversed.
*
"Article 3. Changes. -- The contracting officer may at any time,
by a written order and without notice to the sureties, make changes
in the drawings and (or) specifications of this contract and within
the general scope thereof. If such changes cause an increase or
decrease in the amount due under this contract, or in the time
required for its performance, an equitable adjustment shall be made
and the contract shall be modified in writing accordingly. . .
."
"Article 4. -- Changed conditions. -- Should the contractor
encounter, or the Government discover, during the progress of the
work subsurface and (or) latent conditions at the site materially
differing from those shown on the drawings or indicated in the
specifications, the attention of the contracting officer shall be
called immediately to such conditions before they are disturbed.
The contracting officer shall thereupon promptly investigate the
conditions, and, if he finds that they materially differ from those
shown on the drawings or indicated in the specifications, he shall
at once, with the written approval of the head of the department or
his representative, make such changes in the drawings and (or)
specifications as he may find necessary, and any increase or
decrease of cost and (or) difference in time resulting from such
changes shall be adjusted as provided in Article 3 of this
contract."