Where words used in a contract are plain and unambiguous, expert
testimony as to their commercial signification is not admissible
for the purpose of destroying the plain and obvious intendment of a
contract, and so held that, where a government dredging contract,
by its terms, expressly excluded material which slid into the
excavation from the slope outside of the stakes, expert testimony
to show that the trade meaning of the words "measured in place"
includes such sliding material if dredged was properly
excluded.
After the government has, against the contractor's protest,
affixed a meaning to terms used in a contract, the contractor
cannot reassert the same claim in regard to a supplementary
contract for additional work of the same nature even if the
original contract were susceptible of the construction claimed by
him.
41 Ct.Cl. 214, 498, affirmed.
The facts are stated in the opinion.
Page 211 U. S. 180
MR. JUSTICE WHITE delivered the opinion of the Court.
The appellant, the dredge company, sued to recover $28,321.76.
The relief sought was based on the averment that, under a contract
for dredging a channel in the Christiana River and in or about the
harbor of Wilmington, Delaware, made in 1899, and a supplementary
contract made in June, 1901, the dredge company had excavated
260,430 cubic yards
Page 211 U. S. 181
of earth, for which, at the contract price, it should have been
paid the sum sued for, but that the United States, in making
settlement under the contract, despite the protest of the dredge
company, had declined to pay upon the ground that excavating and
removing the earth referred to was not within the contract. The
pertinent facts found by the court below are these:
Prior to September, 1899, the United States was engaged in
excavating a channel in the Christiana River and about the harbor
of Wilmington, Delaware. The work, in September, 1899, was in
process of execution, under a contract between the United States
and the New York Dredging Company. In the office of the United
States engineer in charge of the work, there existed maps or
drawings showing the condition of the river prior to any work's
being done by the New York Dredging Company, the location of the
channel in which the work was being done, and the specifications
controlling the contract, as well as the progress made in the work.
Of these facts, the dredge company had knowledge. On September 18,
1899, the United States engineer office at Wilmington, through
William F. Smith, United States agent, advertised for proposals for
the dredging and removing of about 900,000 cubic yards of material
in connection with the work then being done, as previously stated.
In the advertisement inviting the proposals, it was stated that
specifications, blank forms for proposals, and all available
information would be furnished on application to the engineer
office. The specifications for the work in question recited:
"The project for the completion of which contracts are
authorized in the law above quoted requires the dredging of the
Christiana River to a depth of 21 feet at mean low water from the
21-foot curve in the Delaware River to the upper line of the pulp
works; thence to the draw pier of the Shellpot Branch, No. 4, of
the P., W. & B.R. Co., so as to give a depth which gradually
diminishes to 10 feet at mean low water at the latter-named place
and the removal of shoals having less
Page 211 U. S. 182
than seven (7) feet of water over them; thence to Newport -- the
width to be 250 feet to the mouth of the Brandywine, 200 feet
thence to the upper line of the pulp works, and 100 feet above.
Work is now in progress under contracts for dredging to a depth of
18 feet up to the pulp works, the width to be made being 200 feet,
and for all above-described dredging above the pulp works. The work
required under these specifications is the dredging that remains to
complete the project, additional to that done or to be done under
the contracts above referred to until their termination or
completion. It is estimated that about 900,000 cubic yards will
have to be removed."
The character of the work required, the method of carrying on
the same, and the steps to be taken to fix the amount to become due
under the contract when fully performed, were stated in the
specifications as follows:
"The amount of material removed will be paid for by the cubic
yard, measured in place, and shall be determined by surveys made
before dredging is commenced and after it is completed. All surveys
and measurements are to be made under the direction of the engineer
in charge, by persons employed by him for that purpose. The
decision of the engineer in charge as to the amount of material
excavated and removed, as well as to its location and deposit,
shall be final and without appeal on the part of the
contractor."
"The location of the work shall be plainly located by stakes and
ranges. The level of mean low water, as established by the engineer
in charge, shall not be changed during the progress of the work.
The contractor shall be required to supply the lumber for the
necessary stakes and ranges, and shall at all times, when called
upon, furnish men and boats to set them and keep them set under the
direction of the inspector, the expense thereof to be included in
the contract price for the dredging."
"No guaranty is given as to the nature of the bottom, but, as
far as it is known, it is sand, mud, day, and gravel. Bidders
Page 211 U. S. 183
are requested to satisfy themselves upon this point and to
examine all other local conditions, as it will be assumed that
their bids are based upon personal information. No extra allowance
will be made for excavating material differing from that herein
described."
"It is understood and agreed that the quantities given are
approximate only, and it must be understood that no claim will be
made against the United States on account of any excess or
deficiency, absolute or relative, in the same. Bidders are expected
to examine the drawings, and are invited to make the estimate of
quantities for themselves. It is not expected that the actual
quantities will vary more than 10 percentum from the
estimates."
"Payments will be allowed for actual dredging to twenty-one (21)
feet below mean low water level. Work done outside of the
designated lines of excavation or below the specified depth will
not be paid for, and any material deposited otherwise than
specified and agreed upon must be removed by the contractor at his
own expense."
On November 20, 1899, the claimant (dredge company), whose
proposal had been accepted, entered into a contract with the United
States through General William F. Smith, United States agent, for
the performance of the additional dredging, in conformity with the
advertisements and specifications referred to in the preceding
findings. It was provided in the contract that
"the said Bowers Hydraulic Dredging Company shall furnish all
labor, machinery, and appliances necessary or proper for the
faithful execution of the contract, and shall do the work called
for, and in all respects carry out and comply with the said
specifications for dredging."
The sum to be paid was fixed by the contract at 10 7/8 cents for
each and every cubic yard of material dredged, "measured in place,"
the said price including removal and redeposit.
Presumably in consequence of knowledge on the part of the dredge
company of a refusal by the government to pay the New York Dredging
Company for the work being done by
Page 211 U. S. 184
it for the removal of any earth from the excavated channel
derived from the sliding from slopes of the same, the dredging
company, before commencing work, addressed a letter to General
Smith, engineer in charge, requesting to know whether its contract
would be construed as excluding payment for removing such earth.
General Smith replied
"that payment will be made for the quantity of material removed
within the designated lines of excavation as determined by
measurement before and after the dredging, and that such
measurement does not include material which comes in from the sides
during the progress of dredging."
The letter stated: "I deem it proper to add that this is in
conformity with the instructions received from the chief of
engineers on the subject." The dredge company thereupon replied,
protesting against this construction, declaring that it was not
bound thereby, and that its performance of the work must not be
construed as an acceptance of the correctness of such
interpretation.
The work was commenced. Whenever a payment was made under the
contract, the dredge company, in receiving the same, asserted that
it was entitled to be paid for removing any earth which had fallen
into the excavation from the slopes and which had been removed by
it, and, on payment for such work being refused, it protested. On
June 21, 1901, while the work on the contract was proceeding, the
dredge company made a supplementary contract, increasing the amount
to be by it excavated, in accordance with the terms and
specifications of the prior contract, from 900,000 to 1,300,000
cubic yards. As the work thereafter progressed under both
contracts, payments were continued to be made by the government and
received by the dredge company under protest, as before stated,
until the work under the contracts was finally completed.
The court below found:
"The amount of material that fell or slid from the sides or
slopes of the vertical walls in front of the dredge and that was
removed thereby along with the excavated material within the
Page 211 U. S. 185
designated lines for dredging as provided by the contract was
more than 30,000 cubic yards, which at the contract price of 10 7/8
cents per cubic yard, would amount to over $3,000."
In the opinion delivered by the court below it was said:
"We are therefore of the opinion that the specifications, which
are made part of the contract, are plain and unambiguous, and that
they not only furnish the basis of measurement in place of the
material to be excavated, but that the measurements made by the
engineer in charge were in strict accord therewith. This being so,
any other method of measurement in place, even though customary, is
excluded by the terms of the contract, and therefore expert
testimony is not admissible to explain language that needs no
explanation."
And for these reasons, the right of the dredge company to
recover was denied. A new trial was asked, among others, on the
ground that error had been committed in not finding the trade
meaning of the words, "measured in place," and because the amount
of cubic yards of earth which had slid in from the sides or slopes
of the excavation while the contract was being performed, and which
had been removed by the company, had not been fixed at 260,430
instead of "as above 30,000," as stated in the findings. In
addition, a request was made that the findings be amended so as to
qualify the finding that the price paid should be 10 7/8 cents for
each and every cubic yard of material dredged, measured in place,
by adding the words, "the same being the trade meaning or
understanding of the words
measured in place.'" In addition, it
was asked that the finding as to the amount of cubic yards removed
of matter that fell from the sides or slopes be increased from
above 30,000 to 260,430. The motion for a new trial and the motion
to amend the findings were overruled. The court, in its reasons for
denying the motion, while stating that certain expert testimony had
been offered as to the meaning of the words "measured in place,"
further stated that it had declined to consider the same and make a
finding thereon,
Page 211 U. S.
186
as it concluded, as said in its previous opinion, that the
import of the words "measured in place," as used in the contract,
was so free from ambiguity that it did not consider the testimony
relevant. This was based upon the opinion that, whatever might be
the commercial signification of the words, that meaning could not
be imported into the contract for the purpose of destroying its
plain and obvious intendment when the terms of the entire contract
and the specifications forming part of the same were given their
proper weight.
The errors complained of are all embraced under the following
headings:
a. The refusal of the court to receive and consider testimony
offered as to the trade meaning of the words "measured in place"
and its refusal to make a finding on the subject, it being
contended that the action of the court in refusing to amend its
findings and the statement in its opinion that it declined to
consider such testimony adequately preserves the question for
review.
b. The refusal of the court to find the precise amount removed
of earth which slid in from the sides or slopes, thus leaving the
finding uncertain on that subject.
c. The attributing of conclusive efficacy to the action of the
officer in charge.
And finally,
d. The construction given by the court to the contract.
It is apparent that the question of construction last stated
lies at the foundation of all the assignments, and therefore first
commands consideration. We say this because, if it be that the
court below was correct in its conclusion that the contract gave to
the words "measured in place," as therein used, a plain and
unambiguous signification, it is obvious that the abstract or
commercial meaning of those words, upon the hypothesis that they
have such meaning, was rightly held to be irrelevant. And it is
equally plain that if the court below rightly construed the
contract in the particular mentioned, it will be unnecessary to
consider the effect which was given
Page 211 U. S. 187
to the action of the officer in charge, since that action was in
accordance with the meaning which the court gave to the
contract.
Coming to consider the contract, we are of opinion that the
court below correctly enforced its self-evident meaning. The
requirement that the amount of material removed should be paid for
by the cubic yard, measured in place, and shall be determined by
surveys made before dredging is commenced and after its completion,
clearly in and of itself established a method for fixing the amount
of material which might be excavated, and which was to be paid for,
absolutely incompatible with the contention that the contract
contemplated that payment should be made for excavated earth which
might slide into the channel from the slopes of the same during the
progress of the work. And this is fortified by the requirement as
to the location of the stakes and the keeping of them continually
in place during the performance of the work under the contract. It
is, moreover, additionally sustained by the provision, "that no
extra allowance will be made for excavating material different from
that herein prescribed," and by the stipulations, "that work done
outside of the designated lines of excavations or below the
specified depth will not be paid for," and "that any material
deposited other than that specified and agreed upon must be removed
by the contractor at his own expense." When these provisions are
read in connection with the specification stating that
"no guaranty is given as to the nature of the bottom, but, as
far as it is known, it is sand, mud, day, and gravel; bidders are
requested to satisfy themselves as to this point, and to examine
all other local conditions, as it will be assumed that their bids
are based upon personal information,"
in connection with the statement of the approximate quantity,
and the further condition that "no claim will be made against the
United States on account of any excess or deficiency, absolute or
relative in the same," we think the conclusion is beyond reasonable
controversy that the contract, by its express terms and without
ambiguity, excludes
Page 211 U. S. 188
the possibility of holding that earth which might slide from the
slopes during the excavation was to be paid for by the United
States. To separate the words "measured in place" from all the
other provisions of the contract, in order to give them an assumed
or proven abstract trade meaning, repugnant to their significance
in the contract, would be to destroy, and not to sustain and
enforce, the contract requirements. Lest our silence upon the
subject may give rise to misconception, we deem it well to observe
that, even if the original contract was susceptible of a different
construction from that which we hold arises from its plain import,
such result could have no possible influence on the asserted claim
of the dredge company, insofar as that claim is based upon
excavation done under the supplementary contract. We say this
because that contract was made with the full knowledge of the
meaning affixed by the United States to the terms of the contract,
and which had been insisted upon in the carrying on of the previous
dredging operations.
Affirmed.