1. A contractor who incurred expense under a contract to
manufacture articles for the government for use in the late war,
but whose opportunity to perform and earn the contemplated profits
was cut short by the sudden cessation of hostilities, the
declaration of the armistice, and the consequent termination of the
contract in accordance with its terms, took the chances of this
contingency, and cannot recover damages. P.
260 U. S.
124.
2.
Held, in this case, that delay of the government in
furnishing necessary specification as contemplated by a contract
for the manufacture of airplane motors of a foreign model, due to
an honest but mistaken belief, shared by the contractor, that the
model was perfected and adequate specifications in existence, was
not an actionable breach of representation in view of the conduct
and dealings of the parties for the expedition of the work, the
absence of any protest over the delay, and the absence of averment
that it prevented the contractor from being fully occupied with
preparatory and other work under the contract . P.
260 U. S.
123.
Page 260 U. S. 116
3. Time was of the essence for the government, but not for the
contractor. P.
260 U. S.
124.
56 Ct.Clms. 96 affirmed.
Appeal from a judgment of the Court of Claims dismissing, on
demurrer, a petition claiming (1) the profits that would have been
made by the claimant, under a contract with the government for
manufacture of airplane motors, but for the government's alleged
failure to supply the necessary specifications as agreed; (2)
amounts paid by the claimant, because of the delay, as interest on
money borrowed from the government and private sources for use in
executing the contract, and (3), if (1) cannot be recovered, the
amount lost by the claimant through terminating its commercial
business to accept the contract.
Page 260 U. S. 119
MR. JUSTICE McKENNA delivered the opinion of the Court.
Action in the Court of Claims against the United States for
expenses in endeavoring to perform certain contracts with the
United States made during the war with Germany, or for anticipated
profits.
The contracts were for aeronautical equipment for war purposes.
There were a first and primary contract and seven other contracts
called supplemental agreements. The latter contained modifications
of the first or primary contract, and each agreement contained
modifications of those which preceded.
The first or primary contract, dated November 20, 1917, provided
for 500 United States standard 12-cylinder engines, sometimes
referred to as Liberty engines. By an agreement dated December 11,
1917, the number was increased to 1,000. By another agreement,
dated January 4, 1918, the type of motor was changed, and a motor
called the Bugatti motor was substituted, and there were other
agreements.
From this general statement it will be seen that the contract
and agreements are determining elements in the claims sued upon. A
full recital of them, however, would extend this opinion to an
embarrassing length. We shall confine ourselves, therefore, to
those which we regard of determining pertinence.
Page 260 U. S. 120
Upon demurrer of the United States, the Court of Claims decided
the contractor entitled to no relief and dismissed its petition.
This action is contested, and it is earnestly insisted that the
contracts made time their essence and required speed and dispatch
from the contractor, and demanded in their performance precedence
upon all other work, involving necessarily sacrifice and expense
upon the part of the contractor. And time, it is contended, being
of the essence of the contracts, this necessarily implied that the
United States must have done everything to permit the contractor to
comply with its obligations. The government, however, was
delinquent, and it is alleged that
"the drawings and specifications referred to in the contract
(Exhibit A) as being attached thereto (but which were not in fact
so attached) were furnished piecemeal from time to time, but not so
as to enable the claimant to enter into quantity production, and
the only work which was practicable under said contract was in
making extensive alterations in the plant of claimant company to
adapt it to the uses of the government for the purpose of carrying
out the contract (Exhibit A), to assemble a competent engineering
staff, and to make other preparations for the performance of said
contract, all of which the claimant did at great expense."
And further delinquency is charged in not performing the
agreement which substituted the Bugatti motors and Article I of the
agreement is quoted as follows:
"That, subject to all the provisions of Article I in said
contract No. 2318 contained, the contractor shall make for the
government, instead of the articles described in Article I of said
contract, 2,000 Bugatti motors, and such spare parts for said
motors as the government may order from time to time during the
period of the construction of said motors, in accordance with
specifications to follow."
The specifications were not furnished, it is said, until
September 25, 1918, and that the delay was a breach of
Page 260 U. S. 121
the contract and the contractor is entitled to recover for the
losses caused thereby.
To this the Court of Claims answered that the contract
contemplated a revision of the schedule [times of delivery] in
regard to the engines. The provision to which that purpose was
attributed is that:
"in view of the present uncertain factors inherent in the
articles and in the establishment of the industry of producing
them, it is understood that this schedule may require revision. . .
."
The schedule designated June, 1918, as the month of complete
production.
Changes were provided for in another article, and by still
another it was provided that if, in the opinion of the Chief Signal
Officer of the United States, the public interests so required, the
government might, upon 30 days' notice terminate the contract. And
there was provision for settlement of disputes.
Dates are important to be considered. The supplemental contract
in which Article I appears, and which adopts Article I of the first
contract, is dated January 4, 1918. Another agreement which was
supplementary to that agreement was dated January 15, 1918, and
still another dated February 11, 1918.
In none of these agreements, continuing as they did the
obligations of the parties to them and the means of their
performance, is there a word of complaint that the government had
been or was delinquent on account of not furnishing specifications
or in any way. In the agreement of February 11, 1918, in Article
II, it is provided that:
"In the interest of both parties hereto and in order to expedite
the delivery of the said supplies, the government will advance to
the contractor under the principal agreement the sum of four
hundred thousand dollars ($400,000) on the terms and security
hereinafter mentioned, and will make payments directly to the
contractor by check dated February 25, 1918. "
Page 260 U. S. 122
There was another agreement dated February 14, 1918, which
continued in effect, except as modified, all that preceded. There
was no protest or complaint of any kind, no accusation of default
or delay on the part of the government.
There was a seventh agreement made September 26, 1918, and
another made October 23, 1918, for advance payments to the
contractor.
The agreements are of significant strength. Their legal effect
and that of the contract cannot be determined by any one provision,
but the totality of them must be regarded and their relations and
purposes.
A war of magnitude was waging. The government was eager for
efficient instrumentalities, and the contractor was enticed by the
profit of their manufacture. The matters were urgent, but they were
beset with contingencies. The government could terminate the
contract in the interest of the public welfare, and the war might
cease. The latter did happen. However, before it happened and
before, it may be, there were signs of its happening, there were
dealings and adjustments of preparation between the government and
the contractor. They took care of, and were intended to take care
of, changing purposes, and no dissatisfaction was expressed. One of
the changes was, as we have said, from the construction of 500
Liberty motors to 1,000, the completion and delivery of which was
to be in June, 1918, and, as we have said, another change was the
substitution of 2,000 Bugatti motors for the Liberty engines and
for such spare parts as the government might order from time to
time; the motors to be delivered by September, 1918. By the
supplemental agreements which provided for those changes it was
also provided that their cost was to be paid by the government, and
the profit of the contractor was changed from $625 for each article
to $750, and the government agreed to advance the contractor
$1,250,000 to be repaid with interest at 6%.
Page 260 U. S. 123
Upon this change to the Bugatti motors comes the first claim of
the contractor, based upon Article I of the agreement of January 4,
1918, by which it was provided as follows:
"That subject to all the provisions of Article I in said
contract No. 2318 contained, the contractor shall make for the
government, instead of the articles described in Article I of said
contract, two thousand (2,000) Bugatti motors, and such spare parts
for said motors as the government may order from time to time
during the period of the construction of said motors,
in
accordance with specifications to follow."
(Italics ours.)
No time is specified. It is, however, contended that necessarily
a reasonable time must have been intended and was not observed. The
specifications, it is alleged, did not follow until September 25,
1918, when the entire time for the production of the motors was
within a few days of expiring, whereby it became impossible to
produce any of the articles within the time limit of the
contract.
It is not alleged, however, that the failure to furnish the
specifications was willful on the part of the government or
fraudulent. On the contrary, it is alleged that there was a belief
upon the part of the government officers by whom and under whom the
supplemental agreement was made that there were in existence
complete specifications of the articles which needed only to be
obtained from France; that the motors had passed the experimental
stage and were ready for production. It is, however, alleged that
the statements in the contract operated as a representation to the
contractor that such was the fact, and that production in quantity
could begin at or shortly after the entry into the agreement. It is
further alleged that, when the first motor was received shortly
after the date of the agreement it developed that extensive changes
would be necessary and the contractor was directed to proceed,
meanwhile actively, with production
Page 260 U. S. 124
on the separate parts to the extent possible in view of the
undeveloped character of the specifications of the engine. This was
done in conjunction with the officers of the government.
It will be observed that it is not alleged that the belief of
the government officers was not consistently entertained nor that
the contractor did not share it. Nor is it said that the work on
the separate parts and the preparations for the performance of the
contract did not engage the contractor's time. Indeed, the fact is
that, by January 4, there were changes to the advantage of the
contractor, and again by the agreement of February 11, 1918, and
another as late as October 23, 1918, by which the government agreed
to advance to the contractor $1,250,000. And still no complaint. On
the contrary there was acceptance of assistance.
It is manifest there were uncertainties on both sides and that
as they developed preparations were necessary to meet them, and in
meeting them, the contractor did not regard the government in any
way delinquent. It was the abrupt and unexpected suspension of
hostilities and the declaration of an armistice that was the cause
of loss to the contractor, and the disappointment of profits from
its contract which it was preparing to realize and would have
realized. But it took that chance and has not now a legal claim
against the government for reimbursement of its outlays. We need
not distinguish between the outlays nor dwell upon them. They were
outlays of the speculation, and subject to sacrifice and loss with
its disappointment.
We have seen that counsel make much of the effect of the
government's urgency, and, it is contended, time in consequence
became an essential of the contract. This, the contention is,
influenced the contractor and necessarily determines the obligation
of the government. The government was undoubtedly urgent, made so
by its serious
Page 260 U. S. 125
situation and tremendous responsibilities, but such was not the
situation of the contractor. Time to perform its contract was all
that was necessary to it, and, but for the Armistice, it would have
had time. If the Armistice could have been foreseen, the relative
situations might have been different. Expedition would not then
have been exigent to the government's purposes, but would then have
been necessary to the contractor if profits were to be realized
from the production of the motors. There was no prophecy of the
Armistice -- its sudden happening terminated the further execution
of the contractor's undertaking, preventing, as we have said, the
realization of profits. And, we repeat, this chance the contractor
took and must abide the result.
Judgment affirmed.