A contract to produce a result does not bring the means employed
to provide it into the contract.
United States v. O'Brien,
220 U. S. 321. In
this case, a contractor was not allowed the expense of erecting
temporary dams because the government engineer suggested that it be
placed in a certain location that proved impracticable,
necessitating relocation and rebuilding, as the contract only
called for the location of the permanent structure by the
engineer.
An extension of time requested by claimant, without any
suggestion that it was made necessary by fault of the government or
by the violence of the elements,
held, in view of the
warning given on granting the extension, not to absolve claimant
from the extra expenses specified in the contract in case such
extension were allowed.
Page 239 U. S. 345
A government contractor in this case
held not to be
entitled to extra compensation by reason of advanced prices in
labor and materials due to outbreak of war, it appearing that the
increased expense was not due to any breach on the part of the
United States.
49 Ct.Cl. 73 reversed.
The facts, which involve the construction of, and the amounts
due on, contracts for public works with the United States are
stated in the opinion.
Page 239 U. S. 346
MR. JUSTICE HOLMES delivered the opinion of the Court.
This is a claim for extra expenses incurred in performing a
contract to build a dam and certain accessories on the Yamhill
River, Oregon. The contract was made on March 11, 1898, and
required the claimants to begin work as prescribed by paragraph 41
of the specifications, to complete the keeper's dwelling, etc.,
within sixty days from notification, and the whole work before
December 31, 1898. Paragraph 41 of the specifications stated that
the sites for the construction had not yet been purchased, and that
no work would be begun until they were secured. It then provided
that, within ten days after notification that the sites had been
secured and the contract had been approved, the contractor
"must proceed with the work in a vigorous manner; he must
complete the keeper's dwelling, woodshed, walks, fences, etc.,
within sixty days from date of notification, and the whole contract
on or before December 31, 1898."
It added that, because of the spring rise of the Willamette,
etc., it was probable that work on the lock and dam could not be
begun before June, at the earliest, and that the date of completion
had been set because it was desired that all work should be
finished during one low water season -- the meaning of which was
known by the claimants. Authority to purchase was asked by
telegraph on March 10 and granted on March 15. The abstract of
title and deeds were sent to the Chief of Engineers on April 9 and
14, and the contractors, who had given notice of their readiness to
begin, were told on April 9 that the deeds had been sent on. On
April 29, a telegram was received showing encumbrances to be
removed before the deeds were accepted. On May 13, the attorney for
the United States approved the title. On May 12, the contractors
began work on the keeper's dwelling, etc., and on June 14, were
given the notification to proceed.
Page 239 U. S. 347
Before June 14, 1898, considerable work had been done, material
had been assembled, and labor employed. The war with Spain began on
April 21, 1898, raising the price of labor and materials. The
increased cost is found, but it is found also that this increase
was not shown to be due to any breach of contract by the United
States, and that the claimants did not have room and facilities for
storing large consignments of materials. The claimants, however,
insist upon this item being allowed, and make it the ground of
their cross-appeal.
In 1899, after a lock wall had been built at right angles with
the line of the wing dam and parallel to the line of the stream, it
became necessary to divert the water from the line of the wing dam
in order that the latter might be built. This had to be done by
sending the water through the lock chamber, and to that end it was
necessary to build a temporary dam. The claimants had no civil
engineer, although they commanded some experience. They asked the
local engineer in charge for the United States where the temporary
dam should be placed. He indicated a site near the head of the
lock, where the river was narrow, as the only suitable place, and
the claimants started upon the dam in June. The upstream end of the
lock chamber was closed with a lift-wall, and to turn the water
through the chamber, it had to be raised 16 feet. The bottom of the
river was inclined to disintegrate, and when the water was raised
to 12 feet, the dam broke. Two more attempts were made with the
same result. Early in 1900, the claimants applied to the local
engineer for leave to change the place and to cut a hole through
the lift-wall, which was granted, and the dam was built. The bottom
of the river at the new site was similar to that at the old, and it
would not have been possible to construct the dam there without the
relief afforded by the hole. The Court of Claims allowed the cost
of the last two temporary dams, and the United States appeals.
Page 239 U. S. 348
The specifications provided that, if the time for performance
should be extended, all expenses for inspection and superintendence
should be deducted. The claimants requested an extension of time,
not suggesting violence of the elements, contemplated in the
contract as a ground, or fault of the United States. The extension
was granted with a warning that it would not absolve them from the
above expenses. The Court of Claims allowed the claimants the
expenses accrued during the time of building the second and third
temporary dams, from which allowance also the United States
appeals.
Taking up first the allowance for the unsuccessful temporary
dams and charges for superintendence during the time consumed in
constructing them, we are of opinion that the United States is
entitled to prevail in its appeal. The contract was silent as to
them, and did not embrace them. A contract to produce a result does
not bring the means employed to provide it into the contract.
Bacon v. Parker, 137 Mass. 309, 311;
United States v.
O'Brien, 220 U. S. 321,
220 U. S. 327.
They remain under the control of the contractors alone. The
claimants rely upon specification 40: "The lines and levels for
this work will be established on the ground by the engineers, and
the contractor must conform and keep thereto." But this refers to
the work, the permanent structure, not to the transitory
instrumentality used in building it. While the engineer, in answer
to the claimants, pointed out a place for the temporary dam, it
does not appear to have been ordered to be placed there. Moreover,
the site seems to have been as good as any other, the final success
having been achieved by cutting a hole in the lift-wall of the lock
chamber, not by the change of place. There is nothing to show that
the claimants could not have left this opening, or have obtained
leave to make it earlier. Leave was granted as soon as asked. The
mode of constructing the temporary dam was wholly the claimants'
affair.
Page 239 U. S. 349
Upon the cross-appeal, also, we are of opinion that the
government is in the right. If it had attempted to hold the
claimants to the time originally mentioned in the contract, the
question might be different, but we see no ground for a claim on
their part to hold the United States liable for delay.
Specification 41, the substance of which has been stated, is
inconsistent with the implication of an undertaking that the
claimants shall be notified to begin within any particular time.
The findings hardly warrant the statement in the opinion that the
delay from May 13 to June 14 was chargeable to the defendant's
neglect. It simply is left unexplained. The notice was given in
time to begin work on the lock and dam as early as was contemplated
by specification 41. But further, as is pointed out by the court
below, the prices had advanced before the supposed neglect began,
not to speak of the finding that the claimants had not the
facilities to accumulate material, even if they had been notified
at an earlier date.
Judgment reversed.
Petition dismissed.
MR. JUSTICE McREYNOLDS took no part in the consideration or
decision of these cases.