1. A board of commissioners, one from each of five counties,
having been incorporated by a state statute to construct and
maintain levees, with authority to make contracts for the doing of
the work and having made such a contract, and been sued in equity
thereon in the district in which the domicile of the board was
established by its act of incorporation, by persons residing out of
the district, a subsequent statute of the state abolished the
offices of the commissioners and constituted the treasurer and the
auditor of accounts of the state
ex officio the levee
board, with the declared purpose "to substitute the treasurer and
auditor in place of the board of levee commissioners now in
office," and a bill of revivor was filed against them by leave of
the court.
Held that the suit might be prosecuted against
the new board, although both the treasurer and the auditor resided
out of the district, and that an appeal from a final decree for the
complainant might be taken by the treasurer and auditor, describing
themselves by their individual names, and as such officers, and as
ex officio the levee board.
2. A board of commissioners, authorized by statute to make
contracts for the building of levees, and to borrow money, issue
bonds, and sell and negotiate them in any market, but not at a
greater rate of discount than ten percent, may make a contract for
the work at certain prices by the cubic yard, payable in such
bonds, and may afterwards amend that contract by inserting "at the
rate of ninety cents on the dollar" and issue bonds to the
contractors accordingly, upon being satisfied that such was the
agreement actually made between the parties, although the work is
actually done by subcontractors for lower prices in cash.
3. A board of levee commissioners made a settlement with
contractors employed to do the work on certain levees by which it
paid them a certain sum and took a receipt in full of all demands.
The parties afterwards executed an agreement under seal reciting
the settlement and receipt in full of all demands, a complaint of
the contractors that injustice had been done them in that
settlement, and the desire of the board to do full justice, and
stipulating that two engineers, one designated by each party,
should measure the work done, and render to the parties an estimate
of the amount due to the contractors for such work according to the
original contract; that if this should differ from the amount
already paid, the difference should be paid or refunded
accordingly, and that these two engineers and a third, to be agreed
on by them, should be arbitrators for the adjustment of all
questions of difference; that, in the adjustment of questions
pertaining to the measurement,
Page 106 U. S. 400
the contractors should have the privilege of introducing all
proper evidence, and the board of rebutting that evidence, and
that, before proceeding with the measurement, the contractors
should give written notice to the board of the points to be proved
and the character of the evidence to be offered. The contractors
thereupon gave notice of their intention to introduce proof of
several matters, some of which did not concern the measurements, to
which the engineer of the board objected, and the arbitration fell
through.
Held that the settlement and receipt bound the
contractors as an accord and satisfaction, and they could not
maintain a suit upon the original contract to recover further
compensation for the work.
The facts are stated in the opinion of the Court.
MR. JUSTICE GRAY delivered the opinion of the Court.
This is an appeal by "William L. Hemingway, Treasurer of the
State of Mississippi, and Sylvester Gwinn, Auditor of said state,
and
ex officio the Levee Board of Mississippi, District
No. 1," from a final decree of the District Court of the United
States for the Northern District of Mississippi upon a bill in
equity for the specific performance of a contract, filed in that
court on the 23d of February, 1873, by Hiram A. Partee, a citizen
of Tennessee, and Jephthah W. Stansell, a citizen of Arkansas,
co-partners under the name of Partee & Stansell (of whom the
appellee is the survivor), against the Levee Board of Mississippi,
District No. 1, and the five persons constituting that board.
By an act of the Legislature of the State of Mississippi of
March 17, 1871, entitled "An act to redeem and protect from
overflow from the River Mississippi certain bottom lands herein
described," this board, consisting of commissioners to be appointed
by the supervisors of Tunica and four other counties respectively,
was incorporated for the purpose of constructing, repairing, and
maintaining levees along a part of the Mississippi River. Its
domicile was fixed at the county seat of Tunica County, in the
Northern District of Mississippi, and it was authorized to appoint
a secretary and treasurer, and to let out and contract for the
construction of the works, and to issue
Page 106 U. S. 401
negotiable bonds to the amount of $1,000,000, and to sell and
negotiate them in any market, but not at a greater rate of discount
than ten percent
This suit was brought upon a contract made by the board with the
plaintiffs for the construction of certain levees. While it was
pending, on the 11th of April, 1876, the Legislature of Mississippi
passed an act entitled "An act to abolish the Levee Board of
District No. 1 and to pay the debts of said board," and enacting
that the offices of commissioners, secretary, and treasurer of
Levee District No. 1, as existing under the statute of 1871, be
abolished, and that the auditor of public accounts and the
treasurer of the state be constituted and appointed the Levee Board
of District No. 1
ex officio, and discharge all the duties
of the levee board, and of the secretary and treasurer of the
same,
"it being the intent and purpose of this act to substitute the
auditor of the state and the treasurer thereof,
ex
officio, as such commissioners, secretary, and treasurer, in
place and stead of the board of levee commissioners, secretary, and
treasurer of Levee District No. 1, now in office,"
and that
"The auditor and treasurer shall have full power to settle up,
under the laws now in force, the unfinished business of the said
Levee Board of District No. 1 and to pay any outstanding
liabilities of the same in such funds as may be applicable to the
same."
The defendant thereupon moved to dismiss the bill because by
this statute the levee board had been abolished and was no longer
capable of suing or being sued. The court overruled this motion and
allowed the plaintiffs to file a bill of revivor against the
auditor and treasurer (both of whom resided at Jackson, in the
Southern District of Mississippi), as constituting the Levee Board
of District No. 1, and, after due pleadings and proofs, entered the
final decree against the levee board, from which this appeal is
taken.
The appellee now moves to dismiss the appeal because it is the
appeal of Hemingway and Gwinn only, and not of the levee board. But
we are of opinion that this motion, and the motion made in the
court below to dismiss the bill, are equally groundless.
Page 106 U. S. 402
The statute of 1876, while it abolished the offices of the
commissioners who previously constituted the corporation of the
levee board, did not dissolve or extinguish the corporation, but
merely substituted the state treasurer and the auditor of accounts
as the members of that corporation. The suit might therefore be
prosecuted against the levee board as a corporation notwithstanding
the change in its members, and a bill of revivor having been
allowed to be filed for that purpose, it need not be considered
whether any revivor is requisite. The fact that the new members
reside in another district is immaterial. A court which has once
acquired jurisdiction of a suit does not lose it by a change of
domicile of the parties, and may, when the suit is of a nature that
survives, bring in the representatives or successors of a party who
has died or ceased to exist, without regard to their domicile.
The levee board, being the defendant in the suit, might appeal
from the final decree, and the appeal taken by Hemingway and Gwinn,
describing themselves not only by their individual names, and as
treasurer and auditor respectively, but also as
ex officio
the levee board, is the appeal of the board.
It follows that the motion to dismiss the bill because of the
passage of the statute of 1876 was rightly denied by the court
below, and that the motion to dismiss the appeal must be overruled
by this Court.
The evidence shows that the board, under the authority conferred
by its act of incorporation, advertised for written bids for
contracts to do the work; that the plaintiffs made a bid
accordingly for the work on certain parts of the levees at
specified prices by the cubic yard, payable in bonds at ninety
cents to the dollar, or ten percent discount; that this bid was
accepted by the board, and on the 28th of September, 1871, a
contract in writing was signed by the parties, by which the
plaintiffs agreed to do the work according to the specifications,
and to the satisfaction and acceptance of the chief engineer of the
board. The board agreed to pay them in bonds the prices named in
the bid, four-fifths on monthly estimates by its engineer of the
relative value of the work done and the rest on the final
completion of the work, the engineer's acceptance thereof, and
estimate of the quantity, character, and value of
Page 106 U. S. 403
the work done, and the plaintiffs' release under seal of all
demands arising under the contract, and it was mutually agreed that
the decision of the chief engineer should be final and conclusive
in any dispute which might arise between the parties to this
contract. It further appears that afterwards, and to carry out the
intention of the parties at the time of signing the contract, the
board at the plaintiffs' request, caused to be interlined therein,
after the word "bonds," the words "at the rate of ninety cents on
the dollar," and that monthly, during the progress of the work,
four-fifths of the engineer's estimates of the amount of work done
were paid for at the prices stipulated in the contract, in bonds at
that rate.
The board, in its answer and by a cross-bill, contended that the
plaintiffs had been largely overpaid because the prices agreed on
greatly exceeded the prices at which the work could be done, and
was done by subcontractors, for cash, and because the issue of
bonds at ninety cents on the dollar in payment of those prices was
in effect a negotiation of the bonds at a greater rate of discount
than ten percent. But the board had authority to make contracts,
and consequently to agree upon the compensation for the work. Being
authorized to issue bonds, it might issue them directly to the
plaintiffs, and the prices agreed to be paid, as well as the rate
at which the bonds should be taken, corresponded to the original
bid made by the plaintiffs and accepted by the board, as well as to
the terms deliberately adopted in the formal contract. The
suggestion that this course was pursued with the purpose of
fraudulently evading the restriction of the statute is unsupported
by proof, and there is no evidence that the funds necessary to
repair the levees could have been obtained in any other manner.
This position of the levee board therefore cannot be maintained,
and to that extent the decree of the district court must be
affirmed.
But the remaining question in the case presents greater
difficulties. The facts as disclosed by the record appear to us to
be as follows:
After the plaintiffs had completed the work, W. R. Kirkpatrick,
the chief engineer of the board, who had superintended the work,
made a final estimate of its quantity, character, and
Page 106 U. S. 404
value. The board, being dissatisfied with his estimate,
discharged him and caused the work to be remeasured by B. Mickle, a
special engineer (afterwards appointed chief engineer), whose
estimate showed a much smaller sum to be due to the plaintiffs. The
board thereupon refused to pay the amount due according to
Kirkpatrick's estimates, and after some controversy and
negotiation, settled the claim by paying the plaintiffs $47,800,
the amount found due by Mickle, and the plaintiffs signed and gave
them a receipt in these terms:
"Memphis, June 18, 1872"
"Received of A. R. Howe, Treasurer Mississippi Levee Board
District No. 1, $47,800, on account of work on levee, the same
being in full of all demands to date."
The plaintiffs in their bill allege that this receipt was
fraudulently and oppressively extorted by the levee board, and was
signed by the plaintiffs under protest. But the only evidence to
support their allegation is the testimony of Stansell himself, and
he on cross-examination admitted that he did not know much about
the matter, as Partee attended to the money transactions of the
firm, and his testimony is met and controlled by the explicit
denial in the answer of the board upon the oath of two of its
members, as well as by the recitals of an agreement under seal,
made between the board of the first part and the plaintiffs of the
second part on the fourth of October, 1872, the important portions
of which are as follows:
"Whereas, said party of the first part have heretofore made full
and complete settlement for all work done on said levee by said
party of the second part, as evidenced by their receipt
acknowledging the same, and said party of the second part do now
come forward and complain that injustice was done them in said
settlement, and it being the desire of the party of the first part
to do full justice to all men, it is hereby agreed that the party
of the second part shall designate an engineer, who shall proceed
with the chief engineer of this board to measure all work done by
said party of the second part on said levee, and render to the
parties to this agreement an estimate of the amount due to the
party of the second part for such work, according to the contracts
entered into for the completion of the same. And it is further
agreed that should said estimate exceed the estimate
Page 106 U. S. 405
made by the special engineer of this board in the month of June,
1872, the party of the first part shall pay to said Partee &
Stansell, party of the second part, the amount of such excess, and
all the expenses of this measurement shall be borne by the board.
But if the said estimate shall be less than the estimate of the
said special engineer in June, 1872, then said party of the second
part shall refund to said party of the first part the amount of
such deficit, and pay all the expenses of this measurement."
"It is further agreed that the party of the second part shall
designate an engineer, which engineer shall suggest a third
engineer, who shall be acceptable to the chief engineer of this
board, and the said engineers so selected shall, with the chief
engineer of this board, constitute a board of arbitrament for the
adjustment of all questions of difference, the agreement of any two
to be final. In the adjustment of questions pertaining to this
measurement, the contractors shall have the privilege of
introducing all proper evidence, oral or written, of notes,
profiles, or other evidence, which testimony may be rebutted by the
president of the board, this testimony being allowed to give the
engineer information as to the fills or any other fact not
perceptible to the engineers, to which testimony the engineers
shall give such weight as they may think the same entitled to
receive."
On the 12th of December, 1872, the parties signed a further
agreement stating that Mickle on the part of the levee board,
George B. Fleece on the part of the plaintiffs, and R. L. Cobb,
designated by Fleece with the consent of Mickle, constitute the
board of arbitrament referred to in the agreement of October 4,
1872, and establishing rules to govern that board in adjusting all
matters brought before them, one of which rules was as follows:
"Inasmuch as by the terms of said agreement the first party can
only rebut the testimony introduced by the second party, it is
agreed that the said second party shall, before further proceeding
with the measurement, notify the first party in writing what points
they expect to prove and the character of the evidence proposed, so
that the said first party may be ready with the rebutting
evidence."
On the same day, the plaintiffs gave notice in writing to the
levee board that they would introduce proof before the board
Page 106 U. S. 406
of arbitration upon twelve different matters, including these
three:
"4th. The clause in the contract touching shrinkage, its
meaning, and the adjudication of that question by the chief
engineer of your board prior to and about simultaneous with the
signing of the original contract."
"9th. The damage done to us by the repeated refinishing of work
under orders of your engineers."
"11th. The delay of a final estimate, of various payments, and
the damage to us arising therefrom."
On the next day, Mickle wrote a letter to Fleece, beginning
thus:
"In arranging the preliminaries to our organization as a board
of arbitrament on the question of difference between the levee
board of this district and Messrs. Partee and Stansell, I am
notified that claims will be made and testimony offered clearly in
contravention of the terms of the agreement from which our
authority is to emanate, and as such proceeding would render our
decision unsatisfactory and void, I cannot proceed further in the
matter unless it is distinctly understood that the following
provisions of the contracts and agreements entered into by the said
parties, and on which our authority is understood to be based,
shall be strictly observed."
He proceeded to point out that the agreement of October 4, 1872,
did not permit any evidence to be introduced except in relation to
the measurement of levees, and also stated the substance of the
following provisions in the specifications annexed to the original
contract:
"Nothing will be paid for settling, but its cost will be
included in the price paid for the levee, as estimated up to true
grade. If the levee be found deficient in height, slopes, or base,
or not to have the full settling on top and slopes, the contractor
must go over it immediately and correct all deficiencies, when the
engineer in charge will run a test level over it to see that all is
right."
"All damage or injury to the work, resulting from flood or other
cause, shall be sustained by the contractor until finished and
received by the chief engineer, and no work shall be received until
fully and completely finished in accordance with the above
specifications."
To this letter Fleece immediately replied, contending that the
board of arbitrament was already organized and declining to discuss
in advance any point likely to come before it. A
Page 106 U. S. 407
correspondence of six weeks ensued between Mickle and Fleece in
the course of which, after much dispute upon the question whether
Cobb had been in due form accepted as one of the arbitrators,
Fleece designated him anew in writing, Mickle declined to accept
him, Fleece offered Mickle the choice of either of several other
persons in Cobb's stead, and the correspondence ended in Mickle's
insisting on the objections made in his letter of December 13,
1872, and in the plaintiffs' abandoning the arbitration.
The court below was of opinion that the receipt in full of the
18th of June had been wholly set aside by the agreement of the 4th
of October, and that the arbitration under this agreement had
failed by the fault of the defendant, and entered a decree for the
plaintiffs according to the final estimate of Kirkpatrick.
We cannot concur either in the reasons or in the result. In our
view, the effect of the agreement of the 4th of October, 1872, was
to recognize that there had been a settlement in full between the
parties of the amount due from the levee board to the plaintiffs,
which bound both parties as an accord and satisfaction, and to
agree to open that settlement to this extent only: three engineers,
to be appointed as therein provided, should measure the work done
by the plaintiffs. If their estimate should differ from the
estimate of Mickle, according to which the settlement had been
made, the difference should be paid by the board or refunded by the
plaintiffs. The stipulation that the three engineers should
"constitute a board of arbitrament for the adjustment of all
questions of difference" was necessarily limited to questions of
difference in relation to the subject to be referred to them. If
such measurement by the arbitrators should not modify the estimate
of work done, or if the arbitration should fail without fault of
the levee board, the settlement stood.
The evidence, the substance of which is above recited, satisfies
us that the arbitration did not fail by any fault on the part of
the levee board, but by reason of the persistent attempts of the
plaintiffs, against the steady opposition of the levee board, to
introduce evidence before the board of arbitrament, not limited to
the question of measurement, which was the
Page 106 U. S. 408
only matter to be submitted to this board, but touching other
matters which had been concluded by the contracts executed and the
settlement made between the parties.
The result is that the decree below must be reversed, and the
case remanded with directions to enter a decree
Dismissing the bill.