In answer to an advertisement under Rev.Stats. § 3709, claimant
made the lowest bid for furnishing envelopes and wrappers to the
Post Office Department, which was duly accepted.
Held that
a contract was completed with the same force and effect as if a
formal writing had been executed, and bond approved, by the
Department, and that the Postmaster General or his successor had no
discretion to revoke it. P.
249 U. S.
317.
Charges embodied in requests for findings that such a contract
was procured by one without financial standing by imposing on the
Postmaster General
held concluded by the judgment of the
Court of Claims sustaining the contract. P.
249 U. S.
320.
Upon the government's repudiation of such a contract before the
time for performance has arrived, the measure of claimant's damages
is the difference between the contract price and what would have
been the cost of performance.
Id.
This Court will assume that evidence touching the amount of
damages, including the expense necessary to make the contractor
ready (as it was found to be) for performance of its contract, was
duly considered by the Court of Claims. P.
249 U. S.
321.
A contract to furnish and deliver promptly in quantities as
ordered the envelopes and newspaper wrappers that the contractor
may be called upon by the Post Office Department to furnish during
four years
construed as entitling the contractor to supply
all needed by the Department in that period. P.
249 U. S.
322.
Motion to remand to the Court of Claims for additional findings
denied. P.
249 U. S. 323.
51 Ct.Clms. 211 affirmed.
The case is stated in the opinion.
Page 249 U. S. 315
MR. JUSTICE McKENNA delivered the opinion of the Court.
Action brought by appellee, the Purcell Envelope Company, which
we shall designate as the Envelope Company, against the United
States for damages for breach of an express contract. The Court of
Claims rendered judgment for the Envelope Company for the sum of
$185,331.76. The United States appeals.
The findings of the court are quite voluminous, but it is only
necessary to quote from them to the following effect: the Post
Office Department, through the Postmaster General, James A. Gary,
invited by advertisement bids "for furnishing stamped envelopes and
newspaper wrappers in such quantities as may be called for by the
Department during a period of four years beginning on the first day
of October, 1898." In pursuance of the invitation, the Envelope
Company submitted a bid in the manner and time specified in the
advertisements of the Department.
The bid of the Envelope Company was accepted, and the following
order entered:
". . . 2nd. That the contract for furnishing the envelopes
called for by the advertisement and specifications referred to be
awarded to the Purcell Envelope Co., of Holyoke, Mass., as the
lowest bidder for the government standard of paper at the following
prices a thousand, namely: . . ."
The Department, before issuing the order, investigated the
financial responsibility of the Envelope Company and considered it
satisfactory.
April 21, 1898, the Department sent to the Envelope Company a
"contract in quadruplicate," to be executed "at once" and returned
to the Department. It was promptly returned as requested, signed by
the president of the Envelope Company, with the Fidelity &
Deposit Company of Maryland as surety in the sum of $200,000.
Page 249 U. S. 316
April 27, 1898, the Department, by the Third Assistant
Postmaster General, wrote to the Envelope Company as follows:
"Your telegram of today is before me. As the Postmaster General
has not yet signed the contract awarded by the Department to your
company for furnishing stamped envelopes during the coming four
years, but is holding the matter in abeyance, I have to request
that you suspend all action under my letter of the 21st instant
until further orders."
The Envelope Company had, however, already made arrangements and
contracts for the supplying to it of the necessary materials to
fulfill the terms of the contract, and was ready and willing at all
times to fully perform it according to its terms. But neither the
Postmaster General nor any Department or officer of the government
made any call or request upon the Envelope Company to furnish or
deliver the envelopes or wrappers which were the subject matter of
the contract, and the company's plant was kept intact ready for the
performance of the contract, remaining idle.
July 22, 1898, the Department, through Postmaster General Smith,
the immediate successor of Postmaster General Gary, the latter
having gone out of office, revoked and cancelled the contract and
declared it to be null and void. Prior to doing so, the Postmaster
General instituted an investigation through one of his proper
officers into the business and financial standing of the Envelope
Company, and the report thereunder was unfavorable to the
company.
On or about July 22, 1898, the Envelope Company, having received
information that the Postmaster General designed readvertising for
proposals, sought by a bill filed in the Supreme Court of the
District of Columbia to enjoin his action. The bill was dismissed
August 15, 1898. The court, however, was of opinion that a contract
had been executed, but that the Envelope Company had an efficient
remedy at law.
Page 249 U. S. 317
An offer was subsequently made by two other companies to supply
the Post Office Department, upon an emergency contract, stamped
envelopes and wrappers of the kinds and qualities the government
should need. The Department declared that an emergency existed
under § 3709 Rev.Stats., accepted the offer, and entered into a
contract in accordance therewith.
The total cost to the Envelope Company for materials and the
manufacture and delivery of the envelopes and wrappers in
accordance with the terms of its contract would have been
$2,275,224.46. Deducting that sum from the contract price leaves a
difference of $185,331.76, which represents the profit the company
would have made if it had been allowed to perform its contract. For
that sum, judgment was entered.
It will be observed from the recitation of the above facts that
the case presents the propositions: first, was there a completed
contract between the Envelope Company and the United States through
its Postmaster General, and second, if there was such contract,
what is the measure of damages?
For an affirmative answer to the first proposition, the Envelope
Company relies on
Garfielde v. United States, 93 U. S.
242, and on that case the Court of Claims rested its
decision and considered that the case was supported by other cases
which were cited.
The case may be considered as the anticipation of this -- its
prototype. It passed upon a transaction of the Post Office
Department and decided that a proposal in accordance with an
advertisement by that Department and the acceptance by it of the
proposal "created a contract of the same force and effect as if a
formal contract had been written out and signed by the parties."
And for this, it was said, many authorities were cited, but it was
considered so sound as to make unnecessary review of or comment
upon them.
Page 249 U. S. 318
In resistance to the case as conclusive, the government urges
the qualification that
"the Court did not say, or assume to say, that the acceptance of
the proposal in
all [italics counsel's] cases constituted
a contract, but held that it did in the present [that] case,"
and that "there was reason for the conclusion which does not
obtain in the case at bar." We cannot agree, and in answer to the
first qualification it is only necessary to say that the Court
expressed a principle, not, of course, applicable to all cases, but
applicable to like cases, and the present is a like case, identical
in all that makes the principle applicable. And in so determining,
we answer the other objection of the government that there were
features in the law in the
Garfielde case which do not
obtain in the pending case, which constituted, if we understand
counsel, the determination of the law against the act of the
Postmaster General, his duty being merely ministerial. In the
present case, it is insisted his action is not so subordinate, that
he has discretion, and when exercised it is paramount, his action
being "
quasi-judicial," the contract not having been
consummated, and that therefore it was within his power to review
and set aside the decision of his predecessor. We are unable to
concede the fact or the power asserted to be dependent upon it.
There must be a point of time at which discretion is exhausted. The
procedure for the advertising for bids for supplies or services to
the government would else be a mockery -- a procedure, we may say,
that is not permissive, but required (§ 3709, Rev.Stats.). By it,
the government is given the benefit of the competition of the
market and each bidder is given the chance for a bargain. It is a
provision, therefore, in the interest of both government and
bidder, necessarily giving rights to both and placing obligations
on both. And it is not out of place to say that the government
should be animated by a justice as anxious to consider the rights
of the bidder as to insist upon its own.
Page 249 U. S. 319
And, we repeat, there must be some point at which discretion
ceases and obligation takes its place. That point is defined in the
Garfielde case, and that the definition is applicable to
the case at bar is illustrated by the findings of the Court of
Claims. Upon the invitation, in accordance with law, of Postmaster
General Gary, the Envelope Company and eleven others submitted
bids. The Envelope Company was the lowest bidder, and after the
company had been found upon investigation to be financially
responsible, its bid was accepted by entry of a formal order. The
company was then directed by the Department to execute the
necessary contract in quadruplicate, which it did, and returned the
contract to the Department with a surety whose responsibility was
not questioned at any time, nor was other security demanded, as it
might have been. Postmaster General Gary went out of office, and
his successor, either by inducement or upon his own resolution,
revoked the contract and entered into a contract with other
companies.
The record furnishes no justification of such action. There is
no charge of default against the Envelope Company, no charge of
inability to perform its contract, except in a particular which we
shall hereafter mention. There is, it is true, a finding that
Postmaster General Smith caused an investigation to be made of the
financial standing of the Envelope Company and that the report
thereunder was unfavorable to it. This is made a great deal of, and
the fact that the contract was not signed nor the bond of the
Envelope Company approved.
It makes no difference that the contract was not formally signed
or the bond formally approved, as counsel for the government
contends they should have been, both by the terms of the contract
and by a statute of the United States. Act Aug. 13, 1894, c. 282,
28 Stat. 279. Their formal execution, as we have seen, was not
essential to the consummation of the contract. That was
accomplished, as was decided in the
Page 249 U. S. 320
Garfielde case, by the acceptance of the bid of the
Envelope Company and the entry of the order awarding the contract
to it. Therefore, we do not follow with minute attention the
argument of the government in asserting the power of Postmaster
General Smith to review and annul his predecessor's decision and
that directed against the financial standing of the Envelope
Company or the deception the government asserts was practiced on
Postmaster General Gary, which are made the subject of a request
for findings. We may assume that the Court of Claims considered
such charges and all other elements before concluding that the
Envelope Company was entitled to recover. And we pass to the
question of damages.
The Court of Claims decided that the measure of damages was the
difference between the cost to the Envelope Company of materials
and the manufacture and delivery of the envelopes and wrappers in
accordance with the terms of its contract and what it would have
made if it had been allowed to perform the contract. For this the
court cited and relied upon
Roehm v. Horst, 178 U. S.
1. It is there decided that the positive refusal to
perform a contract is a breach of it, though the time for
performance has not arrived, and that liability for the breach at
once occurs. And it is further decided that the measure of damages
is the difference between the contract price and the cost of
performance. The case was replete in its review of prior cases. We
may refer, however, to
United States v.
Speed, 8 Wall. 77,
75
U. S. 85;
United States v. Behan, 110 U.
S. 338;
Hinckley v. Pittsburgh Steel Co.,
121 U. S. 264.
The government does not attack the ruling, but contends that it
was not properly applied by the Court of Claims. The contention is
rested on the following finding:
"Claimant, contemplating making the envelopes under its said
contract on the Wickham envelope machines, entered into
negotiations with Horace J. Wickham whereby he promised
Page 249 U. S. 321
to furnish claimant with a sufficient number of said machines on
which to perform said (envelope) contract and to have some of them
ready before the beginning of the contract term, October 1,
1898."
The government says of the Wickham machine that it made the
envelope in one operation and that there is nothing to show that
the Court of Claims,
"as an incident to the cost of performance of the contract,
considered the cost of the Wickham machine to appellee although
evidence of the same was submitted to it."
And further, "if the court did find this item and did consider
it in arriving at the judgment, appellant is entitled to know
this." Again, the government contends that
"so far as the findings are concerned, it does not appear that
the court allowed a reasonable deduction from the amount of the
judgment by reason of appellee's release from care, trouble, risk
and responsibility attending the performance of the contract."
To the contentions there may be offset the decision of the Court
of Claims. The court in its opinion expressly declares that the
findings showed that the Envelope Company had fulfilled all the
requirements of the Postmaster General and was ready and willing to
furnish the envelopes and wrappers and recognized, we may assume,
as grounds to be considered the elements the government urges, so
far as the court deemed them relevant or as having any probative
strength, and its appreciation of them was obtained after
protracted litigation involving two complete trials. We are not
therefore disposed, on assertions so elusive or disputable of
estimation as those of the government, to reverse or modify the
judgment.
There are other contentions of the government which we may pass
without comment, except one which it submits upon a supplemental
brief. It is addressed to the rule of damages adopted by the Court
of Claims, and urges that it was erroneous, based on the theory, as
it is asserted,
Page 249 U. S. 322
that the Envelope Company
"had a contract which entitled it to furnish all the stamped
envelopes and wrappers of the sizes mentioned in the specification,
which the Post Office Department
should need [italics
counsel's] during the four years contract."
This is denied, and it is said, quoting the contract, that the
Envelope Company was only to "furnish and deliver promptly and in
quantities as ordered," the envelopes and wrappers "that it may be
called upon by the Post Office Department to furnish during the
four years." It is difficult to treat the contention seriously.
There is something surprising in the declaration that a contract to
supply a great department of the government with envelopes and
newspaper wrappers which it might need for a period of four years
at a cost of nearly two and one-half million dollars bore but scant
obligation upon the part of the government, or, to be precise and
in the language of counsel, that the Envelope Company "could not
have forced the giving of orders [by the government] in excess of
fifteen days' supply," and that this was the extent of the
government's obligation. And the further contention is that, the
obligation being thus limited, the damages the Envelope Company was
entitled to were, at most, "the expenses, incurred in getting ready
to perform the contract, and the profits it would have derived from
the manufacture and sale" of such fifteen days' supply that all
else was expectation, and cannot be capitalized by the Envelope
Company and made the basis of profits and the responsibility of the
government. If the contention be more than dialectical, we may
express wonder that it was not given prominence in the Court of
Claims and that in this Court it was reserved for the afterthought
of a supplemental brief. The further answer may be made that the
contract of the Envelope Company was not so dependent as urged, and
that its expectation was substantial is evidenced by the haste of
the Department, after the revocation of the contract
Page 249 U. S. 323
with the company, to declare an emergency in its need and enter
into a contract with other companies.
On January 13th, the government made a motion to remand the case
to the Court of Claims for additional findings. It was denied, but
the right reserved to make such order if we should be so advised.
Our attention is directed to the motion, which it is submitted
should be considered on the merits. Again, considering the motion
and the case as it has been developed by argument of counsel, we
think the motion should not be granted. The judgment of the Court
of Claims is
Affirmed.
MR. JUSTICE McREYNOLDS took no part in the consideration and
decision of this case.