1. Where a contractor with the government completed the job
under the contract, reserving the right to claim damages due to
long delays by the government in performing its part, the measure
of such damages was not the difference between the contract
price
Page 271 U. S. 264
and the higher market value of the work at time of performance,
but the loss actually sustained by the contractor as the result of
the delay. P.
271 U. S.
266.
2. In computing such damages,
held that the contractor
could not be allowed the difference between the cost of supplies
bought and held for the work under the contract and the higher
market price they had acquired by the time when they were used in
it, in the absence of evidence that this was the measure of the
loss. P.
271 U. S. 267.
59 Ct.Cls. 980, reversed.
Appeal from a judgment of the Court of Claims allowing damages
for delay in performance of the claimant's contract due to the
fault of the United States.
MR. JUSTICE BRANDEIS delivered the opinion of the Court.
The Wyckoff Pipe & Creosoting Company, Inc., contracted with
the United States, in December, 1917, to lay creosoted wood block
floors in Navy Yard buildings at Norfolk, Virginia, furnishing all
necessary labor and materials. On a part of the job, the contractor
was to begin the work immediately after delivery of a copy of the
contract. This part was to be completed within 30 days thereafter.
On other parts, work was to be deferred until such time as the
government was ready to proceed. These parts were to be finished
within 43 days from the dates on which they were begun. The
flooring was to be set in a concrete base which was to be laid
promptly by the government. The contractor prepared itself
immediately to perform the contract. Among other things, it
purchased the lumber and creosote oil needed for the job. Long
delays by the government in furnishing the concrete
Page 271 U. S. 265
bases prevented performance by the contractor. Thus, more than
two years elapsed before the work was completed. The contractor was
without fault.
The government's delays confessedly caused the contractor some
loss. For the loss so suffered the government was confessedly
liable. It made payment at the fixed contract rate of $2.26 per
square yard, and paid an additional amount, also provided by the
contract, equal to 50 percent of the estimated increase in the
labor cost. It paid nothing otherwise on account of the damages
caused by its delay. To recover compensation for the loss suffered,
this suit on the contract was brought in the Court of Claims in
January, 1923. That court assessed the damages at $10,122.99, and
for that amount it entered judgment, without an opinion, on June 2,
1924. 59 Ct.Cls. 980. The case is here on appeal under ยง 242 of the
Judicial Code. The only question presented is whether there was
error in the measure of damages adopted.
The findings of fact recite that the contractor, in reserving
its right to claim damages for extras by reason of the long
unanticipated delay, had enumerated as items of the proposed claim
extra labor on account of the advance in the scale of wages, extra
expense by reason of renewal premiums on surety company bonds,
additional freight rates on sand and other material, additional
cost of sand, additional cost of creosote oil, storage, insurance,
and carrying charges "on a large stock of lumber purchased for the
account of your contract and carried in our yard for a space of
between one and two years." The findings also recite that the
record does not disclose by items the amount of extra expense
incurred by the contractor by reason of the lengthy delay in the
performance of the work. The court made no finding or estimate of
the loss so incurred. It found merely that the increase in the
prevailing market price of lumber from the time
Page 271 U. S. 266
that used was bought by the contractor until it was actually
employed on the job was $6,021.23; that the increase in the
prevailing market price of the creosote oil required from the time
it was purchased for the job until it actually was so used amounted
to $712.59; that the reasonable value of the contract work per
square yard at the time it was actually performed was, for a part
$2.68, for a part $2.98, and for the rest $3.28, and that the
reasonable value of the whole work at the time it was done by the
contractor, based upon prices then paid by the government on other
work then done at the Navy Yard, was $9,936.54 in excess of the
amount which the contractor had received. It was for this sum of
$9,936.54, plus an item of $186.45 about which there is no dispute,
that the Court of Claims entered its judgment of $10,122.99.
The government contends that recovery cannot be had on the
contract for the higher market value of the work at the time it was
actually performed; that the correct measure of damages for its
delay is the loss actually sustained by the contractor as the
result of the delay,
United States v. Smith, 94 U. S.
214;
United States v. Mueller, 113 U.
S. 153;
Ripley v. United States, 223 U.
S. 695; that the increase in the market value of
materials purchased for use on the contract cannot be deemed a
loss, and that to assess damages on the basis of the value of the
work at the time it was performed was, in effect, to make a new
contract for the parties or to allow recovery as upon
quantum
meruit. The contention is, in our opinion, well founded.
The contractor urges that the long delay was a breach which
would have justified it in terminating the contract and refusing to
do the work except under a new one at an increased price. But,
despite a contention to the contrary, it did not do this. It
completed the work under the contract as originally made. It did
not attempt to
Page 271 U. S. 267
make a new contract, or to modify the existing one. It sought
merely to reserve its right to make a claim for the damages
resulting from the government's delay. After completing
performance, it brought this suit declaring on the original
contract.
The contractor urges also that, because of the delay, it might
have used the supplies purchased on another job, receiving on that
their then market value, or might have sold them and taken the
incidental profit due to the rise in values, and that, if it had
done either and had been obliged later to purchase new supplies at
the higher market values in order to perform the government job,
the increased cost would have been recoverable as a loss, and that,
as the amount of this increase has been found, the recovery should
be sustained at least to that extent. The contractor's contentions,
however, ignore the rule that damages for delay are limited to the
actual losses incurred. The contractor elected to hold itself in
readiness to perform its contract, and, to this end, to retain both
the lumber and the creosote oil. The carrying charges thus incurred
are an allowable item of damage, but these were not shown. It may
even be that, in the event of a use or resale of the supplies, if
under the circumstances such a course of action was open to the
contractor, the profits made would have been available in reduction
of damages.
Compare Erie County Natural Gas & Fuel Co. v.
Carroll, [1911] App.Cas. 105. But clearly it cannot now charge
as a loss profits which it might have made if it had sold the
supplies in the market or used them on another job.
It is argued that the Court of Claims is under no obligation
when assessing damages to specify the elements of the calculation
by which it arrives at its results, that itemization is often
impossible, and that, like a jury, the court may make an estimate
and return such sum as the damages recoverable,
compare
94 U. S.
Smith, 94
Page 271 U. S. 268
U.S. 214,
94 U. S. 219, and
that, accepting the rule that damages are to be limited to actual
loss, the award of the lower court is to be regarded as an estimate
of such loss. But, in the case at bar, the court did not pursue
that course. It made no estimate of the loss suffered. It found
merely the increase in value of the work at the time it was
performed and the increase in value of the material during the
period of the delay. Then it found and concluded as a matter of law
that the excess of the reasonable value of the work at the time it
was done over the amount paid therefor was recoverable as damages.
This was error.
The judgment must be reversed. As there are no findings from
which the amount of the loss can be determined, the case is
remanded for further proceedings.
Reversed.