The purpose of the Act of February 24, 1905, 33 Stat. 811, is to
provide security for the claims of all persons who furnish labor or
material on public works of the United States; the act, and bonds
given under it, are to be construed liberally to effectuate this
purpose, and the release of sureties through mere technicalities is
not to be encouraged.
S, while conducting his business under supervision of a
creditors' committee, entered into a contract with the United
States for the doing of certain work, and gave bond with surety to
secure claims for labor and materials under the Act of February 24,
1905,
supra. After part performance of the contract, he
and the creditors formed a corporation to take over his affairs,
which, without the consent of the United States or the surety,
received a transfer of all his business and assets, and thereafter,
under the management of S, as president, and the control of the
creditors through the board of directors, continued for a time to
perform the contract.
Held:
(1) That, in view of § 3737, Rev.Stats., the transfer could not
effect an assignment of the contract, but amounted, at most, to a
subletting.
(2) That, as the responsibility of the contractor under the
contract and the actual management of the business were not
changed, nor
Page 244 U. S. 377
the surety prejudiced, the transfer did not operate to discharge
the surety from past or future liability.
(3) That labor and materials furnished in the prosecution of the
work under the contract, after the transfer of the contractor's
business to the corporation, were to be regarded as furnished to
him within the meaning of the Act of February 24, 1905,
supra, as well as to the corporation, and that the latter,
besides, might be deemed the successor of the contractor within the
condition of the bond, binding him "his heirs, successors,"
etc.
Questions of liability to pay interest under a bond given to
secure payment for labor and materials, furnished under a
construction contract with the United States, are determinable by
the law of the state in which the contract and bond were made and
to be performed.
Under the law of Illinois, the liability of a surety on a bond
is extended beyond the penalty by way of interest from the date
when the liability on the bond accrued.
Where claims are all liquidated and amounts are not disputed,
but only liability under the bond, the surety which has not elected
to pay into court is properly chargeable with interest from
commencement of suit upon the aggregate of the claims allowed as
reduced to the penal amount of the bond.
Acts of creditors upon which the surety neither acted nor
relied, which did not affect it, and which are not inconsistent
with a resort to the security of the bond afford no basis for an
equitable estoppel in favor of the surety.
The renting of a plant of cars, track, and equipment actually
used in the construction of public work for the United States is a
furnishing of "materials" within the meaning of the Act of February
24, 1905, and the rent reserved, together with the loading and
freight expenses incident to bringing the plant to and from the
place of use, are liabilities covered by the contractor's bond.
226 F. 653 affirmed.
The case is stated in the opinion.
Page 244 U. S. 378
MR. JUSTICE BRANDEIS delivered the opinion of the court:
This is an action against the Illinois Surety Company on a bond
given by one Schott under Act of Congress, February 24, 1905, 33
Stat. 811, to secure performance of his contract for work on the
Naval Training Station at Chicago. [
Footnote 1] It is brought for the benefit of persons who
furnished labor or materials. he bond provides:
"The condition of the above bond is such that, if the said above
bounden principal, W. H. Schott, his or their heirs, successors,
executors or administrators . . . shall promptly make payments to
all persons supplying him or them labor and materials in the
prosecution of the work provided for in the aforesaid contract,
then this obligation to be void and of no effect, otherwise to
remain in full force and virtue."
The bond was given on August 3, 1908. Schott was then heavily
indebted, and his business was being conducted under the
supervision of a creditors' committee. Later, on the advice of that
committee, the Schott Engineering Company was incorporated to take
over the business, and on January 2, 1909, all the assets were
transferred to it. Schott became president, the members
Page 244 U. S. 379
of the creditors' committee directors. Substantially all the
capital stock was issued to Schott, and all was retained by him
except $36,000 preferred stock, which was later sold, the proceeds
being used to pay debts. Neither the government nor the Surety
Company was advised of the transfer, which left the management and
the conduct of the business unchanged, and the work was proceeded
with continuously from the execution of the bond until January 14,
1910, when both Schott and the company were adjudicated bankrupt.
After a short interruption, the work was resumed by the receiver
under authority of the court, and settlement was made with the
government. Twenty-seven creditors, six of whom furnished labor or
materials prior to January 2, 1909, the rest of whom had claims
arising between that date and the bankruptcy, sought to recover on
the bond.
The district court allowed recovery on five of the claims,
aggregating $15,333.24, which accrued prior to the transfer of the
business to the Schott Engineering Company. The circuit court of
appeals reversed that judgment and allowed the claims of all who
joined in the writ of error to that court -- nineteen, aggregating
$38,121.02 -- but it reduced them
pro rata to make the
aggregate equal the penalty of the bond, $31,047.18. It then
allowed interest on all from the date of the commencement of the
suit. 226 F. 653. The Surety Company appealed to this Court, and
contends:
(1) As to each claim, that it was released from liability by the
transfer of the business to the Schott Engineering Company during
the progress of the work.
(2) As to each claim, that interest should not begin to run
before the date when the amount payable on all claims was
ascertained by the judgment of the circuit court of appeals.
(3) As to certain claims, that the creditors are estopped by
specific acts from enforcing the liability upon the bond.
Page 244 U. S. 380
(4) As to the claim of the United States Equipment Company, that
rental for cars, track, and equipment is not a claim for "labor and
materials" recoverable on bond.
These contentions will be considered in their order.
First: The purpose of the act was to provide security
for the payment of all persons who provide labor or material on
public work. This was done by giving a claim under the bond in lieu
of the lien upon land and buildings customary where property is
owned by private persons. Decisions of this Court have made it
clear that the statute and bonds given under it must be construed
liberally in order to effectuate the purpose of Congress as
declared in the act. In every case which has come before this Court
where labor and materials were actually furnished for and used in
part performance of the work contemplated in the bond, recovery was
allowed if the suit was brought within the period prescribed by the
act. Technical rules otherwise protecting sureties from liability
have never been applied in proceedings under this statute.
[
Footnote 2] As the basis of
recovery is supplying labor and material for the work, he who has
supplied them to a subcontractor may claim under the bond even if
the subcontractor has been fully paid.
Mankin v. United
States, 215 U. S. 533.
Page 244 U. S. 381
If Schott had formally sublet the contract to the Engineering
Company, the Surety Company would clearly be liable. But the
transfer of the business was, at most, a subletting, since, under
Rev.Stats. § 3737, Schott could not assign a contract with the
United States.
It is urged that the bond referring to Schott provides
protection only to those "supplying him or them labor and
materials." But the claims in question were in a very practical
sense furnished him, as well as the Engineering Company. He
remained liable on the contract, and no one else was known to
United States. Furthermore, if the attention is to be directed to
the precise wording of the bond, it should be noted that it refers
to Schott, "his or their heirs, successors, executors or
administrators," and the Engineering Company may properly be deemed
a successor. The argument that the surety's risk ought not to be
increased by holding it liable for the default of strangers to the
original contract is of no greater force in the case of an assignee
than it is in that of the subcontractor. The Surety Company could
protect itself by insisting that the contractor require a bond from
all subcontractors and assignees. The Surety Company was in nowise
prejudiced by the transfer of the business, since the management
remained unchanged, and no reason is shown for applying the rule of
strictissimi juris. Guaranty Co. v. Pressed Brick
Co., 191 U. S. 416,
191 U. S.
426.
Second: The contract and bond were made in Illinois,
and were to be performed there. Questions of liability for interest
must therefore be determined by the law of that state.
Scotland
County v. Hill, 132 U. S. 107,
132 U. S. 117.
Under the law of Illinois, the liability of a surety on a bond is
extended beyond the penalty by way of interest from the date when
the liability on the bond accrued.
Holmes v. Standard Oil
Co., 183 Ill. 70.
See United States v. U.S.
Fidelity Co., 236 U. S. 512,
236 U. S.
530-531. The liability here accrued at least as early as
the commencement of the
Page 244 U. S. 382
suit. The Surety Company contends that the amount each claimant
was to receive was not made definite until it was actually decided
by the court of appeals. But the claims were all for liquidated
amounts, and in no instance was the amount in dispute. The
controversy was merely as to which of the claimants should be
entitled to share in the liability under the bond. The Surety
Company might have paid into court at the commencement of the suit
an amount equal to the penalty of the bond. It did not elect to do
so, and, as the aggregate liability on the claims exceeds the
penalty, it was properly held for an additional amount equal to
interest from the commencement of the suit.
Third: The contention of the Surety Company that
certain of the claimants are estopped from enforcing liability on
the bond rests upon different acts in respect to the several
creditors. As to some, it is because they filed against the estates
in bankruptcy of both Schott and the Engineering Company the whole
of their claims for material delivered in part to each. As to one
creditor, the estoppel is predicated upon the fact that, in answer
to an inquiry, he recommended that the receiver in bankruptcy
complete the contract. As to another creditor, the estoppel is
predicated upon the fact that he filed his claim in bankruptcy
against the Engineering Company while the materials had been
furnished to Schott. As to still another, the contention rests upon
the fact that, having claims against both Schott and the
Engineering Company, he had stated to the Engineering Company a
single account covering all the items, and had accepted part
payment, and furthermore had participated in the activities of the
creditors' committee which supervised the business throughout the
whole period. Such acts lack all the elements of an equitable
estoppel. The Surety Company was not led thereby to do or to omit
to do anything. It did not rely upon, nor was it affected by, any
of the acts it now calls
Page 244 U. S. 383
attention to.
Dickerson v. Colgrove, 100 U.
S. 578,
100 U. S. 580.
There is in fact no inconsistency between the claimants' earlier
acts and their attempt to recover on the bond. The Surety Company's
contention is without merit.
Fourth: The specific objection made to the claim of the
United States Equipment Company, for rental of cars, track, and
equipment used at the Naval Training Station, and the expense of
loading the plant and freight thereon to and from the station, is
also unfounded. The Surety Company contends that this is not
supplying "labor and materials." The equipment was used in the
prosecution of the work. Material was thus supplied, although a
loan serving the purpose, no purchase of it was made. The expense
of loading and freight was properly included with the fixed rental
as recoverable under the bond.
Title Guaranty & Trust Co.
v. Crane Co., 219 U. S. 24,
219 U. S.
34.
Judgment affirmed.
MR. JUSTICE VAN DEVANTER and MR. JUSTICE McREYNOLDS dissent.
[
Footnote 1]
The act, which is entitled, "An Act for the Protection of
Persons Furnishing Materials and Labor for the Construction of
Public Works," provides that a contractor's bond shall include the
obligation to:
"promptly make payments to all persons supplying him or them
with labor and materials in the prosecution of the work provided
for in such contract, and any person, company or corporation who
has furnished labor or materials used in the construction or repair
of any public building or public work, and payment for which has
not been made, shall have the right to intervene and be made a
party to any action instituted by the United States on the bond of
the contractor, and to have their rights and claims adjudicated in
such action and judgment rendered thereon, subject, however, to the
priority of the claim and judgment of the United States."
[
Footnote 2]
Guaranty Co. v. Pressed Brick Co., 191 U.
S. 416;
Hill v. American Surety Co.,
200 U. S. 197;
United States Fidelity Co. v. United States, 209 U.
S. 306;
Mankin v. Ludowici-Celadon Co.,
215 U. S. 535;
Title Guaranty & Trust Co. v. Crane Co., 219 U. S.
24;
United States Fidelity Co. v. Bartlett,
231 U. S. 237;
A. Bryant Co. v. N.Y. Steam Fitting Co., 235 U.
S. 327;
Illinois Surety Co. v. Peeler,
240 U. S. 214.
See also Equitable Surety Co. v. McMillan, 234 U.
S. 448. In
Hardaway v. National Surety Co.,
211 U. S. 552,
where recovery was denied, the "use plaintiffs" had not furnished
materials or labor, but were financiers. In
Texas Cement Co. v.
McCord, 233 U. S. 157, the
questions involved were whether suit was brought within the
statutory period. In
United States Fidelity Co. v. Kenyon,
204 U. S. 349;
United States v. Congress Constr. Co., 222 U.
S. 199;
Title Guaranty & Surety Co. v. United
States, 228 U. S. 567, the
questions raised were as to the jurisdiction of the court.