A schooner bound with cargo from New Orleans to Bordeaux
developed leaks because of unseaworthiness existing when she broke
ground, and was forced to take refuge in Havana for repairs. Before
the repairs were completed, an embargo was put into effect by the
United States. Prevented by this from continuing to Bordeaux, she
proceeded to New York, and was there libeled by the cargo owners.
The unseaworthiness was unknown to her owner or master when the
voyage began, but could have been discovered by due diligence.
Held:
Page 277 U. S. 324
1. That recovery was rightly limited to actual damage to the
cargo due to unseaworthiness and to the difference between the
value of the cargo at Bordeaux had it arrived there on the contract
voyage and its value on arrival had the vessel proceeded there from
Havana when she was repaired and ready for sea. Pp.
277 U. S. 330,
277 U. S.
333.
2. Clauses in the bill of lading entitling the ship owner to
retain the prepaid freight in case of forced interruption or
abandonment of the voyage, and exempting the vessel from liability
for "restraint of princes," etc., were not displaced by the
departure, so that the freight and the damage due to the embargo
were not recoverable by the cargo owners. P.
277 U. S.
333.
3. The rule that a voluntary deviation from the prescribed
voyage displaces the contract of affreightment is not to be
extended to deviation to avoid perils of the sea, even in a case
where the deviation would not have been necessary if the owner had
used reasonable diligence to start the voyage with a seaworthy
vessel. P.
277 U. S.
332.
4. In the absence of any showing that the embargo could
reasonably have been foreseen by the ship owner, or of special
circumstances charging the ship owner with the knowledge or
expectation that the unseaworthiness, or consequent delay, would
bring the vessel within its operation, the damage resulting from it
to cargo owners is not attributable to the negligence of the ship
owner, but to the embargo itself. P.
277 U. S.
333.
5. The ship owner having brought itself within the exception of
the bill of lading, the burden was on the cargo owners to show that
the negligence was the cause of or contributed to the loss. P.
277 U. S.
334.
20 F.2d 304 affirmed.
Certiorari, 275 U.S. 517, to a decree of the circuit court of
appeals, reversing a decree awarding damages in a suit begun by
libel against the schooner above named. The present respondent
petitioned for exoneration and limitation of liability.
*
Page 277 U. S. 329
MR. JUSTICE STONE delivered the opinion of the Court.
Petitioners, in July, 1917, shipped a cargo on the schooner
Malcolm Baxter, owned by respondent, from New Orleans to
Bordeaux, and prepaid the freight. The bill of lading
stipulated:
"prepaid freight is to be considered as earned in shipment of
goods, and is to be retained by vessel's owner . . . if there be
forced interruption or abandonment of the voyage at a port of
distress or elsewhere."
In addition, there was the usual clause exempting the vessel
from "restraints of princes, rulers, and peoples." After departure
from New Orleans, the
Baxter developed leaks due to
unseaworthiness which caused her to put in at Key West, where she
was surveyed. In order to effect the necessary repairs, she was
towed to Havana, where she was unladen and repaired, remaining
there for that purpose until January 14, 1918. Before the
completion of the repairs, the United States Export Administrative
Board put into effect its ruling of November
Page 277 U. S. 330
18, 1917, that sailing vessels would not be permitted to clear
for points beyond the war zone. This ruling remaining in force when
the repairs were completed, the
Baxter, being unable to
secure a clearance for Bordeaux, took her cargo on board and
proceeded to New York, where the petitioners libeled the vessel in
the District Court for Southern New York to recover freight money,
damages to cargo, and damages for failure to perform the contract
voyage from New Orleans to Bordeaux.
Respondent, as owner, filed a petition for exoneration and
limitation of liability and enjoined further proceedings on the
libels. Petitioners filed claims in the limitation proceedings,
claiming damages as in the original libels, setting up the
deviation and the abandonment of the voyage by reason of the ship's
unseaworthiness on sailing.
The district court denied the petition to limit liability, but
allowed the claim for freight money and for damages sustained by
petitioners, including damage to cargo. A special master, appointed
to take proof of damage, found that the measure of damages was the
excess cost of the substituted carriage and incidental expenses,
and, in the case of goods which could not be sent forward, the
damage was measured by the difference between the value of the
goods at the time when and in the condition in which they should
have arrived at destination and their value at the place where and
in the condition in which they actually were received, less charges
saved plus incidental expenses. Final decree was given to the
petitioners for the damage as found.
The Circuit Court of Appeals for the Second Circuit upheld the
ruling of the district court denying exoneration and limitation of
liability, but reversed the judgment, holding there could be no
recovery of the prepaid freight or excess cost of transportation
over prepaid freight; that the recovery of damages must be limited
to actual damages to
Page 277 U. S. 331
cargo resulting from unseaworthiness, and the difference between
the value of the cargo had it arrived in Bordeaux on a straight
voyage on August 16, 1917, the date when the
Baxter
sailed, and on a voyage leaving Havana January 14, 1918, the date
when the repairs were completed and the
Baxter was ready
for sea.
The Malcolm Baxter, Jr., 20 F.2d 304.
Both courts below agreed that the
Baxter was
unseaworthy on sailing, and that respondent failed to exercise due
diligence to ascertain her condition before sailing. This was
sufficient ground for denying the petition for exoneration and
limitation of liability under the Harter Act (Act Feb. 13, 1893),
c. 105, 27 Stat. 445, and acts permitting limitation of liability
to the vessel and pending freight. R.S. §§ 4282-4289. The
correctness of this determination is not raised on the petition
here,
Federal Trade Commission v. Pacific Paper Assn.,
273 U. S. 52,
273 U. S. 66,
but petitioners urge that the
Baxter's putting in first at
Key West, and later at Havana, must be deemed a voluntary deviation
because due to the negligence of the owner in failing to discover
the unseaworthiness and to make the vessel seaworthy before
sailing.
Unseaworthiness alone, or deviation caused by it, displaces the
contract of affreightment only insofar as damage is caused by the
unseaworthiness.
The Caledonia, 157 U.
S. 124;
The Europa, [1908] P. 84;
Thorley
v. Orchis S.S. Col, Ltd., [1907] 1 K.B. 660;
Kish v.
Taylor, [1912] A.C. 604, 618. But if the deviation here is to
be classed with voluntary deviations, respondent may not claim the
benefit of the clauses of the bill of landing and is responsible
for the cargo as insurer.
The Willdomino, 272 U.
S. 718;
St. Johns Corp. v. Companhia Geral,
etc., 263 U. S. 119;
Mobile & Montgomery Ry. v. Jurey, 111 U.
S. 584;
Lawrence v.
Minturn, 17 How. 111.
And see The
Indrapura, 171 F. 929. In any case it is contended that
respondent's negligent failure to discover the unseaworthiness
Page 277 U. S. 332
of the vessel resulted in the delay which brought her within the
operation of the embargo, and that the shipowners are for that
reason liable for damages for all the delay, including that
immediately resulting from the embargo.
Respondents had purchased the vessel about one month before she
sailed. At that time, she was unseaworthy due to a hog or camber in
her keel, a structural weakness dangerous to the ship in heavy
weather, which later caused the leak and made necessary the repairs
at Havana. Following the purchase and before sailing from New
Orleans, a survey was made by the owner which appears not to have
disclosed her condition, but both courts below agree that the fact
of her unseaworthiness could have been discovered by due
diligence.
The evidence supports the finding of the court of appeals that
the master of the
Baxter
"did not leave New Orleans with knowledge that he would have to
make port for repairs, and honestly thought he could make the trip
in safety, and tried unsuccessfully to do so."
The case is therefore not one where the master set sail with the
knowledge that the deviation from the voyage, as described in the
bill of lading, would ensue, and with the purpose and intent to
deviate, as in
The Willdomino, supra. There, the officers
of the vessel, under direction of the owner, sailed from Ponta
Delgada, bound for New York, all knowing that the supply of fuel
was insufficient for the voyage, and intending to take the vessel
to North Sidney, and we held that the deviation under the
circumstances was voluntary and inexcusable.
But here, the deviation was not voluntary, and the point to be
determined is whether a like effect is to be given to a deviation
to avoid perils of the sea where the deviation would not have been
necessary if the owner had used reasonable diligence to start the
voyage with a seaworthy vessel.
No sufficient reason is suggested to us for thus extending the
rule, nor do we perceive any. Petitioner, without
Page 277 U. S. 333
resort to it, is entitled to recover all damages caused by the
unseaworthiness. The basis of the privilege of deviation to avoid
perils of the sea is humanitarian.
See Carver, Carriage by
Sea (7th ed.) §§ 291, 292. To hold that the master whose ship is in
a perilous position must choose between the hazard of continuing
the voyage and gaining safety only by forfeiting the contract of
affreightment would be a departure from that principle for no
purpose except to give the shipper an added and unnecessary
protection. "It is the presence of the peril, and not its cause,"
which justifies the deviation.
See Strang v. Scott, 14
App.Cas. 801. This is the conclusion reached in other circuits
(
The Turret Crown, 297 F. 766;
The Turret Crown,
284 F. 439, 445;
The Turret Crown, 282 F. 354, 360;
see The Thessaloniki, 267 F. 67), and by the House of
Lords in
Kish v. Taylor, supra, holding that a deviation
caused by unseaworthiness due to improper and negligent loading of
the ship by the master did not displace the bill of lading. This
rule we adopt as most consonant with the reason and consequences of
the rule that a voluntary deviation displaces the contract of
affreightment. It follows that the clauses of the bill of lading
remain effective, and that petitioner may not recover the freight
money.
Allanwilde Corp. v. Vacuum Oil Co., 248 U.
S. 377.
But for all damages legally attributable to the breach of
warranty of seaworthiness petitioners may recover.
The
Caledonia, supra. For the delay caused by the embargo alone,
petitioners may not recover, both because it was within the
exception of the bill of lading and because, while it continued,
performance of the contract of affreightment would have been
illegal.
See Allanwilde Corp. v. Vacuum Oil Co., supra,
385; Carver, Carriage by Sea (7th ed.) §§ 237, 238, 343, 344.
It was the embargo, and not the unseaworthiness of the vessel,
which delayed the voyage after the
Baxter was repaired and
ready for sea on January 14, 1918, and the unseaworthiness of the
vessel did not cause the embargo.
Page 277 U. S. 334
But it is urged that it is enough to sustain the recovery for
the failure to complete the voyage that it was the unseaworthiness,
for which respondent was responsible, that brought the vessel
within the excepted peril. This view, although not without support
(
Green-Wheeler Shoe Co. v. Chicago, Rock Island & P. R.
Co., 130 Iowa, 123;
Michaels v. New York Central R.
Co., 30 N.Y. 564;
Condict v. Grand Trunk Ry., 54 N.Y.
500), does not generally prevail.
See 2 Williston,
Contracts § 1906, and cases cited.
It was rejected by this Court in
Railroad
Co. v. Reeves, 10 Wall. 176. There, negligent delay
in the transportation of goods by the carrier brought them within
the path of a flood, which caused their destruction. The Court held
that the flood, and not the negligent delay, was the proximate
cause of the damage, and that the rule "
causa proxima non
remota spectatur" applied to contracts of common carriers as
to others. There has been no departure from this rule, and we see
no reason for departing from it now.
See Milwaukee & St.
Paul Ry. v. Kellogg, 94 U. S. 469;
Atchison, Topeka & Santa Fe Ry. v. Calhoun,
213 U. S. 1;
The
Indrapura, supra; The Lusitania, 251 F. 715, 732;
The
Turret Crown, 282 F. 354, 360. There is no finding, nor is it
suggested, that at the time when the contract of affreightment was
entered into, or when the vessel broke ground, that the embargo
could reasonably have been foreseen, or that there were any special
circumstances charging petitioners with the knowledge or
expectation that the unseaworthiness or consequent delay would
bring the vessel within its operation. The respondent having
brought itself within the exception under its bill of lading, the
burden is on petitioners to show that respondents' negligence was
the cause of or contributed to the loss.
Railroad Co. v.
Reeves, supra, 77 U. S. 190;
Transportation Co. v.
Downer, 11 Wall. 129.
See Southern Ry. v.
Prescott, 240 U. S. 632,
240 U.S. 641;
Kohlsaat
v. Parkersburg & Marietta Sand Co., 266 F. 283, 285.
Affirmed.
* The docket title of the case in this Court was
Republic of
France et al. v. French Overseas Corporation, as owner,
etc.