A railroad company, having surveyed a line over public land and
filed map and application for right of way under the Act of March
3, 1875 (which affects public land only), and the land having in
the interim become part of a National Forest, made application,
upon the same map, to the Commissioner of the General Land Office
for permission to construct in the Forest, received such permission
from the Forest Service, to which the matter was referred, amended
its location somewhat so as to lay the right of way, staked 200
feet wide, across a mining claim in the Forest, obtained conveyance
of 100 feet in width from the mining claimants, and constructed and
operated its road. Thereafter, the original application was
approved by the Secretary of the Interior, and thereafter the tract
crossed was thrown open to entry.
Held (construing the Act of 185,
supra, and
the Act of March 3, 1899, relating to rights of way in forest
reservations):
(1) That the right of the railroad to the full 200 feet was
superior to the right of one who held under the mining claim until
the land was thrown open and who then settled, and ultimately
obtained patent, under the Homestead Law, although his homestead
right was initiated before the company amended its map to show the
change of location and before the Secretary approved the
application as thus amended. P.
248 U. S.
53.
(2) That the question whether failure to describe the route in
its charter left the company without power to construct upon it,
and unqualified to receive the grant, was not subject to be raised
by the homesteader. P.
248 U. S.
54.
18 Ariz. 220 affirmed.
The case is stated in the opinion.
Page 248 U. S. 50
MR. JUSTICE McKENNA delivered the opinion of the Court.
Error to review a judgment of affirmance of a judgment rendered
in the Superior Court of Gila County, Arizona, quieting the title
of the Railroad Company to 2.23 acres of land in the N.W. 1/4 of
the S.E. 1/4, Sec. 30, T. 1 N., R. 15 E., Gila County, Arizona.
The trial court made findings of fact which were concurred in by
the Supreme Court. And we see no reason for not accepting them,
notwithstanding plaintiffs in error urge a review of them. They are
as follows:
The railroad, as the successor of the Gila Valley Globe &
Northern Railway Company, acquired its rights, including rights of
way and all other assets. In March, 1906, the latter company
platted a line of railroad from Globe to Miami, Arizona, about nine
miles in length, passing over and across certain public land, and,
November 5, 1908, filed in the local land office its map or profile
of definite location as provided by the Act of Congress of March 3,
1875. Prior to that time, the land covered by the map as well as
the land in dispute was thrown into the Crook National Forest
Reserve. April 16, 1909, written application to the United States
Department of Agriculture, Forest Service, with map of right of way
attached, was made by the railroad to enter and extend its line
across a portion of the forest reserve. The railroad was given
permission on July 6, 1909, to enter the reservation and to locate
and construct its road therein. The map and profile of its road was
approved September 21, 1909, by the Secretary of the Interior in
accordance with the act of Congress.
In April, 1909, the Globe Company commenced the construction of
its road, and completed it in September of that year, and it and
the appellee company have operated trains ever since October, 1909.
Before construction was commenced, to-wit, in November and
December, 1908,
Page 248 U. S. 51
the Globe Company amended its line of survey and changed the
course of its road upon and across the land in dispute and along
its entire length to the extent of 100 feet in width on each side
of the center line of its railroad and constructed its road on the
amended location conforming on the ground to the staked and marked
line.
At the time of the amended location, the land was held by the
Miami Land & Improvement Company, a corporation, as mineral
land, and the Globe Company accepted a deed from it to a right of
way across the land. By executive order, the land in dispute was
restored to the public domain December 22, 1909, on which date
appellant, Cleve Van Dyke, filed upon the same under the homestead
law. He had theretofore accepted it under an option to purchase as
a mineral location from the Miami Improvement Company. On that
date, he went off the land, but immediately returned and
established his residence with a view to homesteading. In due
course, he made final proof, and on February 12, 1912, a patent
without any reservation was issued to him for his homestead.
December 30, 1909, the Globe Company filed its amended map and
profile of its right of way in the local land office, which was
regularly and duly approved March 4, 1911.
Van Dyke attempted to show that he had established residence
upon the land prior to December 22, 1909, the date upon which he
filed his homestead entry. But it is clear that he did not go upon
the land prior to its inclusion in the Forest Reserve. He was upon
the land under the option to purchase mentioned, and he attempted
to show that he was there under a verbal permit from the Forest
Supervisor with the intention of entering the land as a homestead,
and that he made application to the Forestry Department for an
examination and listing thereof under the Act of June 11, 1906;
application, however, was rejected.
Page 248 U. S. 52
That he did not rely upon the settlement prior to December 22,
1909, is clearly shown by his testimony. He said:
"It is a fact that, about midnight on the 22d of December, 1909,
I took up residence in the house testified to. That is, I went off
the ground and back on again at midnight."
December 22d was the first time the land could have been settled
upon without permission from the national government, and this
permission he did not obtain.
Upon these facts the supreme court said certain contentions
arose: (1) it is that of the railroad that its rights were fixed
and established in August and September, 1909, when it completed
the construction of its railroad; (2) opposing, plaintiffs in error
assert that, because the railroad changed its route as located by
its original map and profile approved by the Secretary of the
Interior, it acquired no rights until it filed with the local land
office on December 30, 1909, its amended map of location, which was
too late, Van Dyke having taken the land as a homestead December
22, 1909. And to the contention of the company that, if the land
was public it was not bound to follow the line as shown on its map
and profile, plaintiffs in error reply that the land had ceased to
be public land by being thrown into the National Forest Reserve,
and that the railroad was hence restricted to the specific right of
way shown on its approved map and profile, or, if changed to
another and different route, the consent of the Interior Department
was necessary, and that such permission had not been given, and
hence the railroad acquired no rights at least against plaintiffs
in error. It is conceded, however, that the railroad company was
entitled to a right of way to the extent of 50 feet on each side of
the center of its line of track acquired by deed from the Miami
Land & Improvement Company, in the execution of which deed Van
Dyke "acquiesced." Therefore, as said by the supreme court:
"Fifty feet on each side of
Page 248 U. S. 53
the center line of the track, or one hundred feet of the right
of way, are not involved in this suit, the area in question being
the excess of one hundred feet up to two hundred feet, amounting to
2.23 acres."
We have had occasion to consider the Act of March 3, 1875, c.
152, 18 Stat. 482, and what constituted a definite location of the
right of way under it, and have decided that such event occurs by
the actual construction of the road.
Jamestown & Northern
R. Co. v. Jones, 177 U. S. 125;
Minneapolis, etc., Ry. Co. v. Doughty, 208 U.
S. 251;
Stalker v. Oregon Short Line R. Co,
225 U. S. 142.
It was found by the courts below that the construction of the
railroad was commenced in April, 1909, and completed September,
1909, and that trains have been operated on it ever since. This
satisfies the condition expressed in the cited cases of the
appropriation of a right of way. But it is objected that the land
was not then subject to appropriation, being within a Forest
Reserve. In reply, the Act of Congress of March 3, 1899, c. 427, 30
Stat. 1233, is adduced. It reads as follows:
"That, in the form provided by existing law, the Secretary of
the Interior may file and approve surveys and plats of any right of
way for a wagon road, railroad, or other highway over and across
any forest reservation or reservoir site when in his judgment the
public interests will not be injuriously affected thereby."
Of this act we said, in
Chicago, Milwaukee & St. Paul
Ry. Co. v. United States, 244 U. S. 351,
244 U. S.
357-358, that it commits to the Secretary of the
Interior the question of determining whether the public will be
injuriously affected by the grant of a right of way to a railroad
through a forest reserve, and authorizes him to file and approve
surveys and plats of the right of way. The measure of his
discretion is large, and only through his approval can a right of
way be acquired.
The condition was satisfied in this case. The Globe Company --
to the rights of which defendant in error
Page 248 U. S. 54
succeeded -- in 1906, in preparation for the construction of its
road, platted its road and filed in the local land office its map
and profile of definite location under the Act of 1875, in
November, 1908. Several months prior to the latter date, the land
of the platted line and the land in dispute were thrown into the
Crook National Forest Reserve. In the following year, the railroad
company made application to the Commissioner of the General Land
Office for permission to enter the reserve and to locate and
construct its road thereon. And the application was communicated to
the Department of Agriculture and approved by the Acting District
Forester; the permission was granted and the map and profile of the
road was approved September 21, 1909, by the Secretary of the
Interior pursuant to the Act of Congress of March 3, 1875. The road
was constructed, and, as we have said, completed in September,
1909, and put in operation in October. And these successive steps
were before the date on which Van Dyke attempted to initiate a
homestead right. The discretion of the Secretary of the Interior
was therefore exercised, and we agree with the supreme court that
we cannot infer a rule of the Department which precluded the
granting of permission upon the original map and profile.
Plaintiffs in error contend that the railroad company had no
power to construct a road from Globe to Miami, Arizona, because its
charter failed to designate such a line as within the project for
which it was incorporated. This was made an issue by the pleadings,
and the court found against it. Besides, it is not within the
province of plaintiffs in error to make the objection; it was a
matter for the Secretary of the Interior to determine. And, again,
plaintiffs in error have not such relation to the railroad company
as to complain of the exercise of power outside of its charter.
Judgment affirmed.