The averments in the declaration, when taken together,
held sufficient to allow proof of negligence on the part
of one defendant, although one specific charge related exclusively
to the other defendant as to whom the case was dismissed.
A modification of the requested charge so as to make it conform
to the facts of the case,
held in this case not to have
been error, the jury having been properly instructed by the court
on the subject of contributory negligence.
A variance between proof and declaration should be called to
the
Page 228 U. S. 195
attention of the trial court when the declaration can be met by
an immediate amendment.
A contractor erecting a building arranged with another and
independent contractor who was putting in the elevator to use and
control the elevator and an operator therefor before it was turned
over to the owner; he also arranged to allow his own subcontractor
painting the elevator shaft to use the elevator and to signal when
and where the elevator was to stop to let the employees off and
take them on.
Held that the contractor was the sole
master, and was responsible for damages sustained by an employee of
the subcontractor resulting from negligence of the operator in
failing to respond to signals properly given by such employee.
35 App.D.C. 595 affirmed.
The facts, which involve the liability of a contractor for
personal injuries caused by negligence in operating an elevator,
are stated in the opinion.
Page 228 U. S. 197
MR. JUSTICE HUGHES delivered the opinion of the Court.
This action was brought by Wilson A. McCloskey, the defendant in
error, to recover damages for personal injuries caused by alleged
negligence in the operation of an
Page 228 U. S. 198
elevator in the Hibbs Building in this District. At the time of
the accident, McCloskey, who will be called the plaintiff, was
engaged in painting the elevator shaft, and for this purpose was
riding on top of the elevator. The action was brought against the
Otis Elevator Company and the plaintiff in error, George A. Fuller
Company. Without objection, a verdict was directed in favor of the
Otis Elevator Company, but the case against the George A. Fuller
Company was submitted to the jury, who found a verdict in favor of
the plaintiff. The judgment on this verdict was affirmed by the
Court of Appeals of the District, and the case comes here on writ
of error. 35 App.D.C. 595.
The facts appearing upon the trial are succinctly stated in the
opinion of the court below, in which the George A. Fuller Company
is described as the defendant, as follows:
"The defendant company contracted with William B. Hibbs to erect
for him an office building on 15th Street in this city. The work
was to be completed by a time certain. This contract did not
include the installation of an elevator. That work was provided for
in a contract between Hibbs and the Otis Elevator Company. The
elevator company installed its elevator long before the completion
of the building. This elevator, down to the time of the injury to
the plaintiff, had not been turned over to the owner of the
building, but was operated by an employee of the Otis Company, who
was paid and generally controlled by that company. After its
installation, the defendant company entered into an arrangement
with the elevator company by which it became entitled to use this
elevator in the prosecution of its work, paying to the elevator
company $3 per day, which was to cover the wages of the caretaker
or operator aforesaid, the Otis Company reserving the primary right
to use the elevator. Under this arrangement, the defendant
Page 228 U. S. 199
company was to have no control over the elevator operator other
than to notify him when to start and when to stop his machine."
"The defendant company entered into a subcontract with the
Robert E. Mackay Company, of New York, for the painting required by
its contract with Mr. Hibbs. The plaintiff was an employee of the
Mackay Company. The elevator shaft was included in this
subcontract. To paint this, it was, of course, necessary that some
means be provided whereby workmen could ascend and descend the
shaft. Therefore, the Mackay Company entered into an agreement with
the defendant company by which the defendant company agreed to
furnish the Mackay Company, for use in painting said shaft,
elevator, power, and operator at any time that the elevator company
or the defendant company did not want them. Nothing whatever was
said about the arrangement between the elevator company and the
defendant company, the agreement between the Mackay and the
defendant company proceeding upon the theory that the equipment and
elevator were under the control of the defendant company. The
Mackay Company was not to have, and in fact did not have, any
control over the operator other than to direct him when to start
and when to stop his elevator while thus temporarily used as a
movable staging."
"Upon the day of the accident, plaintiff and another workman
were on the roof of the elevator touching up the walls of the
shaft. They had worked down until the floor of the car was on a
level with the first floor of the building. To finish the walls of
the shaft between the first and second floors of the building, the
space then occupied by the body of the car, it became necessary to
get under the car. To do this, it was necessary for the painters to
be taken to the next or second floor landing. The plaintiff was
standing on the rim or ledge around the top of the car and facing
the center of the car. He had
Page 228 U. S. 200
a paint box and brush in his hands. The other painter was on
another side of the top, with his back to the plaintiff. This rim
or ledge was about six and one-half inches wide. Plaintiff called
to the elevator operator to take him and the other painter up to
the second floor and let them off there. There was evidence before
the jury that, when the car had reached a point where plaintiff had
directed that it be stopped, the car paused and suddenly started
again, throwing plaintiff off his balance, which he was unable to
regain until the car had reached the fifth floor, where he was
caught in the weights which passed the car at that point."
The contention based upon the asserted insufficiency of the
declaration is without merit. So far as appears, the evidence was
received without any objection upon this ground, and the assignment
of error rests solely upon the refusal of the trial court to grant
a general prayer that the court should instruct the jury that,
"under the pleadings and all the evidence," their verdict should be
for the Fuller Company. It is urged that there is no sufficient
averment of the negligence of this company, and attention is
directed to the allegation of the declaration that the
plaintiff
"requested the said defendant, Otis Elevator Company, its
servants and employees, to stop said elevator at the second floor,
so that he might get off and alight therefrom."
It is manifest, however, from the other allegations of the
declaration that the plaintiff intended to charge, and did charge,
negligence on the part of both defendants. The attention of the
trial court was not called to any particular in which the
declaration was deemed to be insufficient as against the Fuller
Company, and no mention was made of the specific point now raised.
If this point had been suggested, it is apparent that, in view of
the allegations contained in the declaration, such variance as
there was between pleading and proof could properly have been met
by an immediate amendment, and the case could
Page 228 U. S. 201
then have been submitted to the jury precisely as it was
submitted.
It is also assigned as error that the trial court improperly
modified one of the requests of the Fuller Company for instruction
upon the subject of contributory negligence. The requested
instruction, with the modification made by the trial court, which
appears in the words italicized, was as follows:
"If the jury find from all the evidence that the accident to the
plaintiff was occasioned wholly or in part by reason of the fact
that he had placed himself in an exposed and dangerous position on
the ledge around the top of the elevator car, with reference to
obeying the signals to stop at the second floor, if you find such
signals were given when he might readily have placed himself
in a safe and secure position, the verdict should be for the
defendant, the George A. Fuller Company, regardless of any supposed
negligence on the part of the elevator operator and regardless of
whether the operator was a servant of the Fuller Company or
not."
The court undoubtedly added these words because the evidence
showed that the plaintiff had asked the operator to stop at the
second floor, and there was no danger from the weights until the
elevator reached the fifth floor. The fact that the plaintiff
intended to go only to the second floor, and had signaled
accordingly, was properly to be taken into consideration in passing
upon the question whether, in the circumstances, he acted with
reasonable prudence. The court, in other portions of the charge,
correctly instructed the jury on the subject of contributory
negligence, and there is not the slightest ground for the
conclusion that there was any doubt as to the meaning of the court
in the words used in modifying the defendant's request, or that any
prejudicial error was committed.
The principal argument for reversal is based on the ruling of
the trial court that Locke, the operator of the elevator, was the
servant of the Fuller Company. The
Page 228 U. S. 202
court below approved this ruling, and we find no error in its
conclusion. So far as Locke's employment was concerned, there was
no dispute as to any matter of fact, and the question of the
liability of the Fuller Company for his negligence, if he was
negligent in the operation of the elevator, was one of law. It
cannot be said that, under the arrangement between the Fuller
Company and the Mackay Company, Locke was transferred to the
employment of the latter. The Fuller Company had contracted for the
construction of the building. It had made a subcontract with the
Mackay Company which covered the painting of the elevator shaft. It
was convenient in doing this that the top of the elevator should be
used as a movable platform. But the Fuller Company needed the
elevator from time to time for other purposes, and it was important
to it that the elevator shaft should be kept free of obstructions
and that the elevator should continue to be at its command.
Accordingly, the Fuller Company agreed to furnish to the Mackay
Company the use of the elevator and the service of the operator,
for a specified sum per hour, when the elevator was not otherwise
required. The Fuller Company was thus aiding in the prosecution of
the work which it had contracted with the owner of the building to
perform, and in providing the use of a facility to a subcontractor
it secured the doing of the work at the smallest inconvenience to
itself. It must be concluded that the operating of the elevator
under this arrangement with the Mackay Company was an operating of
it by the Fuller Company. It is true that the employees of the
Mackay Company were to give the signals for starting and stopping
the elevator, but this did not make the operator who received them
the servant of the Mackay Company. These signals simply notified
him as to what was required from time to time in the course of the
service which the Fuller Company had agreed to provide.
Page 228 U. S. 203
The court below followed the decision of this Court in the case
of
Standard Oil Co. v. Anderson, 212 U.
S. 215. There, the plaintiff was employed as a
longshoreman by a master stevedore, who was acting under a contract
with the defendant, the Standard Oil Company, in loading a ship
with oil. The plaintiff was working in the hold, where, without
fault on his part, he was struck by a load of cases containing oil
which was unexpectedly lowered. The ship was alongside a dock
belonging to the defendant, and the cases of oil were conveyed from
the dock to the hatch by means of tackle, guy ropes and hoisting
ropes furnished and rigged by the stevedore. The motive power was
supplied by a winch and drum owned by the defendant and placed on
its dock. The work of loading was done by employees of the
stevedore, except that the winch was operated by a winchman in the
general employ and pay of the defendant. The stevedore paid the
defendant an agreed sum for the hoisting. The winch was placed
where it was impossible to determine the proper time for hoisting
and lowering the cases of oil, and the winchman necessarily
depended upon signals from an employee of the stevedore stationed
on the deck of the ship. The negligence consisted in lowering a
draft of cases before the signal was received. The court held that
the winchman remained the servant of the defendant, and affirmed a
judgment recovered against the defendant for his negligence. With
respect to the argument based on the fact that the winch was to be
operated for the stevedore, according to the orders of his
employees, Mr. Justice Moody, in delivering the opinion of the
Court, said:
"Much stress is laid upon the fact that the winchman obeyed the
signals of the gangman, who represented the master stevedore, in
timing the raising and lowering of the cases of oil. But when one
large general work is undertaken by different persons, doing
distinct parts of the same undertaking, there must be cooperation
and coordination, or there will be chaos.
Page 228 U. S. 204
The giving of the signals under the circumstances of this case
was not the giving of orders, but of information, and the obedience
to those signals showed cooperation, rather than subordination, and
is not enough to show that there has been a change of masters."
Id., p.
212 U. S.
226.
In the present case, the Fuller Company obtained the use of the
elevator and the operator from the Otis Company, and paid therefor.
But the Otis Company had nothing to do with the arrangement with
the Mackay Company. To this transaction, and to the employing of
the top of the elevator as a movable platform for the painters, the
Otis Company was a stranger. The Fuller Company, having obtained
the use of the elevator, agreed to supply it to the Mackay Company,
and undertook to furnish that company the necessary service in
operating it; it asserted control for this purpose, and assumed the
duty of operating with proper care.
Judgment affirmed.