An agreement was made by way of compromise more than four months
before the petition was filed to pay from a fund of which the
bankrupt was entitled to the residue all lienable claims, including
claims of one who had waived the right to file liens, but had
subsequently filed claiming the right so to do owing to failure of
bankrupt to fulfill contract, and to whom payments were made from
the fund within four months of the filing of the petition which the
trustee brought suit to recover as preferential.
Held that
the earlier agreement created an equitable lien in favor of all
parties thereto having color of right, and the payments thereunder
did not become preferential because the amounts were not
ascertained and liquidated until within the four-month period.
219 F. 397 affirmed.
The facts, which involve the right of a trustee in bankruptcy to
recover an alleged preferential payment made by the bankrupt within
four months of the filing of the petition under an agreement made
more than four months before the filing, are stated in the
opinion.
Page 241 U. S. 162
MR. JUSTICE HOLMES delivered the opinion of the Court.
This is a suit to recover an alleged preference from the
defendant in error. The circuit court of appeals reversed a
judgment recovered by the plaintiff and ordered judgment for the
defendant. 219 F. 397. This writ of error was taken out before the
passage of the Act of January 28, 1915, c. 22, ยง 4, 38 Stat. 803,
804.
The facts are these: on May 9, 1910, the Warren Construction
Company, the bankrupt, had contracted to do some construction for a
railroad company, receiving monthly payments on account and
agreeing that if at any time there should be evidence of any lien
for which the railroad might become liable, and which was
chargeable to the Warren Company, the railroad might retain an
amount sufficient to indemnify it. Should there prove to be such a
claim after the payments were made, the Warren Company agreed to
refund all moneys the railroad might be compelled to pay in
discharging any lien made obligatory in consequence of the Warren
Company's default. The Warren Company gave a bond with sureties for
the performance of this contract. Later it made a
Page 241 U. S. 163
written subcontract with the Root Manufacturing Company for
materials, in which the Root Company in the fullest terms renounced
all lien on its own behalf, and contracted that all under it should
do the same. Monthly payments were to be made on account, and final
payment within forty days after the contract was "fulfilled."
In 1911, the Root Company notified the railroad that it was not
being paid, and that it would not furnish more material unless the
railroad would see that it was paid. The railroad gave the
assurance, and the Root Company continued to furnish the materials
called for by its contract. Seemingly the payments continued to be
unsatisfactory, and on November 18, 1911, after the Root Company
had performed its contract, there was unpaid $12,895.34. On
November 25, 1911, the Root Company filed statutory notices of its
intention to hold a lien upon the railroad's property for the
amount then due. On January 12, 1912, after conferences of all
parties concerned, a contract was made between the railroad, the
Warren Company, and its sureties reciting controversy as to whether
the Warren Company's contract had been performed, the filing of
claims for liens and attachment suits for more than the sum
admitted by the railroad to be due, and the railroad's assertion of
its right against the surety companies. This contract fixed $42,000
as a sum to be paid by the railroad in full settlement of the
mutual claims between it and the Warren Company, and provided that,
with $20,000 to be furnished by the surety companies, the sum
should be put into the hands of named trustees, "to be used in
paying all lienable claims" growing out of the construction
contract. If the fund was not sufficient to pay lienable claims in
full, the surety companies were to furnish the additional money
necessary. After all lienable claims were paid, the balance, if
any, of the fund was to be paid first to reimburse the surety
companies for their contribution,
Page 241 U. S. 164
and after that to the Warren Company, subject to such
attachments as might be filed against the sum.
On April 10, 1912, a written contract was made between the
railroad, the sureties, the Warren Company, and the Root Company,
which recited the claim of the Root Company and that the railroad
had money in its hands, held back under its contract with the
Warren Company, for the purpose of protecting the road against
liens, and agreed that $6,447.67 should be paid to the Root Company
by way of compromise, that the Root Company should assign its claim
to the trustee under the former instrument, surrendering to the
Warren Company notes for 60 percent of its claim, and that the
trustee should reassign to the Root Company the unpaid portion of
its claim when attachments against the fund had been disposed of.
The payment was made the same day, and the Root Company executed a
release, as agreed. The sum was a larger percentage than will be
received by the unsecured creditors of the Warren Company, but a
smaller one than that received by any other subcontractors with a
lien. The petition in bankruptcy was filed on July 18, 1912, and
the above payment was a preference if it stood as a payment to an
unsecured creditor in the circumstances on the date when it was
made.
The circuit court of appeals held that the instrument of January
12 created an equitable lien that justified the payment, although
it was of opinion that the lien asserted by the Root Company could
not have been enforced. The plaintiff in error contends that the
provision in favor of "lienable claims" was confined to those that
were secured by a valid lien. We express no opinion as to whether
the lien of the Root Company, asserted against the property of the
railroad, could have been defeated by its contract with the Warren
Company notwithstanding the Warren Company's default. It is enough
that we agree with the ultimate view of the circuit court of
Page 241 U. S. 165
appeals. The agreement of January 12 was intended, for practical
purposes, to clear the railroad property from claims. It
contemplated possible controversies, as it provided for costs, but
it did not require that every disputed lien should be fought out to
the end. It was understood by the parties to extend to the
compromise of claims that stood upon debatable ground, as was shown
by the agreement under which the payment was made. It set aside a
specific fund in a third hand to that end. All the parties acted in
good faith. The $42,000 credited to the Warren Company as retained
by the railroad was nearly twice what the railroad admitted to be
due, apart from the compromise by which it secured the application
of that sum to clearing its land. We are of opinion that there is
no reasonable doubt that all parties were justified in the course
adopted, that the instrument of January 12 created an equitable
lien in favor of all alleged liens which the parties should deem to
have color of right, and that, the fund being thus appropriated and
set aside, it does not matter that the formal ascertainment of the
specific beneficiary was made within four months of the bankruptcy
proceedings. It was well understood before. The Root Company took
part in the preliminary discussions, and there can be no doubt that
it was expected by all on January 12 that its claim, however
disputed, would have to be dealt with when the fund came to be paid
out.
Decree affirmed.