A government contract for dredging a channel contained a
provision that time was an essential feature, and provided for a
specified amount per day as liquidated damages for delay and not as
a penalty; it also provided that, unless extraordinary and
unforeseen conditions should supervene, the time allowed was
sufficient, and extensions could only be granted on recommendation
of engineer in charge affirmed by Chief of Engineers; a submerged
forest which had not been discovered by the contractor prior to
commencement of the work, although the contract placed the burden
on him to do so, was encountered and so impeded progress as to
cause delay for which the government deducted as liquidated damages
the amount specified in the contract. In a suit to recover that
amount,
held:
The provision in the contract that the time was sufficient
unless extraordinary conditions should supervene does not amount to
a promise for extension if such conditions do supervene.
The extent of promise for an extension under the contract was
confined to what the engineer in charge would grant with the
sanction of the Chief Engineer; nor was the Chief Engineer bound,
in the absence of fraud, to give his sanction to a recommendation
of the engineer in charge for an extension.
For extraordinary conditions to supervene in such a case, they
must come into being after commencement of the work, and not merely
be thereafter discovered to have existed and still to exist.
The provision in the contract for liquidation of damages at $20
per day contains no element of deception or exorbitance, and the
contractor cannot escape the terms agreed upon.
The facts, which involve the construction of a contract with the
United States for excavation of a channel, and the liability of the
contractor for damages for delay in completion, are stated in the
opinion.
Page 241 U. S. 186
MR. JUSTICE HOLMES delivered the opinion of the Court.
This is an appeal from a judgment of the court of claims
dismissing the claimant's petition upon demurrer. On August 15,
1908, the claimant made a contract with Captain Brown of the
Engineers, acting for the United States, to excavate a channel from
Beaufort Inlet to Pamlico Sound, through Core and Adams Creeks, in
conformity with specifications made part of the contract. It was
approved on September 10, and required the work to be begun within
forty-five days after date of notification of approval, September
14, and to be completed within eighteen months. The work not having
been finished on time, $7,320 of the agreed compensation was
withheld as liquidated damages, and $210.50 as additional costs of
superintendence and inspection, $7,530.50 in all, for which sum
this suit is brought.
The petition alleges that, after getting through Core Creek to
and through the headwaters of Adams Creek to a point on tidewater
about five miles from its mouth, where for a mile and a half it
averages more than 1,200 feet wide, and for the next three miles
and a half 2,500 feet, the stumps and roots of a submerged forest
were encountered at about eight feet below the bottom of the water,
which made it impossible to do the work with the ordinary machinery
and in the ordinary way, or to finish the work by the time agreed.
It is alleged that the forest was submerged by some abnormal force
and violence of the elements, and that it could not have been
discovered by the ordinary methods of inspection, and was not
discovered in fact, although the claimant and others and the
government had exercised every known precaution, and had made
exhaustive examinations with the utmost care and skill. The
petition sets up that this was a prevention "by abnormal force and
violence of the elements" within
Page 241 U. S. 187
the contract, and and that the claimant also was entitled to an
allowance of time under a clause in the specifications stating that
the time is considered sufficient "unless extraordinary and
unforeseeable conditions supervene." It also sets up that an
extension of time was recommended by Captain Brown, although
disallowed by the Chief Engineer. Finally, the petition alleges
that it was known by the government officials when the contract was
made that the portion of the canal excavated by the claimant could
not be used to any practical extent for commercial purposes until
adjoining portions of a proposed line were completed, and that the
additional work was not provided for or seriously contemplated
within the time of the claimant's work. It is concluded that,
although the contract purports to provide for liquidated damages,
fixed at $20 a day, yet, in the circumstances, it really imposed a
penalty, and that the government has no right to retain the
sum.
As has been implied already, the contract agreed
"that time shall be considered as an essential feature of this
contract, and that, in case of the failure upon the part of the
party of the second part to complete this contract within the time
as specified and agreed upon, that the party of the first part will
be damaged thereby, and the amount of said damages being difficult,
if not impossible, of definite ascertainment and proof, it is
hereby agreed that the amount of said damages shall be estimated,
agreed upon, liquidated, and fixed in advance, and they are hereby
agreed upon, liquidated, and fixed at the sum of twenty (20)
dollars for each division for each and every day the party of the
second part shall delay in the completion of this contract,"
and the claimant agrees to pay that amount "as liquidated
damages, and not by way of penalty." It is agreed further that the
United States shall have the right to recover all costs of
inspection and superintendence incurred by it during the period of
delay, and that it may
Page 241 U. S. 188
retain all the above-mentioned sums from any moneys falling due
under the contract.
There is a proviso that, if the claimants
"shall, by strikes, epidemics, local or state quarantine
restrictions, or by the abnormal force or violence of the elements,
be actually prevented from completing the work . . . at the time
agreed upon"
without contributory negligence on his part,
"such additional time may, with the prior sanction of the Chief
of Engineers, be allowed him . . . as, in the judgment of the party
of the first part or his successor, shall be just and
reasonable."
As we have intimated, the specifications also state that the
time allowed is considered sufficient "unless extraordinary and
unforeseeable conditions supervene." The claimant further thinks
that he finds some support for his argument in a provision that
"solid rock, large boulders, and compact gravel will not have to
be removed at the prices bid for ordinary excavation. If such
materials should be encountered, their removal, if required by the
engineer, will be done under special agreement, and paid for as
extra work."
On the other hand, the claimant was required to remove all
trees, and
"the channel must be cleared of all snags, logs, roots, stumps,
or wreckage that project into or encroach in any way upon the
cross-section, . . . the cost of same being included in the unit
price bid for excavation."
The claimant invokes a provision that the engineer's decision as
to quality, quantity, and interpretation of the specifications
shall be final, and this ends the statement of his case.
It is hopeless to argue against the provisions that we have
recited, and the further express warning that each bidder "is
expected to examine and decide for himself, as no allowance will be
made should any of it prove to be otherwise than as stated," except
as above recited with regard to solid rock, etc. It is suggested
that the special agreement to be made for the removal of "such
materials"
Page 241 U. S. 189
means materials of similar kind, but the phrase cannot be
stretched to cover roots. The statement in the specifications that
the time is sufficient unless extraordinary conditions supervene
does not promise an extension if such conditions do supervene. The
extent of this promise is found in the words of the contract
providing for the allowance of such additional time as, with the
sanction of the Chief Engineer, the engineer in charge may think
reasonable. Those words tend also to support the contention of the
government that "supervene" means come into being in the course of
the work, as in the case of strikes, epidemics, etc., and not
merely be discovered to have existed and still to exist. We may add
that the averment hazarded that the submergence of the forest was
due to abnormal force of the elements is too obvious an attempt to
pervert the meaning of the proviso as to being actually prevented
by such force from completing the work to require analysis. But it
is enough to say that any extension depended on the sanction of the
Chief of Engineers, and that that sanction was denied. It is said
that the engineer in charge construed the contract differently, as
he recommended an allowance of time. But the ground of the
recommendation does not appear to have been an incorrect
interpretation of the contract; on the contrary, it is alleged that
the liquidated damages were withheld by Captain Brown, and if his
interpretation had been wrong, it is hard to see how it would have
bound his superior on whose sanction the recommendation depended
for effect. The suggestion that it was the duty of the Chief
Engineer to give his sanction in the absence of fraud finds no
support in the words used. The claimant must abide by the words.
Carnegie Steel Co. v. United States, 240 U.
S. 156,
240 U. S.
164.
The allegations by which the claimant attempts to avoid his
contract making time of the essence, that the damages were
difficult cult to prove, and that therefore they should be fixed at
$20 a day are too speculative
Page 241 U. S. 190
to do more than emphasize the necessity for the liquidation.
There is no element of deception or exorbitance, and although the
case seems a hard one, we see no ground upon which the claimant can
escape from the terms to which he has agreed.
United States v.
Bethlehem Steel Co., 205 U. S. 105,
205 U. S.
119.
Judgment affirmed.