1. Where a contractor performs labor and furnishes materials
upon a section or division of a railroad in Iowa then in the
process of construction, and there was a preexisting and duly
recorded mortgage executed by the company on its entire line of
road to secure its bonds.
Held that on filing his claim
within the time, and in the mode prescribed by the statute, he has,
as against the mortgagees, a paramount lien upon the entire
road.
2. A subcontractor, between whom and the contractor a settlement
had been made and the balance ascertained, filed within the
required time in the clerk's office of the proper court his claim
in due form against the contractor and the company, and, in a suit
whereto they were all parties, judgment establishing his lien on
the road was rendered. In a foreclosure suit subsequently brought
against the company and him, the mortgagees objected to the
validity of his lien because he had not also presented to the
company that settlement certified by the contractor to be just.
Held that the objection was not well taken.
The facts are stated in the opinion of the Court.
MR. JUSTICE MILLER delivered the opinion of the Court.
The appellants, who were complainants below, are trustees in a
mortgage made by the Burlington and Southwestern Railway
Page 101 U. S. 444
Company on its road and other property to secure $1,800,000 of
bonds put on the market and sold. They instituted this foreclosure
suit against the company, and brought in, during its progress,
other parties who were asserting mechanics' liens on the road. Of
these parties only the interest of O'Hara Brothers and Wells,
French, & Co., whose liens were by the court held to be
paramount to that of complainants, remain to be considered in the
appeal of the trustees from that decree.
The company was organized under the laws of Iowa to build a
railroad from Burlington, on the Mississippi River, in a
southwestern direction to some point on the Missouri River. From
the initial point, at Burlington, to Viele, in Lee County, Iowa,
they by contract used the track of a road already built between
Burlington and Keokuk. From Viele to Bloomfield, in Davis County,
they built and paid for their own track. From Bloomfield to
Moulton, in Appanoose County, fourteen miles, they used the road of
another company, already built, and from Moulton to Unionville, in
Missouri, they built their own road. It is for the work and labor
done and materials furnished on the latter piece of the road that
the lien of the appellees was allowed by the court on the road and
right of way, stations, &c., of the company from Viele
Junction, in Lee County, to the South Iowa State line, in Appanoose
County, in favor of O'Hara Brothers for $39,763.24, and in favor of
Wells, French, & Co., for $8,528.83.
It is conceded that the work for which these liens were allowed
was done for the company by the parties claiming them, and no
question is raised here as to its value, or to the liability of the
company to pay for it. The fact is undisputed that before any of it
was done, or the contract therefor made, the mortgage to the
complainants had been executed and duly recorded.
It was also undisputed that both the appellees, whose claim is
now contested, were subcontractors, and that the only contract
which the railway company made for labor and materials was with
another organization, known as the Mississippi and Missouri
Construction Company.
This purely artificial being, composed of the officers and
some
Page 101 U. S. 445
of the stockholders of the railway company, was organized for
the purpose of building this road. It belongs to a class of
corporations which have become well known of late years as
instruments to enable the officers of railroad companies to make
contracts with themselves to build the roads for their
stockholders. In the present case, this construction company having
sublet all the contract to one J. W. Barnes, very soon took itself
out of the way, and by an agreement between it and the railway
company, of which the following extract is found in the record, its
existence ceases to be of any further significance in this
contest:
"
Contract between B. & S. W. Railway Company and the
M. & M."
"
Construction Company Dated Feb. 6, 1873"
"The railway company assumes all outstanding liabilities of the
construction company, except officers' salaries. All previous
contracts between the two companies are annulled."
"The railway company assumes the contract of J. W. Barnes for
construction of portions of the main line and branch of the B.
& S. W. Railway Company, and the payment of all estimates due
and to become due thereon."
This leaves to be considered here the railway company, J. W.
Barnes, the principal contractor for construction of the road,
O'Hara Brothers, and Wells, French & Co., subcontractors, and
the complainants. It is also to be observed that before the present
foreclosure suit was begun O'Hara Brothers and Wells, French &
Co. had both commenced legal proceedings in the proper courts of
the State, and had, after a contest with the railway company,
obtained judgments establishing their liens. It was after this that
they were made defendants to this suit.
To those proceedings, Barnes, the principal contractor, and the
railway company were parties, and we take it for granted that as
against them the judgments establish the validity of the liens. The
judgments do not bind the appellants, as they were not parties
thereto. The validity of the liens as against them, and if valid,
their precedence to that of the mortgage, are the questions for
consideration here, and they must be determined by applying the
statutes of Iowa to the facts of this case.
Page 101 U. S. 446
By the law in force when these transactions took place, a
mechanic has, for labor done or things furnished, a lien on the
entire land upon which the building, erection, or
improvement was made, which had been held to include railroads, and
it shall be preferred to all other liens and encumbrances which
shall be attached to or upon such building, erection, or other
improvement made subsequently to the commencement of said building,
erection, or other improvement. Revision of 1860, sec. 1853; Code
of 1873, sec. 2139.
This provision, it will be observed, relates to the land on
which the improvement is made and gives the mechanic a paramount or
preferred lien only as against other liens and encumbrances created
subsequently to the beginning of his work. Those made
prior to that time are unaffected by it. But sec. 1855 of the
Revision, now sec. 2141 of the Code, makes a different provision in
regard to his lien on the
building, erection, and
improvement for which the lien is claimed. It reads thus:
"The lien for the things aforesaid on work shall attach to the
building, erections, or improvements for which they were
furnished or done, in preference to any prior lien or encumbrance
or mortgage upon the land upon which the same is erected or put,
and any person enforcing such lien may have such building,
erection, or other improvement sold under execution, and the
purchaser may remove the same within a reasonable time
thereafter."
The mechanic, therefore, has a lien upon the land paramount to
all rights accruing after the commencement of his work, and upon
what he puts upon the land paramount to all other claims, whether
created before or after that time. The decisions of the courts of
Iowa are to this effect and the proposition is not disputed in
argument here.
Have the subcontractors in this case taken the necessary steps
to establish their lien?
What is required to initiate the lien as to all other persons
but subcontractors is to be found in sec. 1851 of the Revision of
1860.
"Sec. 1851. It shall be the duty of every person, except as has
been provided for subcontractors, who wishes to avail himself of
the provisions of this chapter, to file with the clerk of the
district court
Page 101 U. S. 447
of the county in which the building, erection, or other
improvement to be charged with the lien is situated, and within
ninety days after all the things aforesaid shall have been
furnished, or work or labor done or performed, a just and true
account of the demand due or owing to him after allowing all
credits, and containing a correct description of the property to be
charged with said lien and verified by affidavit."
This section was subsequently modified by the following
statute:
"
An act to amend sec. 1851 of Revision of
1860,"
"
relating to Mechanics' Liens"
"Sec. 1. Be it enacted by the General Assembly of the State of
Iowa, that the following words are hereby added to sec. 1851 of
Revision of 1860, to-wit: "
"But the failure to file the claim, account, settlement, or
demand, in the time named in this section and in sec. 1847, shall
not operate to defeat the claim or demand, nor the lien of the
person supplying the labor or material, as against the owner nor
the contractor, nor as against any one except purchasers or
encumbrancers, without notice, whose rights accrued after the
ninety days and before the account, or settlement, or claim, or
lien is filed."
"Approved April 7, 1862."
The statute, however, makes provision that a subcontractor who
shall do the work which his principal had contracted to do shall by
proper proceeding secure to himself the lien which arises from the
work done or materials furnished. In such case there is a more
complex affair. There are here the owner of the property, the
principal contractor, and the subcontractor, who, as well as prior
and subsequent encumbrancers or lien holders, have rights to be
affected. It may generally be supposed that the principal
contractor has sublet his contract so as to leave a profit to
himself. He is entitled, therefore, to see that his subcontractor
does not take this profit. The owner is not bound for more than he
agreed to pay the principal contractor. In view of these interests,
sec. 1847 of the Revision, sec. 2131 of the Code of 1873, enacts
that every subcontractor wishing to avail himself of the benefit of
the act, shall give notice to the owner of the land, before or at
the time he furnishes any of the materials or performs any of the
labor, of his intention
Page 101 U. S. 448
to perform or furnish the same, and afterwards he shall settle
with the contractor therefor, and having made the settlement in
writing, the same, signed by the contractor and certified by him to
be just, shall be presented to the owner. He is also required,
within thirty days from the time the things shall have been
furnished or the labor performed, to file with the clerk of the
district court of the county in which the building is situated a
copy of said settlement, and a correct description of the property
to be charged with the lien, the correctness of which shall be
verified by oath. As we have already seen, the act of 1862 declares
that a failure to file this settlement shall not operate to defeat
the lien as against any one except purchasers or encumbrancers
without notice, whose rights accrued after ninety days, and before
the account or settlement or lien claim is filed.
Appellants are not within this exception.
The record shows that there was filed in the office of the Clerk
of the District Court of Appanoose County, on the 31st of October,
1872, a statement by O'Hara Brothers of a claim against J. W.
Barnes, the principal contractor, and against the railroad company,
of a mechanic's lien on their line of said road, from Viele, in Lee
County, through Van Buren, Davis, and Appanoose Counties, in the
State of Iowa, for work and labor done and to be done and materials
furnished under Barnes's contract, in which they said they had
already done work to the amount of $265,000, of which $130,000 had
been paid. This was verified by the oath of O'Hara. An agreed
statement of facts in the present suit states that, in filing their
respective claims for mechanics' liens, settlements had been made
between the subcontractors and Barnes, and that the amounts claimed
had been agreed to by Barnes in these several settlements.
It is now urged by appellants against the validity of these
liens that the notice of the lien to the railway company, which the
statute required from the subcontractor, was never given, and if
any direct written notice was necessary to the establishment of the
lien in this suit it must be admitted that it is not proved.
But we think there are two sufficient answers to this
objections:
Page 101 U. S. 449
1. It is obvious that this notice to the owner of the property
is for the purpose of enabling him to protect himself in his
dealings with the principal contractor, so that he shall neither
overpay the amount of the contract with the subcontractor, nor
embarrass himself by having to deal with two contractors. This
dealing with two contractors instead of one being an obligation
which the law imposes on him for the benefit of the subcontractor,
this notice is required for his protection. It can have nothing to
do with the validity of the lien beyond ascertaining the amount of
it to which the subcontractor is entitled as between those three.
With prior liens it has nothing to do, and can have no effect on
the rights of the holders of them. The initial proceeding for the
establishment of the lien, on which all others rest, is the claim
filed in the clerk's office of the proper court. In the case of
Bundy v. The K. & D. M. R. Co., 49 Ia. 207, the
supreme court of the state held that the paper thus filed by a
subcontractor imparted notice to the owner and principal contractor
of the condition of the account between the parties.
2. Since this notice is designed for the protection of the
owner, and was to be given to him, the judgment of the state court
of Iowa establishing this lien against the railroad company is
conclusive on that subject, and with that question the complainants
in this court have nothing to do.
The next objection very strongly urged by counsel for appellants
is thus stated in the assignment of errors: the court erred in
decreeing a lien on the property in Davis, Van Buren, and Lee
Counties, the first division of the road, for work done in
Appanoose County, the next division, on a contract which was dated
and work begun after recording the mortgage in the latter
county.
As we understand this objection, it is founded on the idea that
while, if the whole road had been uninterruptedly built under one
contract, the lien of the contractors and subcontractors would have
been good against the whole road, though they had contributed only
to the building of a limited portion of it, yet because these
subcontractors were only employed on one division of the road,
after another had been finished, and under a distinct contract with
the company made after that completion, the lien can only attach to
the last section of the
Page 101 U. S. 450
road, and even this is subordinate to the mortgage of the
appellants.
One branch of the question here raised was very fully considered
in the case of
Neilson v. Iowa Eastern Railway Company, 44
Ia. 71. That was a case where, after the building of a railroad had
been commenced, a mortgage was executed on its whole line, both
where work had been done and where none had been done. After this,
the building of the road was continued under new contracts by
persons who did work on the other parts of the road, and the
question was whether they had any lien prior to that of the
mortgage, and if so, whether it extended to all the road or only to
that part built under the new contracts.
The court, after mature deliberation, decided both these
questions in favor of the contractors. It held that the road was an
entire improvement, within the meaning of the act, and that the
continuance of it was a matter to be taken into the calculation of
the mortgagees when the mortgage was made, and the lien for that
work was by the statute given on the road as one improvement. The
court, speaking of the policy of the statute, said
"It is not desirable that the execution of a mortgage upon land
on which a building or other improvement is in process of
construction should arrest the work and prevent its completion.
Both mortgagor and mortgagee are interested in its completion.
Without it the money already expended must ordinarily to a great
extent be lost. Take the present case as illustrative. The
interveners are holders of mortgage bonds upon a road, sixteen
miles of which had been graded at the time the mortgage was made.
The value of their security depended upon the further construction
of the work. They foresaw that work and materials must be furnished
by somebody, or nothing could be realized from what had been
done."
But the argument most confidently urged here is that the road
was built in sections, and that there was such a separation in
space and time in the construction of them that they cannot be
considered as one improvement within the meaning of the statute.
The argument is that the road from Viele to Bloomfield is one road;
that then it is interrupted, and the track of another company is
used from Bloomfield to Moulton;
Page 101 U. S. 451
that there another road begins which was constructed under
another contract, and that no lien for work done here can attach to
the road between Viele and Bloomfield.
The argument seems to us extremely technical, and at war with
the principle in which liens are allowed for work done subsequently
to the creation of a mortgage. That doctrine, or rather the statute
which the courts construed as giving a permanent lien under such
circumstances, was in existence when the mortgage of the appellants
was made. It entered into and became a part of their contract. They
knew that the road was yet to be built, and that while such
building would add to the value of their security, the law gave to
the men whose labor and money built it a lien superior to that of
the mortgage. Now that the venture in which both embarked is to end
in loss to one or the other of them, there is no judicial propriety
in straining the law to limit the rights of one party rather than
those of the other. If that law by its fair construction gives the
mechanic a lien for a few thousand dollars on the whole road,
instead of a part of it, the law should prevail.
In every respect except this one of its construction, the road
is a unit, an entirety. Its route is selected and surveyed as one
road. It is owned and built and run by one corporation. Its trains
run over it all. The mortgage of appellants can have no lien on any
of the road beyond the first few miles upon any other theory, for
its descriptive language refers to the road as one and not as
several subdivisions. It is not easy to see how it can be held to
be one road for the purposes of the mortgage, and two or three
pieces of road for the purposes of the mechanics' lien. This
continuation of the road beyond Bloomfield was as useful to the
security of that mortgage as the part between Viele and Bloomfield.
Though the work was done from Moulton under another contract, there
was never any suspension of the work on the whole road beyond what
is usual in roads built with limited means. There was never any
permanent arrest of the work, nor any intention to cease work on
the road. The intersection of fourteen miles of another road
between Bloomfield and Moulton does not destroy the identity of the
improvement, nor convert it into two railroads.
Page 101 U. S. 452
Canal Company v.
Gordon, 6 Wall. 561, is much relied on by
appellants, and in one of its features -- that now under
consideration -- it bears some analogy to this case. There,
however, the part of the canal first finished, and which was held
not to be subject to a lien for work done on that constructed
afterwards, had been in full operation for some time. How long it
had been finished and in use before work was begun on the new part
is not stated in the report of the case. It may have been long
enough to justify the belief that for a time the further
prosecution of the work was abandoned, and its resumption an
afterthought.
In the case before us the purpose of discontinuing the road was
never for a moment entertained, and the actual work was resumed in
a few months after its completion to Bloomfield. In that case the
decision depended on the construction of a statute of California
which used the word "structure" where the Iowa statute uses the
word "improvement."
In that case, as was said in the opinion, we had no aid from any
decision of the courts of the State. In the one before us, we have
several decisions of the Iowa court.
Neilson v. Iowa Eastern
Railway Company, 44 Ia. 71;
Equitable Life Insurance
Company v. Slye, 45
id. 615.
"A mechanic's lien," says the court in the latter case,
"can, it is true, become paramount to a mortgage executed upon a
partially erected building, provided the work be done or materials
furnished for the purpose of completing the building. This is the
plain provision of the statute, and, to our mind, it is not
unreasonable. Whoever takes a mortgage upon a building in the
process of erection should assume that the mechanics' work is to go
forward, and he may form some estimate of the amount that will be
required. The same is not true in regard to repairs or
enlargements."
If
Canal Company v. Gordon, supra, is at variance with
the decision of the courts of Iowa construing her own statute, we
must follow the latter. They also meet our approval.
Without examining other objections to the decree, or those to
the lien of Wells, French, & Co., we think what we have said
covers the case.
Decree affirmed.