Claimants contracted with the government to plan and supervise
the construction of a public building for a fee, to be paid on
monthly estimates and final completion, of 5 percent of the actual
cost of the work executed from their drawing and specifications and
under their supervision, as shown upon the books of the Supervising
Architect by the net amount of construction contracts
Page 257 U. S. 524
awarded and proposals accepted for additions or deductions. The
building was delayed by an earthquake and fire, and Congress made
an additional appropriation to be paid the building contractor upon
its completion to recoup him for actually resulting losses due to
increased prices of labor and materials, denying him any profit
under his contract, and this extra payment was shown on the book of
the Supervising Architect, but no appropriation was made for the
claimants, although they had suffered likewise, and had applied to
Congress unsuccessfully.
Held:
(1) The allowance to the building contractor was not a gratuity,
but an alteration of his contract based on a moral consideration.
P.
257 U. S.
526.
(2) Claimants were entitled to their percentage on the
additional amount so paid, since their equity was equally as strong
and the words of their contract permitted. P.
257 U. S.
528.
55 Ct.Clms. 215 affirmed.
Appeal from a judgment of the Court of Claims upholding a claim
of architects for fees under a contract with the United States.
MR. CHIEF JUSTICE TAFT delivered the opinion of the Court.
Eames and Young, architects of St. Louis, made the plans for a
custom house at San Francisco and supervised its construction. They
were to receive compensation at the rate of five percentum upon the
actual cost of the work. The work was long delayed, three years, by
the San Francisco earthquake and fire, which increased the cost of
labor and materials. Congress authorized the Secretary of the
Treasury, within a limit of $250,000, to make good to the
contractor his loss from the delay and enhanced prices, so that he
should receive enough to recoup
Page 257 U. S. 525
him for his outlay, but without profit. The architects claimed
from the government five percentum on the extra amount paid to the
contractor. Eames died, and Cook, his executor, joining with the
surviving partner, Young, brought this suit in the Court of Claims.
The Court of Claims gave judgment for $5,085.38, the full amount of
the claim. The government appeals.
The contract provided that the fee of the architects was to be
computed at the rate of five percentum upon
"the actual cost of the work executed from the drawings and
specifications, as shown upon the books of the supervising
architect's office, by the net amounts of contracts awarded and
proposals accepted for additions and deductions."
Until the actual cost could be determined, the monthly payments
were to be on the proposed cost as estimated from time to time by
the government, and upon the completion of the building the entire
fee was to be computed on the actual construction cost of the work
executed from the architect's drawings and specifications and under
their supervision, as shown upon the books of the supervising
architect's office. The extra amount paid the contractor was in
fact shown upon the books of the supervising architect's office,
though not, of course, included in the total cost stated before the
passage of the act and the ascertainment of the amount due
thereunder.
The clause in the Sundry Civil Appropriation Act approved May
27, 1908, 35 Stat. 318, providing for an extra payment to the
contractor was as follows:
"The Secretary of the Treasury is authorized, upon completion of
the custom house in . . . San Francisco, California, to pay to
Thomas Butler, the contractor for the construction of said
building, in addition to the contract price therefor, such sum as
may be equitable and just to reimburse said contractor for any loss
actually sustained
Page 257 U. S. 526
in consequence of the earthquake and great fire of April, 1906,
not exceeding the sum of $250,000:
Provided, that the
amount allowed said Thomas Butler shall not be sufficient to enable
him to make any profit out of the making and execution of said
contract."
The committee appointed by the Secretary of the Treasury to
adjust the claim found that the actual increased cost to the
contractor of constructing the building due to delay and the
increased prices of labor and material was $101,907.66. During the
delay of three years, the architects under their subsidiary
contract had to keep a superintendent of construction on the
building at a cost of $6,700, and their office and certain
contingent expenses in San Francisco went on.
The government contends that the amount awarded to the
contractor under the act was a mere gratuity, and cannot be
properly treated as a part of the cost of construction. We cannot
agree to this view. It seems to us that this was an alteration of
the contract in response to equitable considerations. It was a
change from unit prices to a cost plus nothing contract. It was not
a mere lump sum gift. It was the result of inspection and
examination, as directed by Congress, and an award by actual
estimates. It was the result of a change in the contract terms made
by the principal, in whose name and for whose benefit the contract
was entered into, and acquiesced in by the contractor. It added
to
"the actual cost of the work executed from the drawings and
specifications and under the architects' supervision as shown upon
the books of the supervising architect's office, by the net amounts
of contracts awarded and proposals accepted for additions and
deductions."
The additional sum was part of the net amount of the contracts
awarded, as they were legally modified by the agreement of the
parties embodied in the clause of the congressional act. The
Page 257 U. S. 527
architects' subsidiary contract for compensation contemplated
changes in the amount of actual cost by additions and deductions --
i.e., by changes in the main contract, and a postponement
of final calculation until the full actual cost had been
ascertained. The change by legislation was, of course, not within
the minds of the parties when the work was entered upon, because
the earthquake and fire and change of situation were not
anticipated. This, however, is not enough to exclude it from the
operation of the architects' contract if the change can be brought
fairly within the terms.
It is not helpful to point out that the United States need not
have varied the terms of the main contract, or that no
consideration moved to it in the change, or that the contractor
could not have recovered anything additional in a suit without the
legislation. There was the moral consideration which properly
induced the recognition of an honorable obligation and turned an
unenforceable equity into a binding and effective provision.
Reference is made to
Frisbie v. United States,
157 U. S. 166,
and other cases, in which a pension is said to be a gift, and not a
vested right. These cases have no bearing on the one before us.
They merely establish that Congress, in shaping the form of its
bounty, may impose conditions and limitations on its acquisition
and enjoyment by the beneficiaries which it could not impose on the
use and enjoyment by them of a vested right.
An authority more helpful in the present case is that of
United States v. Realty Co., 163 U.
S. 427. The question there was the validity of an
appropriation by Congress of money to reimburse sugar planters who,
on the faith of a sugar bounty provided by statute,
Field v.
Clark, 143 U. S. 649,
143 U. S. 694,
had planted a crop and were subjected to heavy loss by repeal of
the statute. The government objected that the sugar bounty was
unconstitutional, and that Congress could not pay such a bounty
either by
Page 257 U. S. 528
prior appropriation or by reimbursement. This Court found it
unnecessary to decide whether a sugar bounty was beyond the power
of Congress, but, assuming its invalidity, held that, even though,
in its purely legal aspect, an invalid law could not be made the
basis of a legal claim, the planter had acquired a claim against
the government of "an equitable, moral, or honorary nature," that
Congress had power to pay the debts of the United States, that the
nation, speaking broadly, owed a "debt" to an individual when his
claim grew out of right and justice -- when, in other words, it was
based upon considerations of a moral or merely honorary nature --
and that the power of Congress extended to the payment of such a
debt. The claim of the contractor in this case was more concrete
than that of the sugar planter, and was equitably recognized by
Congress as part of the cost of the building to be paid by the
government.
The architects had just as great an equity in this matter as the
contractor. The delays and rise in the prices affected their
expenses proportionately. When, therefore, the contractor has
received more for the work, it is just that the architects receive
a percentage on what has thus been recognized by the government as
a "debt" to the contractor for his work, and the words of the
contract are inclusive enough to permit this to be done.
The fact that the architects unsuccessfully applied to Congress
for relief similar to that accorded to the contractor is relied on
as an admission by the architects that only by congressional action
could they have equity done them. We do not consider this material
or important. We cannot say from anything before us but that the
reason why Congress did not make special provision for the
architects was the assumption that their equities might be worked
out under their contract, as they have been by this judgment of the
Court of Claims.
Affirmed.