Where the contract contains a provision for a method of
annulment and liquidated damage in case of a breach by failure to
commence work and the government avails of that provision, it is
only entitled to the liquidated damages and cannot recover damages
for difference in cost on reletting the contract under a provision
for failure to complete or abandonment after commencing the work.
United States v. O'Brien, 220 U.
S. 321, distinguished.
The benefit and burden of a provision in a government contract
giving a right to annul in consequence of a breach by failure to
commence work must hang together, and the government cannot avail
of the former without accepting the latter.
195 F. 68 reversed.
The facts, which involve the liability of a contractor and its
surety under a contract with the government for excavation work,
are stated in the opinion.
Page 234 U. S. 274
MR. JUSTICE LURTON delivered the opinion of the Court.
This was an action by the United States against the Stone, Sand
& Gravel Company, a corporation, hereinafter styled the
contractor, and its surety, the American Surety Company of New
York, to recover the excess cost of completion of a certain
contract for excavating 7,500,000 cubic yards of earth within
certain designated localities in the work of improving the harbor
of Vicksburg, Mississippi. For this work the United States agreed
to pay 8.49 cents per cubic yard as the work progressed, and the
contractor agreed to begin active work on or before December 5,
1899, with sufficient force and plant for an output of not less
than 260,000 cubic yards per month, to be increased on or before
January 5, 1900, to a plant adequate for an output of 330,000 cubic
yards per month. Subsequently, upon application of the contractor,
the time for beginning was extended to January 24, 1900. While
by
Page 234 U. S. 275
January 24th the contractor had made large expenditures in
preparing to commence work, it had not on that day assembled the
necessary force or plant. For this reason, the Chief of Engineers
on the following day confirmed a prior anticipatory recommendation
of the engineer in charge that the contract should be annulled. An
application for an extension of time was denied by the Secretary of
War, and on March 7, 1900, formal notice was given to the
contractor, as required by the contract, that it had failed to
prosecute the work of excavation, etc., "in accordance with
specifications and requirements . . . and the said contract is
hereby annulled." The work was relet at a price of 12.4 cents per
cubic yard, making an excess cost of $228,201.91, and an action was
brought and judgment had against the contractor for that sum, minus
a credit of $6,206.69, on account of certain voluntary work of an
experimental character, which sum had been retained by the United
States. There was also judgment against the surety company for
$75,000, the full penalty of the bond.
The only breach of contract alleged was the failure to begin
active operations on the day stipulated with a plant and force
adequate to produce the monthly output required. The breach is
confessed, but the error insisted upon here is that the contract,
for such a breach, limits the measure of recovery to liquidated
damages -- namely, a forfeiture of all money or retained
percentages due or to become due under the contract, and that the
court below erred in allowing as damages the excess cost of the
work under the reletting.
The clauses of the contract which give rise to this contention
occur in the standard form of contract used by the War Department,
known as Form 19, and are the same clauses construed by this Court
in
United States v. O'Brien, 220 U.
S. 321. The clauses involved for purposes of reference
may be described as clauses A and B. In clause A,
Page 234 U. S. 276
it is expressly provided that, if the contractor
"fail to commence with the performance of the work on the day
specified herein, or shall, in the judgment of the engineer in
charge, fail to prosecute faithfully and diligently the work in
accordance with the specifications and requirements of this
contract, then, in either case . . . , the engineer in charge shall
have power, with the sanction of the Chief of Engineers, to annul
this contract by giving notice in writing to that effect . . . and,
upon the giving of such notice, all money or reserved percentage
due or to become due . . . by reason of this contract shall be and
become forfeited to the United States. . . ."
The engineer in charge is thereupon authorized, if an immediate
performance of the work "be, in his opinion, required by the public
exigency, to proceed to provide for the same . . . " as prescribed
in ยง 3709, Revised Statutes.
Following clause A are three other clauses dealing with changes
in the work, cost of extra work, and liabilities for labor and
material furnished. Then comes B, which reads as follows:
"It is further understood and agreed that, in case of failure on
the part of the party of the second part to complete this contract
as specified and agreed upon, that all sums due and percentages
retained shall thereby be forfeited to the United States, and that
the said United States shall also have the right to recover any or
all damages due to such failure in excess of the sums so forfeited,
and also to recover from the party of the second part, as part of
said damages, whatever sums may be expended by the party of the
first part in completing the said contract, in excess of the price
herein stipulated to be paid to the party of the second part for
completing the same."
That there was no abandonment of the contract by the plaintiffs
in error is too plain to need discussion. Large expenditures were
made to get ready, and further extensions
Page 234 U. S. 277
of time were sought both before and after notice of annulment.
The explanation of the failure to get ready lies in the obvious
fact that the contract was larger than the financial capacity of
the contractor, and the United States was plainly within its
contract right in putting it off the job and in reletting the
work.
What is the measure of recovery against the contractor where the
government "annuls" the contract for failure to commence the work
upon a stipulated day? The right to "annul" -- that is, to prohibit
the contractor from going on under the contract -- is plainly
conferred in two distinct cases by clause A, first, when the
contractor fails to begin upon the day stipulated, and second when,
having commenced the work, the contractor fails, "in the judgment
of the engineer in charge, to prosecute the work faithfully and
diligently." In either case, the same section specifically declares
that, upon the giving of the notice of annulment, "all money or
reserved percentages due or to become due to the contractor . . .
shall be and become forfeited to the United States."
It is therefore obvious that, if the right to annul this
contract depends upon clause A, the measure of damages recoverable
in this action is limited by that clause to the forfeiture of all
moneys or retained percentages due or to become due under the
contract.
United States v. O'Brien, supra. This is plainly
conceded in the brief of the Solicitor General.
To escape confession of error in the judgment below, insofar as
the United States was permitted to recover the excess cost of
reletting the job, it has been argued that the right to annul the
contract did not arise out of clause A, but was "a right inherent"
in this and every other contract when time is of the essence, and
that, when there was, as in this case, a breach of an express
agreement to begin the work upon a certain day, the right to annul
was complete, and, upon annulment, the right to recover all actual
damages followed. Of course, this so-called "inherent right" to
annul a contract, with the consequent right to
Page 234 U. S. 278
recover all actual damages as for a complete breach, are rights
supposed to arise not out of any express agreement, but out of the
common law. But the assumption that, aside from clause A, an
agreement to begin such a work on a particular day would be such a
vital term of the contract as to justify the other party in an
immediate annulment if the work was not so begun is seriously
challenged. The vital character of time to the contract would
depend upon its nature and particular circumstances. These might be
such that time would not be of the essence of the contract at all.
Any resort to the contract here involved as making time the essence
of the agreement must include clause A, which expressly determines
the consequences. Such an appeal to the contract would naturally
result detrimentally to the argument here made, since the contract,
while making time vital, provides also for the consequence of a
breach in that respect. The benefit and the burden of clause A must
hang together.
But we need not deal with the consequences as if clause A had
been omitted. The right might have been inherent, or not so vital
as to justify the rigor of annulment. Both parties elected to deal
with the matter by express stipulation, and that should be and is
the end of it. In such a situation, there would be no justice in
straining the contract for a construction which would limit its
application to cases where the right of annulment would not exist
without it. This contract was prepared in advance of the bidding by
the United States. The bidder was required to bid with strict
reference to its terms. One term was that the work should begin
with a plant and force of definite capacity on or before a
particular day. Another was that, if this term was not complied
with, the United States might annul the contract, and that, as a
consequence
Page 234 U. S. 279
of such annulment, all money earned under it should be
forfeited. This forfeiture is not made dependent upon the existence
of any actual damage. Thus, damages were, by stipulation,
liquidated. That such damages may be in this instance inadequate
may be true, but the fact affords no ground for frittering away the
agreement by fanciful distinctions which never entered the head of
either party to it.
The plain purpose was to obtain for the United States the right
to take the contract from a bidder who should break his agreement
at its threshold and let the work to another, possibly for a better
price. At any rate, the right to annul for a breach in respect of
the time of beginning was a valuable right, and for it the
government stipulated and liquidated the damages in the event of
its exercise. The contractor would not only lose his contract, but
also would forfeit everything due him. The agreement settled the
right and all the consequences of its exercise.
There is nothing in the case of
United States v. O'Brien,
supra, which would justify the limitation that the United
States would now have us place upon this plain provision of the
contract. The contract in that case was a dredging contract. The
work was to begin on a day named and be completed on another. The
contract was according to Form 19, and included the two clauses, A
and B, above set out. The work was begun on time. The first member
of clause A was therefore eliminated from any consideration. The
dredging did not progress to the satisfaction of the engineer in
charge, who elected to stop the contractor from going on, when,
confessedly, time enough remained to complete the work within
contract time. The United States, under these circumstances, sought
to recover the excess cost of completing the work, but this Court
held that such excess cost could only be recovered under clause B
for failure to complete according to the terms of the agreement.
There had been no breach of the agreement,
Page 234 U. S. 280
as time remained to finish the work had the contractor not been
prohibited from going on because the engineer in charge was not
satisfied with the progress of the job. But the right to annul for
the later reason was a right conferred by clause A, with the
damages limited as therein provided. The United States was
precluded from the rule of damages prescribed by clause B, and,
being forced to justify under clause A, was held bound by the
limitation of that clause.
The right to annul is expressly conferred by clause A for a
failure to begin on the stipulated day. The United States resorted
to that clause for its authority, and pursued the procedure therein
pointed out. It is plainly bound by the limitation of damages
therein prescribed.
For the error in not so confining the recovery, the judgment
is reversed, and a new trial awarded.