Citadel FNGE Ltd. v. FERC, No. 22-1090 (D.C. Cir. 2023)
Annotate this Case
This case concerns how PJM, the manager of a large, multi-state electrical grid, prices the flow of electricity to utilities in times of congestion. Such congestion arises when energy is scarce in a particular location on the grid due to, for example, extreme weather conditions or a fire at a transmission station. That scarcity causes the dispatch of more expensive generation and can trigger the Transmission Constraint Penalty Factor (“Penalty Factor”) when such alternative generation is unavailable. The Penalty Factor imposes an upper bound on the costs PJM will incur to control a transmission constraint, and it is designed to send transparent price signals to the market and incentivize investment that will resolve the congestion and prevent it from recurring. Petitioner Citadel FNGE Ltd. is an energy trading firm. It challenged the Commission’s suspension of the Penalty Factor as arbitrary and capricious.
The DC Circuit denied the petitions. The court explained that substantial evidence supported the Commission’s decision that the Penalty Factor, as applied to the unique Northern Neck circumstances, could not work as designed because it increased costs without incentivizing supply or demand responses. Because application of the Penalty Factor increased costs for consumers without a commensurate benefit, the Commission reasonably found that its application in this context was unjust and unreasonable.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.