In a contract with the government for the reconstruction of a
drawspan bridge which provides for completion before opening of
navigation, permission to use false work during construction does
not permit such use after the opening of navigation, and where the
completion is delayed through negligence of the contractor until
after opening of navigation and he is obliged by reason of
destruction of the false work to substitute a lift span, he cannot
recover the extra cost occasioned thereby.
Quaere, and not decided, whether a receipt for final
payment on a government contract, given without protest, amounts to
an accord and satisfaction so as to be a bar to a claim for extra
work in connection with the subject matter of the contract but not
specified therein.
38 Ct.Cl. 492 affirmed.
Page 211 U. S. 189
The facts are stated in the opinion.
MR. JUSTICE WHITE delivered the opinion of the Court.
This appeal is prosecuted to obtain the reversal of a judgment
rejecting a claim of the Phoenix Bridge Company for $6,958.14. The
bridge company based its right to recover upon the averment that,
during the performance of a contract entered into by it with the
United States for the partial reconstruction and remodeling a
bridge belonging to the United States, spanning the Mississippi
River between Davenport, Iowa, and Rock Island, Illinois, the
company had, under the orders of the United States officer in
charge of the work, expended the amount claimed for work not
specified in the contract, and for the value of which therefore the
United States came under an obligation to respond. Not following
the precise order in which the court below recited the facts by it
found, we reproduce from such findings the statements made therein
of such facts as are in anywise pertinent to the questions which we
think the controversy involves.
In July, 1895, the government of the United States issued a
circular advertisement, signed by A. R. Buffington, Colonel of
Ordnance, U.S. Army, inviting proposals for the construction of a
new superstructure and making alterations in the abutments and
piers of the government bridge over the Mississippi River
connecting Davenport, Iowa, and Rock Island, Illinois. The bridge
company, in answer to this advertisement, submitted a formal
proposition, and, in addition, addressed a letter to Colonel
Buffington, dated August 10, 1895, which, among other things,
contained the following:
Page 211 U. S. 190
"Col. A. R. Buffington, Col. Ord., Commanding Rock Island
Arsenal, Rock Island, Illinois."
"Dear Sir: Appreciating the importance of finishing the proposed
new bridge at Rock Island at the earliest possible date, we have
been making a very careful study of the best method of removing the
present structure and erecting the new spans, and have finally
decided upon a plan which will enable us to work on the structure
regardless of floods and ice in the river, and thereby give you the
work at least five or six months before the time mentioned in your
letter of July 27th. Our plan of erection is shown in detail on
prints 1 and 2 sent herewith."
"The erection of the drawspan, of course, must be done during
the closing of navigation, between the 20th of November and the
15th of March of the following year, and this span will be removed
in the ordinary manner, by placing false work in the river to
support temporarily the old structure and the railway traffic
during the removal of the present span, and for supporting the new
work during erection, the various parts being put in position by
the ordinary overhead traveler shown on plan 2. This particular
part of the erection does not need any special explanation. As we
have made a specialty of drawspan work and have every facility in
our shops for building such a span, we have named a date of
completion for the new drawspan of March 1st, 1896. The first small
span, 'E,' we will erect in advance of the drawspan, and will have
the same in position on February 1st, 1896. We erect this small
span in advance of the draw, that we may bring these two spans up
to the new grade together."
In August, 1895, the bridge company was notified of the
acceptance of its proposition, such notification stating, however,
that decision upon the character of the stone to be used and the
form of the solid steel railroad floor was reserved. On October 2,
1895, the contract for the performance of the work was
executed.
At the Rock Island end of the bridge, there was a stationary
Page 211 U. S. 191
span, and next to that there was a drawspan, and beyond that
there were several more stationary spans, extending to the Iowa end
of the bridge.
The plan adopted for the erection of the bridge contemplated the
substitution of new material for the old superstructure without
interruption to the railroad traffic over the bridge, and the
scheme adopted was to carry such traffic upon false work,
consisting of timbers extending from the bed of the stream to the
old superstructure for the purpose of supporting the tracks for
such traffic. This false work under the drawspan made a barrier
across that portion of the stream, which would have rendered
navigation impossible in case such false work was not removed prior
to the opening of navigation.
The drawspan was intended for the convenience of navigation upon
the river, and said draw was the only means that vessels and other
craft on the river had of going from one side of the bridge to the
other.
The specifications, as originally prepared, called for the
erection of the drawspan by January 1, 1896, and the completion of
the bridge on November 1, 1896. Subsequently the specifications
were modified so as to fix March 1, 1896, as the date for the
erection of the drawspan, and September 15, 1896, for the final
completion of the whole bridge.
The object of fixing March 1, 1896, for the completion of the
drawspan was that navigation, which was likely to open at that
place in the middle of March, should not be interrupted by the work
of construction upon the bridge. This object was well understood by
both parties to the contract.
The specifications, forming a part of the contract, provided
that the dates given above were of the essence of the contract, and
that no payment would be made for any work or material, as provided
by the specifications and the contract, to be made with the
contractor, while he was in arrears in delivery or erection, and in
case of the failure of the contractor to have the work completed by
November 1, 1896,
Page 211 U. S. 192
he would be required to pay two hundred dollars ($200) per day
as liquidated damages in consequence of such delay.
The specifications besides contained full details as to the
method of doing the work and the supervision thereof by the
government officer in charge. They provided that the contractor
would be required to remove old superstructure without disturbing
trains, and contained many express exactions looking to the
execution of the work so as to enable the bridge to be continuously
operated for the passage of trains during the progress of the
contract. The contract contained the following clause:
"5th. If any default shall be made by the party of the first
part in delivering all or any of the work mentioned in this
contract, of the quality and at the times and places herein
specified, then in that case the said party of the second part may
supply the deficiency by purchase in open market or otherwise (the
articles so procured to be of the kind herein specified as near as
practicable), and the said party of the first part shall be charged
with the expense resulting from such failure. Nothing contained in
this stipulation shall be construed to prevent the chief of
ordnance, at his option, upon the happening of any such default,
from declaring this contract to be thereafter null and void,
without affecting the right of the United States to recover for
defaults which may have occurred; but, in case of overwhelming and
unforeseen accident, by fire or otherwise, the circumstances shall
be taken into equitable consideration by the United States before
claiming forfeiture for nondelivery at the time specified."
No provision was made for payment as such for any of the false
work by which it was stipulated the whole bridge, including the
drawspan, should be supported during the work of reconstruction,
nor for the cost of removal of the same. The compensation
stipulated was a given price per pound for the material to be
placed in the new superstructure, and a fixed price per cubic yard
for alterations in the old masonry
Page 211 U. S. 193
work, and for excavations for additional foundations in the new
masonry work required.
"The claimant proceeded to fulfill the obligations of its
contract, and erected the necessary false work, including that, for
the drawspan, and was proceeding with the erection of the drawspan
itself on February 25, 1896, when, as a result of a rise in
temperature, the ice in the river at that point moved, taking with
it the false work and a substantial portion of the drawspan then in
place. In the condition in which the work was at that time, nothing
could have been done to prevent the destruction of the work. In
case the accident had not happened, the drawspan would have been
completed by March 15, 1896, to such an extent that it could have
been swung so as not to impede navigation. The claimant did not
proceed with the erection of the drawspan as expeditiously as it
might have done, particularly in that it did not procure the
necessary material in the order necessary for the erection of the
drawspan. Said span might have been completed a considerable time
before February 25, 1896, although the claimant was not bound to
have it completed until March 1, 1896, by its contract. The United
States was in no way responsible for any delays in the fulfillment
of said contract, and was in no wise in default."
"After said accident, Col. A. R. Buffington, United States
ordnance officer in charge of the construction, together with
several of his assistants, had a conference with the
representatives of the claimant at the site of the bridge, and it
was determined that the most feasible way of repairing the damage
and going on with the construction of the drawspan was to erect
said span upon the pivot pier running up and down the river, so
that the erection of said drawspan should not interfere with
navigation, which was likely to open at any time after March 1. It
was further determined that the most feasible way of providing for
railroad traffic during the erection of said drawspan was to put in
place a temporary liftspan, which could be so operated as to allow
the passage of vessels. Thereupon,
Page 211 U. S. 194
Colonel Buffington ordered the claimant to erect such liftspan,
which the claimant did at the expense of $6,683.59."
"Colonel Buffington's order was intended to meet an exigency
caused by the imminence of an immediate opening of navigation, and
to avoid the consequent large damage which would have been done to
the shipping of the river and the property interests employed
therein by the obstruction which would have been caused by work
under the contract if navigation had opened about March 1, as might
have been apprehended upon February 26."
"At the time of the conference . . . , representatives of the
claimant demurred to the erection of such liftspan. They claimed
that the bridge company could proceed to repair the damage done by
the accident and erect the drawspan on false work across the
channel of the river prior to the opening of navigation. Colonel
Buffington and his assistants maintained that this could not be
done."
"Navigation opened in the season of 1896, on March 27. At the
time of the accident, it could not have been foreseen that
navigation would not open several weeks prior to that date.
Navigation on the river at this point is heavy and continuous from
the opening of navigation. In case navigation had been interrupted
up to the date when the drawspan could have been ready to swing,
the damage to persons engaged in such navigation would have been
greater than the expense of the erection and operation of such
liftspan."
"The erection of the liftspan was necessary in order to provide
for railroad traffic and the navigation on the river, and was the
most feasible and the least expensive method of so doing."
"After the accident on February 25, 1896, the claimant proceeded
to erect the drawspan, in accordance with the contract, and said
drawspan was ready to swing June 1, 1896."
After the completion of the work, a voucher was drawn for the
final payment under the contract. This voucher recited the total
sum agreed to be paid by the contract, deducted the
Page 211 U. S. 195
previous payments made to the bridge company, and stated the
balance, it being explained that this balance constituted the full
and final payment to the contractor. The amount thus stated to be
the sum finally due under the contract was received by the company,
and a receipt was signed on December 11, 1896, declaring that the
amount received was
"acknowledged as the final and full payment for all the material
furnished, and for all the work performed under the said contract,
and in full for all charges, claims, adjustments, differences, or
other alleged indebtedness incident to the work, or related to it
in any manner whatever."
"At the time of signing this paper, the claimant made no
protest, and understood that it covered all claims it had against
the United States growing out of the erection of the said bridge.
The final completion of the work provided for in the contract was
several months later than the time limited in said contract, and at
the time said instrument was presented to plaintiff's agent for his
signature, he objected to signing it. Buffington then informed him
if he did not so sign it as a final release of all claims, his
instructions were to refer the whole matter, including claims for
delay in the completion of the work, to the Department. Claimant's
agent then advised directly with his principal, after which he
signed the instrument and received the final payment at the same
time, in reply to an inquiry by Colonel Buffington whether he
signed without reservation, replied, 'You have our signature to the
release as you handed it to me.' Before that time, there had been
dispute between the parties both as to the liability of defendant
for the liftspan and the plaintiff for delay in the completion of
the work. No damages for delay were afterwards claimed or sought to
be enforced against the claimant."
Upon these findings, it is insisted that the court below erred
in holding that the bridge company was not entitled to recover the
amount by it expended for the erection of the temporary liftspan,
because that work, done by the direction of the officer
representing the United States, was not within the
contemplation
Page 211 U. S. 196
of the contract, and no duty rested upon the bridge company to
do such work. In other words, the contention is that, as the
contract provided for supporting the old structure across its
entire length, including the drawspan, by false work which was to
hold the old structure until the new was completed, when the false
work should be removed, that the bridge company, when the damage
caused by the melting of the ice took place, was entitled to
continue the use of the false work for supporting the drawspan,
although in so doing the navigation of the river would be entirely
obstructed. And, upon the assumption that such is the true
interpretation of the contract, it is urged the final receipt which
was given did not constitute accord and satisfaction for the
expenditure made concerning the liftspan. In logical order, the
question of accord and satisfaction resulting from the giving of
the receipt when the final payment was made would first arise for
solution. As, however, the contention that accord and satisfaction
did not result from the giving of the receipt rests upon the
assumption that the work done in the temporary erection of the
liftspan was not within the contract, and therefore was not
embraced by the receipt, it follows that we must, in order to
dispose of the controversy as to accord and satisfaction, consider
and determine the nature and character of the obligations which the
contract imposed concerning the work done as to the liftspan. For
this reason, to avoid repetition, we come at once to the
fundamental question -- that is, the interpretation of the contract
for the purposes of ascertaining whether the work referred to was
within the purview of the contract, for if it was, that will
dispose of the whole controversy, including the claim of accord and
satisfaction.
The argument by which it is sought to support the contention
that the bridge company was entitled, after the accident, to
continue the construction of the drawspan by the erection of false
work which would entirely bar the navigable channel, insists that,
as the contract alone provided for the method of construction by
means of false work as a support
Page 211 U. S. 197
for the old structure during the performance of the contract,
the contract must be construed as having authorized the bridge
company to continue the use of the false work after the accident,
even across the navigable channel, despite the injurious
consequences to navigation which would have resulted. And from this
right to use the false work to the destruction of navigation it is
contended that there was no authority to direct the erection of the
liftspan, and consequently an implied and contract liability on the
part of the United States to pay the cost of the same when the span
was erected under the order of the officer of the United States in
charge. But we are of opinion that the interpretation of the
contract upon which this proposition must rest is unsound, because
it is not supported by the text of the instrument and is not
consonant with the intention of the parties as manifested by the
text and as established as a necessary result of the findings below
made.
In considering the text of the contract, attention is at once
attracted to the important stipulations as to the period in which
the work should be carried on and completed, and to the difference
between the time fixed for the completion of the work as to the
drawspan and that as to the remaining spans. When the fact that the
bridge spanned a great navigable river, and the duty of the
government to protect that navigability, is borne in mind,
moreover, when the facts found by the court below as to the period
when navigation would be suspended as the result of natural causes
is also considered in connection with the obligation which the
contract imposed of completing the drawspan within such
nonnavigable period, we are of opinion that the contract must be
interpreted as exacting that the means employed in constructing the
drawspan should be such as would not operate to impede navigation.
We think, therefore, that the contract must be held to have
empowered the bridge company to use and retain the false work in
the navigable channel only during the time expressly stipulated in
the contract, and therefore to have imposed
Page 211 U. S. 198
the duty after that period, if the exigencies of the situation
required it, to perform the work on the drawspan in some other
suitable manner consistent with the noninterruption of the
navigation of the river.
This interpretation, which we think the contract requires, as we
have said, is directly in accordance with the finding below, that
the object of fixing March 1, 1896, for the completion of the
drawspan was that navigation, which was likely to open at that
place in the middle of March, should not be interrupted by the work
of construction upon the bridge, and that this object was well
understood by both parties to the contract.
The argument that, because the contract and its specifications
contained many minute stipulations looking to prevent the
interruption of railroad traffic across the bridge, and no express
requirement as to the preservation of the navigability of the
river, therefore, under the rule that the inclusion of one is the
exclusion of the other, it should be interpreted as not having
contemplated the necessity for preservation of navigability, when
the terms of the contract are accurately considered, is
self-destructive. We say this because, if the provision of the
contract as to the time for completing the drawspan be given its
necessary significance as elucidated by the intention of the
parties as expressly established by the findings below, it must
result that the insertion of the requirement as to the construction
of the drawspan within the period fixed, which was safely within
the time when, by the operation of nature, there would be no
navigation on the river, excludes the conception that the minds of
the parties could have deemed it necessary to expressly provide for
the contingency of the interruption of navigation by the execution
of the work, when such interruption was impossible to arise if the
duties which the contract imposed were executed according to their
express requirements.
As the findings beyond peradventure established that the
liftspan was the most feasible and least expensive substitute
Page 211 U. S. 199
for the false work which could have been employed after the
accident, and as they also established that the objection of the
bridge company to pursuing that method was alone based upon the
assumed right to complete the work by the use of false work in the
navigable channel after the period stipulated in the contract -- a
right which we hold the bridge company did not enjoy -- we think no
express or implied obligation rested upon the United States to pay
for the cost of the temporary liftspan, and that the court below
was correct in so holding.
Disposing of the case, as we do, upon the interpretation of the
contract heretofore made, it is unnecessary to consider whether,
even assuming that there could be a different interpretation, the
bridge company would be entitled to recover in view of the facts
found below as to the state of the work on the drawspan at the time
the accident occurred -- that is, the backwardness of such work,
which it was expressly found was due solely to the negligence of
the bridge company.
Affirmed.