When, in the performance of a written contract, both parties put
a practical construction upon it which is at variance with its
literal meaning, that construction will prevail over the language
of the contract.
In this case, the defendant in error having under a written
contract with the agents of the plaintiff in error constructed a
sewer which in the course of construction was, by mutual consent,
and for reasons assented to by both parties, made to vary in some
respects from the plans which formed part of the contract, but
without any agreement as to a change in the contract price,
held, for the reasons given by the Court of Claims, that
the judgment of that court awarding the contract price for the work
is affirmed.
The case is stated in the opinion of the Court.
MR. JUSTICE MATTHEWS delivered the opinion of the Court.
This suit was brought against the District of Columbia for the
recovery of the sum of $138,459.55; of this $35, 36.49 were alleged
to be payable as the balance due upon a contract for building and
completing the brick arch upon stone abutments of Triber Creek
sewer, as set out and described in the
Page 124 U. S. 506
contract and specifications attached to the petition at the
price of $113 per lineal foot. The additional sum of $98,130.44 was
alleged to be due on account of extra work and materials furnished
by the contractors beyond the requirements of the contract in and
about the same work. This indebtedness was denied, and the
defendant also filed a plea of set-off in the sum of $82,176; of
this, $7,176 was for the value of stone alleged to have been sold
by the defendant to the claimants, $35,000 on account of
deficiencies in the construction of the sewer, and $40,000 as the
reasonable cost and expense of filling the canal for the whole
length of the sewer, which the defendant claimed the petitioners
were bound by their contract to do. Upon the facts found by the
court, it was held that the claimants were entitled to recover upon
their claims the sum of $43,935.74, that the defendant was entitled
to recover upon the set-off and counterclaim the sum of $1,479, and
judgment was rendered in favor of the petitioners for the
difference, being the sum of $42,456.74.
The facts as found by the court, so far as material, are as
follows:
The Triber Creek, prior to the year 1871, was a natural stream
of water flowing through the City of Washington and discharging
into what was then known as the "Washington Canal," on Third Street
West, between Maine and Missouri Avenues, and by that in the
Eastern Branch.
Among the improvements projected by the Board of Public Works
was that of utilizing this stream in connection with the sewerage
system of the city, and the general plan adopted was that of
constructing a main sewer of masonry and brickwork along its
course, through which the stream should flow, receiving and
conducting the sewage from lateral connections on either side.
It was constructed for the most part in sections, by contract
with different parties, and the part here in controversy was the
final or outlet section. It was commonly styled the "Tiber Creek
sewer or arch."
On and before July 14, 1873, a portion of this sewer had been
completed, which (so far as is here material) extended
Page 124 U. S. 507
from the north side of Pennsylvania Avenue across the botanical
garden, into Third Street, and along and under Third Street to a
point three feet north of the south building line of Maryland
Avenue, at which terminus the sewer was (so far as here material)
of the following construction and size, namely, the side walls were
of masonry, about three feet high and 5 feet 6 inches thick,
supporting an approximate semi-elliptic arch of 30 feet span and 7
feet 10 inches rise. The extrados of the arch, including the
skew-back course, was backed up with rubble masonry to the level of
its crown.
The timber sleepers for the foundations were 41 feet in
length.
Proposing to continue the sewer to its outlet with the same
construction and size, the Board of Public Works, on July 14, 1873,
sent to H. L. Gallaher & Co., consisting of Hugh L. Gallaher
and Edwin H. Smith, a written proposal for continuing the Triber
Creek sewer from its existing terminus at Maryland Avenue and Third
Street Southwest, along the line of the Washington Canal to its
junction with the James Creek Canal, the size and manner of
construction of the sewer to be the same as that of the portion of
the same sewer constructed on Third Street Southwest, and to be
paid for at the rate of $113 per lineal foot, and they were
requested by return mail to notify the board of their acceptance or
rejection of the proposal. On the same day, H. L. Gallaher &
Co., by writing, accepted it. A written contract bearing date July
19, 1873, was executed between the parties in the same terms as
that set forth in the petition. Before work was commenced under it,
the District engineer was instructed to give the grade of the
sewer, to be laid out with the same dimensions as of the existing
sewer, which he did in the summer of 1873. It was proposed,
however, and consented to by both parties, to deviate from the
contract, by which the continuation of the sewer was to follow and
be laid in the bed of the canal, so as to take it by a curve from
the point of connection on the westerly bank and then proceed
parallel with and along said bank to the terminus. About the time
of giving the grade, Gallaher applied for a plan of the sewer, when
by direction of the
Page 124 U. S. 508
engineer a plat or working drawing of the structure in
transverse section, exhibiting its form and dimensions according to
a fixed scale, and representing a structure similar to that of the
completed section at the point of connection, was furnished.
Gallaher and Smith then proceeded with the work in accordance with
that plan, and completed some part of the excavation, and procured
and brought on the ground material, but had not constructed any
portion of the arch, when Joseph G. and Henry E. Loane, two of the
petitioners, bought out the interest of Smith in the contract, and
thereupon the original contract was cancelled and one in similar
terms executed on December 22, 1873, by the Board of Public Works
with the claimants, composing the firm of Gallaher, Loane &
Company, a copy of which is set out with the petition. The
claimants on entering into said contract received from Gallaher
& Smith the working plan furnished to them by the district
engineer. It represented the plan and dimensions of the several
parts of the structure of the sewer to be built under their
contract, and was similar to the completed section with which it
was to connect, as provided by the contract, and was the plan under
which the work had been commenced and carried on. They proceeded
with the work in accordance with the plan, and without calling the
attention of the board to any alleged or apparent variation of the
same from the contract, and constructing the flooring, masonry, and
arch according to the dimensions appearing thereon, and had
finished about 680 lineal feet thereof when the Board of Public
Works was abolished by act of Congress of June 20, 1874. The work
as thus far done was constructed under the direction of the
district engineers, but neither they nor the Board of Public Works
intimated to the claimants that the work was not progressing to
their satisfaction, and in accordance with the former sample work,
in which the skew-back was constructed of rubble masonry.
Under the new form of government established by that act for the
District, Richard L. Hoxie was detailed as engineer on July 6,
1874, and forthwith made a careful examination of the work being
done by claimants, as to its character and conformity
Page 124 U. S. 509
with the specification of the contract, in the presence of one
of the claimants.
He found that generally it was being built in conformity with
the specifications, but there were several departures. The flooring
and sleepers were, as he thought, inferior to the quality required;
the masonry was not strictly in conformity with the specifications;
there were too few bond stone used; the inside walls were not
dressed, and the stones generally were small. But what attracted
his attention, and was of the most importance, was the manner of
constructing the skew-back. It was made of small stones, spalls,
and mortar, while it should have been made, as he thought, of large
dimension stone. He called the attention of the party present to
these alleged variations, and particularly to the skew-back, which
he wished constructed of dimension stone. He was informed that to
procure the stone would cause considerable delay in the prosecution
of the work. Thereupon he directed that the skew-back might be made
of brick, and added that he should make a deduction in price, but
named no sum. Thereafter claimants proceeds with their work, making
the skew-back of brick under the direction of defendant's
engineers, without further complaint.
In August, 1874, the claimants applied for measurement of the
work so far as completed and a partial payment. The engineer
thereupon transmitted to the board of audit, which, by the Act of
June 20, 1874, was charged with the settlement of such accounts, a
statement with the measurement requested. In that statement, the
engineer represented that the contract required the inside sewer
face of the stone wall rough-dressed, and a skew-back stone not
less than a three-foot six-inch bed, and in length of not less than
four feet, and that these requirements of the contract had not been
complied with. He therefore on this account recommended a deduction
of $8.94 per lineal foot of the sewer. The board of audit audited
the account with that deduction from the contract price, in
accordance with the statement of the engineer. The claimants
received the partial payment under protest. The amount of this
deduction upon the entire work performed by the claimants
constitutes the sum of $35,436.49, for which they sue.
Page 124 U. S. 510
The whole controversy between the parties as to this item, and
also for a portion of the claimant's demand on account of extra
work and material, arises out of the fact that the letter of the
contract and specifications does not correspond with the plan of
the work as furnished by the district engineer and the sample of
the work which had been done previously by other contractors, and
with which that of the present claimants was to connect. The work
as actually done was done under the direction and supervision of
the District engineer, and was performed in accordance with the
plan and sample which was supposed and understood to be what was
required by the contract, and to be paid for at the contract price.
We think that the practical construction which the parties put upon
the terms of their own contract, and according to which the work
was done, must prevail over the literal meaning of the contract,
according to which the defendant seeks to obtain a deduction in the
contract price. The other items allowed by the Court of Claims,
both to the claimants and the defendant, we think well established
upon the facts as ascertained by it. The reasons for its judgment,
as set forth in the opinion of the court, we think entirely
satisfactory. 19 Ct.Cl. 564.
The judgment is affirmed.