Appellant sued to reoover a large sum of money for the use which
he claimed the government had made of his patented improvement in
dike and breakwaters in the construction of jetties, which, with
dredging, had resulted in rendering navigable to seagoing vessel
the changel of Aranas Pass on the coast of Texas.
Held
that the appropriation acts evinced the willingness of Congress to
expend money in testing his patented devices, but no intention to
pay him until their usefulness should be proved, and that no
promise of the government to pay him for the use made could
reasonably be implied. P.
254 U. S.
278.
53 Ct.Clms. 591 affirmed.
The case is stated in the opinion.
MR. JUSTICE CLARKE delivered the opinion of the Court.
Aransas Pass is an inlet, naturally too shallow for ocean
navigation, connecting the waters of the Gulf of Mexico and those
of Arasnas Bay and the bay of Corpus Christi on the coast of Texas.
The problem of obtaining a navigable channel through this pass
occupied the attention of the government and of private enterprise
for many
Page 254 U. S. 273
years prior to 1912, when a channel of the desired depth of 20
feet was obtained.
This is a suit instituted by the appellant, Haupt, a
distinguished engineer and the patentee of improvements in dikes
and breakwaters, to recover a large sum of money for the use which
he claims the government made of his invention in the construction
of jetties, which, with dredging, resulted in the creating of the
Arasnas Pass channel in 1912. The Court of Claims dismissed the
petition, holding that no contract, express or implied, with the
United States was shown for the use of appellant's patented
invention, and that it was therefore without jurisdiction.
A resume of what was done in the effort to procure the channel,
which is necessary to a decision of the case, will develop the
relations of the appellant to the enterprise and to the government
on which he bases his claim.
Between 1880 and 1889, the United States government constructed
what is designated in the record as the "Mansfield Jetty," 5,500
feet in length, designed to deepen the channel through the Pass,
but it had no appreciable effect on the depth of water, and the
work was suspended in 1889.
In 1890, the State of Texas chartered the Arasnas Pass Harbor
Company, a private corporation, organized for the purpose of
improving the channel at Arasnas Pass, and in the same year
Congress authorized the company to construct such jetties and
breakwaters as might be necessary to create and permanently
maintain a navigable channel "across the outer bar which obstructs
the entrance to Arasnas Pass harbor." This company built the jetty
designated in the record as the "Nelson jetty," about 1,800 feet in
length, which also failed to deepen the channel, and was abandoned
in 1893.
In 1894, another act of Congress granted an extension of time to
the same company to further pursue its objects, and, at this point
in the history, the appellant appeared
Page 254 U. S. 274
with United States patent No. 380,569 for certain improvements
in dikes and breakwaters for improving the channels of rivers and
harbors.
In the view we take of the case, it will be a sufficient
statement of the principle involved in, and of the claims of,
appellant's patent to say that the inventor aimed to accomplish
results with a single jetty, of a form specially adapted to each
locality, which had theretofore been accomplished only with two or
more jetties. The claims are variously worded, as usual, but the
substance of the alleged discovery is that the study of the
conformation of the bottom and shores of a given locality and of
the prevailing currents, tidal and other, will enable one skilled
in the art to so apply the principles disclosed in the patent as to
give such form and location to a single breakwater or jetty that it
will "cut the advancing waves" and "resist and decompose the flood
resultant" in such manner that, without the aid of a second jetty
or of dredging, it will scour out and maintain a channel of the
required depth in a designated location.
The appellant granted a license to the Arasnas Pass Harbor
Company to use his patented device or design on condition that the
work should be done under his supervision, and he thereupon
prepared the necessary plans and drawings for the construction
which he thought would effectuate the desired result. The cost of
the jetty, as thus designed by the appellant, was too great for the
resources of the company, and, upon request, he eliminated a
portion of it, which reduced the estimated cost by one-half. The
jetty thus modified consisted of a reverse curve or letter "S," and
a contract for the construction of it was let in July, 1895. Work
was prosecuted vigorously until the following January, by which
time it was ascertained that a portion of the first, the "Mansfield
jetty," which had been reported officially as having disappeared,
was still in place and in such a position, it was claimed, as
to
Page 254 U. S. 275
prevent free erosion by the currents as they had been and would
be modified by the new jetty under construction. Thereupon, a
contract was let for the removal of a part of the "Mansfield
jetty," but, in May, 1897, before the new jetty was completed or
the old one removed, all work was suspended.
This suspension in the month of May, 1897, marks the end of the
effort to obtain the desired channel through private enterprise,
and Congress, in May of the following year, by resolution called
upon the Secretary of War to prepare and submit plans for the
deepening of the Pass to at least 20 feet. Six months later, a
board created by the War Department reported in favor of two
jetties, to be supplemented by dredging. It was recommended that
the northerly jetty should be located substantially upon the line
of the one partially constructed by the Arasnas Pass Harbor
Company, and the other some distance southerly from it.
While the subject was thus before Congress, appellant brought
his plan for dealing with the problem to the attention of the
committee, and proposed to enter into a contract to construct and
maintain the desired channel for a much less sum of money than the
estimated cost of the work recommended by the War Department board.
His proposition was given serious attention, and, although it was
rejected, he was assured by members of the congressional committee
that they desired to give his plan a trial, as well they might,
for, if it had proved successful, it would have resulted in a great
saving to the government in dealing with many like situations and
problems.
Before any further work was done, the Arasnas Pass Harbor
Company conveyed to the United States the jetty or breakwater,
which we have seen was constructed as designed by appellant, and
Congress, in 1899, appropriated $60,000 for dredging and improving
the Pass, but with the proviso that the Secretary of War was
authorized
"to
Page 254 U. S. 276
contract for the removal of that portion of the old government
jetty [the Mansfield jetty] in said harbor from the end nearest the
curved jetty"
constructed by the Arasnas Pass Harbor Company, but in such
manner as not to interfere with that jetty. This is a plain
indication of interest on the part of Congress in appellant's
theory or method of dealing with the problem, for he was claiming
that the old jetty constituted an obstruction to the action of the
water, and prevented the jetty which the Harbor Company had built
under his direction from scouring out the desired channel.
That appropriation was expended, and, three years later, in
1902, Congress appropriated $250,000 for continuing the improvement
of the Pass, but again with the proviso
"that the work shall be confined to the completion of the north
jetty, in accordance with the designs and specifications of the
Arasnas Pass Harbor Company, and in the continuance of the work
heretofore carried out on said jetty by said company."
Here again is plainly evidenced the purpose of Congress to give
appellant's theory a full and fair trial, for, it should be noted,
as yet it had never been reduced to actual practice.
Plans and specifications for the contract under this second
appropriation were drawn by the government engineer in charge, and
were by him submitted to the Arasnas Pass Harbor Company, and the
appellant suggested amendments, which were adopted. Among other
things done under this contract was the removal of a considerable
part of the Mansfield jetty, which the appellant had claimed so
affected the action of the currents as to prevent the obtaining of
the desired results from his construction.
Three years later, in 1905, Congress appropriated a further sum
of $100,000, and in 1906, a like amount, for the improvement of the
Pass, and, in each case, the provision was incorporated that the
money was to be applied to
Page 254 U. S. 277
construction "in accordance with the design and specifications
of the Arasnas Pass Harbor Company, and in continuation of the work
heretofore done."
The findings of the Court of Claims are that, in compliance with
the provisions of these various acts, the work of improvement was
continued and completed in 1906, in accordance with the plans and
specifications, as modified by appellant; that, from 1896 to 1906,
the depth and width of the channel were variable and shifting, with
a ruling depth of only six feet of water in 1908, and that the
evidence does not show to the satisfaction of the court that the
so-called Haupt jetty, which was constructed under appellant's
direction, "did produce, or would have produced, a navigable
channel of the necessary or proper depth for navigation
purposes."
It is upon the terms in which the three appropriations were made
in 1902, 1905, and 1906, each for the construction or completion of
the project "in accordance with the design and specifications of
the Arasnas Pass Harbor Company," that the appellant relies, and
from them it is argued that a contract to pay him for the use of
his design and for the impairment of his patent should be derived.
But we not only have the Court of Claims finding that the
experiment of attempting to procure the desired channel by
appellant's method and under his plans, pursued through many years,
and definitely for four years, from 1902 to 1906 at an expense to
the government of $450,000, resulted in failure, but we have the
further action of Congress, next to be described, which clearly
shows the correctness of the court's conclusion.
In March, 1906, as we have seen, the work of improvement
according to the plans as modified by the appellant was completed
without securing the required channel. In the following December, a
board appointed by the War Department to further consider the
Arasnas Pass project recommended that the spacing which Haupt had
left
Page 254 U. S. 278
between the end of his jetty and St. Joseph's Island, for its
influence on the currents, should be closed, and that a parallel
jetty should be built to the south of the Haupt jetty, thus making
the project one of two jetties, instead of the single jetty of
appellant's plan.
In 1907, Congress appropriated $200,000 and authorized contracts
for the additional amount of $290,000 for improving the Pass
"in accordance with the plans submitted in its report of
December 22, 1906, by the board of engineers created by authority
of the act of June 13, 1902."
It will be seen that all reference to appellant's method of
solving the problem disappeared from this act, which adopted the
new plan of solution.
Contracts were made under this appropriation of 1907, and a
second jetty, generally parallel to the Haupt jetty, was commenced
in March, 1908, and completed in 1911. The Court of Claims finds
that, beginning with 1912, coastwise and seagoing vessels have been
going through the Pass, and that, in that year, the port of
"Arasnas Pass" was given the status of a commercial port on a par
with Galveston by the Railway Commission of Texas; that "dredging
was necessarily done in the years 1912 and 1915, inclusive, to
obtain a proper navigable depth of channel in the pass," and that
this construction, as ultimately completed, "did not embody any of
the devices of the plaintiff's [appellant's] letters patent No.
380,569."
It is, of course, essential to recovery by appellant on
quantum meruit that he should prove a contract, express or
implied, on the part of the government to pay him, that his
patented method of construction was used, and what the value of it
was.
Gibbons v. United
States, 8 Wall. 269;
Ball Engineering Co. v.
White & Co, 250 U. S. 46. The
three acts requiring the money appropriated to be used in
accordance with the design and specifications of the Arasnas Pass
Harbor Company, which were prepared by
Page 254 U. S. 279
appellant, implied clearly that Congress intended to give the
experimental construction of appellant a fair trial, and common
honesty would infer a disposition, but not a contract, to pay for
the use of the patented form of construction if it should be found
to be valuable. But, saying as much as it did, the failure of
Congress to say more imports a determination on its part to hold
within its discretion the decision as to the usefulness of
appellant's ideas and as to what, if anything, should be paid for
them. The absence of any reference to appellant or to his patent
and of any words implying a contract to pay him, from the three
acts of Congress in which reference is so distinctly made to the
specifications embodying his ideas, is unmistakable evidence that
Congress deliberately dealt with appellant's theories as still in
the experimental stage, and that it was willing to use the public
money to give them a trial in practice, but that payment for them
was reserved for consideration until their usefulness should be
established, and this, the finding by the Court of Claims shows,
was never done.
For these reasons, to the sufficient finding that the
construction which produced the desired channel did not embody any
of the devices of the appellant's patent, we must add that the
record fails wholly to show anything from which a promise by the
government to pay for the use of such devices can reasonably be
implied, and therefore the judgment of the Court of Claims must be
affirmed.
Being of opinion that our conclusion would not be affected by
any findings to be made on the points asked for in the appellant's
motion to remand for additional findings of fact, that motion is
denied.
Affirmed.