A letter from the government engineer in charge to a contractor,
who had, under written contract with the United States, agreed to
furnish a specified amount of material at a specified price, that a
larger amount of material would probably be required,
held
in this case not to be a contract for the additional amount or a
modification of the original contract. As a general rule, specific
or individual marks and figures control generic ones, and there is
an analogy between the control of specific figures over estimates
and that of monument over distances.
Brawley v. United
States, 96 U. S. 168.
Smoot v. United States, 48 Ct.Cl. 427, affirmed.
The facts, which involve a claim for profits on a contract for
sand with the United States for the Washington City Filtration
Plant which the United States refused to receive, are stated in the
opinion.
Page 237 U. S. 39
MR. JUSTICE HOLMES delivered the opinion of the Court.
This is a claim for the profits that would have been realized on
sand that the claimant alleges to have been contracted for by the
United States, but that the United States refused to receive, and
for the cost of additional plant alleged to have been provided for
the purpose of furnishing the sand. The Court of Claims rejected
the claim. 48 Ct.Cl. 427. The facts are as follows:
By a contract approved on April 20, 1903, the claimant undertook
to furnish for the Washington filtration plant 140,200 cubic yards,
more or less, of filter sand, to be deposited in twenty-nine filter
beds at $2.65 per yard. The contract and specifications showed
explicitly that the quantities mentioned were approximate only, and
in October, 1904, there was a discussion in the claimant's presence
as to the probabilities of an increase over the 140,200 yards to
meet shrinkage, which had not been taken into account. The delivery
began in August, 1904, but the claimant's progress was not
satisfactory to the government engineers. By January 3, 1905, 15 of
the
Page 237 U. S. 40
29 beds were completed and the engineer in charge wrote to the
claimant directing him to complete the deliveries in the 15 beds by
placing there before May 15, 70,000 yards in addition to 20,936
yards then in place. The claimant replied, holding out prospects of
performance, and saying that he had another plant under way. But on
February 17, the total sand in place was 28,231 cubic yards.
On that date, the engineer in charge wrote to the claimant
saying that he had "laid down a general program of work of be done
during each of the months from now on," with the following
particulars among others:
February and March . . . filter sand, complete
beds 17, 18, 21, 22 . . . . . . . . . . . . . . . . . 19,000
cubic yards
April . . . filter sand, complete 15, 16, 20, about . . 18,000
cubic yards
May . . . filter sand, complete 3, 4, 5, begin 1. . . . 21,000
cubic yards
June . . . filter sand, complete 1, 2, 9, 14. . . . . . 21,000
cubic yards
July . . . filter sand, complete 7, 8, 13, begin 12 . . 21,000
cubic yards
August . . . filter sand, complete 10, 11, 12, 6. . . . 21,000
cubic yards
September . . . filter sand, complete 25, 26, 27. . . . 18,000
cubic yards
October . . . filter sand, complete 28, 29. . . . . . . 12,000
cubic yards
"In the program outlined above, the quantity of sand going into
each bed has been assumed as 6,000 cubic yards. The depth of sand
varies for the different beds, but 6,000 yards is about the
average. Three and one-half beds have been indicated as a month's
work. In some cases, 3 1/2 beds will require more than 21,000 cubic
yards of sand, while in others they will require less. In any case,
the yardage is the item to which especial attention must be paid,
and this should in all cases be equal to that indicated in the
program. . . . You are required to take notice that the quantities
of work, and, unless otherwise ordered, the locations of the same
above scheduled for the several months will be rigorously exacted
as a minimum, and any failure on your part to perform in any month
the quantity of work stipulated for that month
Page 237 U. S. 41
will be considered by me as sufficient cause for the exercise of
several stringent rights -- to go elsewhere, to annul the contract,
etc."
This letter is relied upon by the claimant as a contract making
definite the amount that was stated only approximately by the
original one. It called for 151,000 yards in addition to the 28,231
yards in place, or, in all, 179,231, as against the 140,200, more
or less, originally mentioned. The actual amount needed after
allowing for shrinkage ultimately was fixed by the engineers at
about 157,000 cubic yards, but the claimant was not notified until
May 29, when he immediately entered a protest. He actually supplied
157,725 yards. The claim is for the net profit upon the 21,506
yards that would have been furnished had the figures of the letter
been exact. As to the duplicate plant, it is found that it was
erected to provide for such increased deliveries per month as were
necessary under the claimant's contract. There is no justification
in the finding for the attempt to attribute the second plant to the
letter of February 17, and therefore so much of the claim may be
dismissed. It is not necessary to consider whether the claimant
would fall under the general rule that, in contracts for sale and
delivery, the purchaser is not concerned with the steps that his
vendor may take in order to enable himself to perform.
United
States v. O'Brien, 220 U. S. 321,
220 U. S. 327;
Bacon v. Parker, 137 Mass. 309, 311; or rather under
Parish v. United States, 100 U. S. 500. We
also pass the question whether complete indemnity is not embraced
in the claim for profits.
Noble v. Ames Mfg. Co., 112
Mass. 492.
The appellant admits that neither claim can be maintained unless
the letter quoted bound the United States as an unqualified
contract. We agree with the Court of Claims that it neither
purported to modify the formal agreement originally made nor had
that or any effect upon it. The letter was a spur to a tardy
contractor and
Page 237 U. S. 42
a sketch of what was expected, but it said nothing to indicate
that the engineer in charge was attempting to affect the agreement
made by his superior, if he could have done so, or if,
notwithstanding the reasons given by the Court of Claims, the
claimant could recover for anything but the work actually done in
any event. The obviously dominant measure of the sand to be
furnished was what was needed for the filters, and the figures in
the letter on their face were the engineer's estimate of what would
be needed, not an order for those amounts whether needed or not.
Brawley v. United States, 96 U. S.
168. In that case, Mr. Justice Bradley refers to the
control of monuments over distances and estimates of quantity, as
an analogy. In general, specific or individual marks prevail over
generic ones.
Praesentia corporis tollit errorem nominis.
Watts v. Camors, 115 U. S. 353.
United States v. Harvey Steel Co., 196 U.
S. 310,
196 U. S. 318.
In
Parish v. United States, supra, the contract to furnish
the ice required at certain points named, for armies that were in
the field, manifestly referred to no certain objective standard,
but could be made definite only by orders. Here, no one could have
supposed that the United States undertook to purchase more than was
needed for its plant, and what was needed only was roughly
estimated in round numbers by the engineer, to let the dilatory
claimant know what he must be ready to do.
Judgment affirmed.
MR. JUSTICE McREYNOLDS took no part in the consideration or
decision of this case.