A railroad company in aid of whose road Congress grants land
upon condition that it shall transport mails at such price as
Congress may direct, and that until the price be thus fixed, the
Postmaster General shall have power to determine the same, is (in
the absence of contracts with the department for special service
with unusual facilities, or for determined periods) bound to
transport mails (until Congress directs the rates) at such
reasonable compensation as the Postmaster General may from time to
time prescribe, and the continuance by such company to transport
mails after the expiration of the term of a written contract
neither implies that it is, after the Postmaster General has
otherwise directed, to be paid the same rates for transportation
which it was paid under the written contract, nor that the contract
is renewed for any specific term for which contracts of the Post
Office Department may usually be made.
Page 118 U. S. 627
This was an appeal from the Court of Claims. The case is stated
in the opinion of the Court.
MR. JUSTICE FIELD delivered the opinion of the Court.
The petitioner, the Jacksonville, Pensacola and Mobile Railroad
Company, was incorporated under the laws of Florida and aided in
the construction of its road by a grant of land from the United
States. The act making the grant contained a clause providing that
the mails of the United States should be transported over the road
and its branches, under the direction of the Postmaster General at
such price as Congress might by law direct, and that, until the
price should be thus fixed, the Postmaster General should have
power to determine the same. 11 Stat. 16, c. 31, ยง 5. This
provision was a condition attending the grant, with which the
company could not refuse to comply without subjecting itself to a
claim for damages on the part of the government and possibly to a
forfeiture of the grant. As was said in the case of
Chicago
& Northwestern Railroad Co. v. United States, 104 U.
S. 680, the power thus vested in the Postmaster General
to establish the price includes the power to prescribe the period
of its duration. He might, if he thought expedient, and in many
cases it would be so, prescribe specially for the service of each
day. There may be, under some circumstances, temporary difficulties
of transportation which would call for frequent, and perhaps daily,
changes in the prices allowed. When, however, a price is agreed
upon for a prescribed service for a designated period, and there
are collateral stipulations annexed to the same which could not be
exacted by the government without the assent of the company, as for
instance the giving of sureties for the performance of the service
in a particular way, then, as held in the case cited, a contract is
created which cannot be disregarded by the government without a
breach of
Page 118 U. S. 628
good faith. But where no such collateral stipulations are made
and no duration of time is prescribed, but the service is exacted
simply from the obligation growing out of the acceptance of the
condition of the land grant, it rests in the discretion of the
Postmaster General to change the price from time to time as in his
judgment the public interest may require. It is not to be presumed
that in such matters he will act in an arbitrary or unreasonable
manner. For any abuse of his authority there is the security which
exists with reference to the action of all heads of the executive
departments in their responsibility to their superior and liability
to be called to account by Congress. No abuse of authority,
however, is suggested in the present case. An error of construction
as to the rights of the petitioner is alone alleged.
It appears from the record that the petitioner had a written
contract with the government for the transportation of the mail
between certain designated points from July 1, 1871, to June 30,
1875, at prescribed rates; that the contract contained various
stipulations on the part of the company as to the manner in which
the service should be performed, the free transportation of special
agents of the department, its liability to fine for neglects and
omissions of duty, and for the giving of adequate security for the
performance of its undertaking. The price for the service was
prescribed, and no question is made as to the entire and
satisfactory fulfillment of the contract by the company or of the
payment of the compensation stipulated by the government. After the
termination of this contract, the petitioner continued to carry the
mail as previously, without any notice from the Postmaster General
that the price to be allowed for the service would be in any
respect different, until the 21st of March, 1876, when he fixed the
rate of compensation at a less sum for the service until June 30,
1876. The service was performed by the company notwithstanding the
reduction made, and the reduced price was received without
objection.
From the 1st of July, 1876, until June 30, 1880, the same
service was performed by the company, but further reductions from
the compensation previously allowed were made under
Page 118 U. S. 629
the Acts of Congress of July 12, 1876, and of June 17, 1878.
Notice of them was given to the company, but the service by it was
continued, and the reduced price was received, also without
objection. It is now claimed that the company is entitled to the
difference between the price thus allowed and the price paid
previous to July 1, 1876. It is to recover such difference that the
petition is filed, the contention being that, by the continuation
of the service of the company after June 30, 1876, without
objection from the Postmaster General, a contract was implied that
the same compensation should be subsequently allowed.
At this time also, by regulation of the department, the United
States were divided into four contract sections. A general letting
for one of these sections was to take place every year, and
contracts were to be then made for four consecutive years,
commencing on the first of July. The road of the petitioner was
within the section in which contracts were to end on June 30, 1875,
until the regulation was altered, when it came within the section
in which contracts were to end on June 30, 1876. From this latter
fact, that the road was thus within the section in which contracts
were to be made for four years from July 1, 1876, it is further
contended that the contract implied from the service afterwards
rendered, as mentioned above, was to continue for four years.
The answer to both positions is obvious. By the condition
contained in the land grant, the company, as already stated, was to
transport the mail at such price as the Postmaster General should
determine unless fixed by a law of Congress. No implication could
therefore arise from the continuance of the service other than that
the company was carrying out the obligation imposed by its
acceptance of the land grant. Without specific stipulations by
sureties, there could be no obligation on their part for the
company, nor, without specific stipulations by the company, could
there be any requirement on its part to perform many of the duties
specially designated in the written contract. The Postmaster
General may have deemed it expedient for the public interest to
change, enlarge, or omit entirely the requirements previously
prescribed, and
Page 118 U. S. 630
to call for others of a different character. No implication can
arise one way or the other from his inaction. All that the company
could ask or expect under the law was that he should prescribe a
reasonable compensation for its service and that the service would
be continued so long as the public interests should require. No
implication of law could extend further than this.
And as to the alleged duration of four years it is sufficient to
say that the regulation of the department referred to was designed
only to further the administration of the postal service, not to
impose any obligation on the Postmaster General, and it would be
against all analogies to hold that a continuance of service after
the termination of a written contract for years creates an
obligation of a renewed contract not merely upon a like
compensation, but for the same duration of time. There is no
principle that could justify the implication.
Decree affirmed.