The Forest Service is authorized by statute to manage national
forests for,
inter alia, recreational purposes. Because
its decision to issue a recreational special use permit is a "major
Federal action" within the meaning of the National Environmental
Policy Act of 1969 (NEPA), that decision must be preceded by the
preparation of an Environmental Impact Statement (EIS). After a
Service study designated a particular national forest location as
having a high potential for development as a major downhill ski
resort, Methow Recreation, Inc. (MRI), applied for a special use
permit to develop and operate such a resort on that site and on
adjacent private land MRI had acquired. In cooperation with state
and local officials, the Service prepared an EIS (the Study),
which, among other things, considered the effects of various levels
of development on wildlife and air quality both on-site and -- as
required by Council on Environmental Quality (CEQ) regulations --
off-site, and outlined steps that might be taken to mitigate
adverse effects, indicating that these proposed steps were merely
conceptual, and would "be made more specific as part of the design
and implementation stages of the planning process." The Study's
proposed options regarding off-site mitigation measures were
primarily directed to steps that might be taken by state and local
governments. After the Regional Forester decided to issue a permit
as recommended by the Study, respondents appealed to the Chief of
the Forest Service, who affirmed. Respondents then brought suit to
review the Service's decision, claiming that the Study did not
satisfy NEPA's requirements. The District Court's Magistrate filed
an opinion concluding that the Study was adequate, but the Court of
Appeals reversed, concluding that the Study was inadequate as a
matter of law on the grounds,
inter alia, that NEPA
imposes a substantive duty on agencies to take action to mitigate
the adverse effects of major federal actions, which entails the
further duty to include in every EIS a detailed explanation of
specific actions that will be employed to mitigate the adverse
impact; that if the Service had difficulty obtaining adequate
information to make a reasoned assessment of the project's
environmental impact, it had an obligation to make a "worst
Page 490 U. S. 333
case analysis" on the basis of available information, using
reasonable projections of the worst possible consequences; and that
the Service's failure to develop a complete mitigation plan
violated its own regulations.
Held:
1. NEPA does not impose a substantive duty on agencies to
mitigate adverse environmental effects or to include in each EIS a
fully developed mitigation plan. Although the EIS requirement and
NEPA's other "action-forcing" procedures implement that statute's
sweeping policy goals by ensuring that agencies will take a "hard
look" at environmental consequences and by guaranteeing broad
public dissemination of relevant information, it is well settled
that NEPA itself does not impose substantive duties mandating
particular results, but simply prescribes the necessary process for
preventing uninformed -- rather than unwise -- agency action. While
a reasonably complete discussion of possible mitigation measures is
an important ingredient of an EIS, and its omission therefrom would
undermine NEPA's "action-forcing" function, there is a fundamental
distinction between a requirement that mitigation be discussed in
sufficient detail to ensure that environmental consequences have
been fairly evaluated and a substantive requirement that a complete
mitigation plan be actually formulated and adopted. Here, since the
off-site environmental effects of the project cannot be mitigated
unless the nonfederal government agencies having jurisdiction over
the off-site area take appropriate action, it would be incongruous
to conclude that the Service has no power to act until the local
agencies have finally determined what mitigation measures are
necessary. More significantly, it would be inconsistent with NEPA's
reliance on procedural mechanisms -- as opposed to substantive,
result-based standards -- to demand the presence of a fully
developed mitigation plan before the agency can act. Pp.
490 U. S.
348-353.
2. NEPA does not impose a duty on an agency to make a "worst
case analysis" in its EIS if it cannot make a reasoned assessment
of a proposed project's environmental impact. Although prior CEQ
regulations requiring such an analysis may well have expressed a
permissible interpretation of NEPA, those regulations have since
been amended to replace the worst case requirement with new
requirements, and the Act itself does not mandate that uncertainty
in predicting environmental harms be addressed exclusively by a
worst case analysis. The Court of Appeals erred in concluding that
the worst case regulation was a codification of prior NEPA case
law, which, in fact, merely required agencies to describe
environmental impacts even in the face of substantial uncertainty.
Moreover, the new CEQ regulations -- which require that agencies,
in the face of unavailable information concerning a reasonably
foreseeable
Page 490 U. S. 334
significant environmental consequence, prepare a summary of
existing relevant and credible scientific evidence and an
evaluation of adverse impacts based on generally accepted
scientific approaches or research methods -- is entitled to
substantial deference even though the worst case rule was in some
respects more demanding, since there was good reason for the change
in light of the substantial criticism to which the old regulation
was subjected, and since the amendment was designed to better serve
the EIS' "hard look" and public disclosure functions in preference
to distorting the decisionmaking process by overemphasizing highly
speculative harms. Pp.
490 U. S.
354-356.
3. The Court of Appeals erred in concluding that the Service's
failure to develop a complete mitigation plan violated its own
regulations, which require,
inter alia, that "[e]ach
special use authorization . . . contain . . . [t]erms and
conditions which will . . . minimize damage to . . . the
environment." Since the Study made clear that on-site effects of
the proposed development will be minimal and easily mitigated, its
recommended ameliorative steps cannot be deemed overly vague or
underdeveloped. Moreover, although NEPA and CEQ regulations require
detailed analysis of off-site mitigation measures, there is no
basis to conclude that the Service's own regulations must also be
read in all cases to condition permit issuance on consideration
(and implementation) of such measures. The Service's regulations
were promulgated pursuant to its broad statutory authorization to
allow recreational use of national forests, and were not based on
NEPA's more direct concern for environmental quality. As is clear
from the text of the permit issued to MRI, the Service has decided
to implement its mitigation regulations by imposing appropriate
controls over MRI's actual development and operation during the
permit's term. It was not unreasonable for the Service to have
construed those regulations as not extending to off-site mitigation
efforts that might be taken by state and local authorities, and
that interpretation is controlling. Pp.
490 U. S.
357-359.
833 F.2d 810, reversed and remanded.
STEVENS, J., delivered the opinion for a unanimous Court.
BRENNAN, J., filed a concurring statement.
Page 490 U. S. 335
JUSTICE STEVENS delivered the opinion of the Court.
We granted certiorari to decide two questions of law. [
Footnote 1] As framed by petitioners,
they are:
"1. Whether the National Environmental Policy Act requires
federal agencies to include in each environmental impact statement:
(a) a fully developed plan to mitigate
Page 490 U. S. 336
environmental harm; and (b) a 'worst case' analysis of potential
environmental harm if relevant information concerning significant
environmental effects is unavailable or too costly to obtain."
"2. Whether the Forest Service may issue a special use permit
for recreational use of national forest land in the absence of a
fully developed plan to mitigate environmental harm."
Pet. for Cert. i. Concluding that the Court of Appeals for the
Ninth Circuit misapplied the National Environmental Policy Act of
1969 (NEPA), 83 Stat. 852, 42 U.S.C. § 4321
et seq., and
gave inadequate deference to the Forest Service's interpretation of
its own regulations, we reverse and remand for further
proceedings.
I
The Forest Service is authorized by statute to manage the
national forests for "outdoor recreation, range, timber, watershed,
and wildlife and fish purposes." 74 Stat. 215, 16 U.S.C. § 528.
See also 90 Stat. 2949, 16 U.S.C. § 1600
et seq.
Pursuant to that authorization, the Forest Service has issued
"special use" permits for the operation of approximately 170 alpine
and nordic ski areas on federal lands.
See H.R.Rep. No.
99-709, pt. 1, p. 2 (1986).
The Forest Service permit process involves three separate
stages. The Forest Service first examines the general environmental
and financial feasibility of a proposed project and decides whether
to issue a special use permit.
See 36 CFR § 251.54(f)
(1988). Because that decision is a "major Federal action" within
the meaning of NEPA, it must be preceded by the preparation of an
Environmental Impact Statement (EIS). 42 U.S.C. § 4332. If the
Service decides to issue a permit, it then proceeds to select a
developer, formulate the basic terms of the arrangement with the
selected party,
Page 490 U. S. 337
and issue the permit. [
Footnote
2] The special use permit does not, however, give the developer
the right to begin construction.
See 36 CFR § 251.56(c)
(1988). In a final stage of review, the Service evaluates the
permittee's "master plan" for development, construction, and
operation of the project. Construction may begin only after an
additional environmental analysis (although it is not clear that a
second EIS need always be prepared) and final approval of the
developer's master plan. This case arises out of the Forest
Service's decision to issue a special use permit authorizing the
development of a major destination alpine ski resort at Sandy Butte
in the North Cascade Mountains.
Sandy Butte is a 6,000-foot mountain located in the Okanogan
National Forest in Okanogan County, Washington. At present, Sandy
Butte, like the Methow Valley it overlooks, is an unspoiled,
sparsely populated area that the District Court characterized as
"pristine." App. to Pet. for Cert. 20a. In 1968, Congress
established the North Cascades National Park, and directed the
Secretaries of Interior and Agriculture to agree on the designation
of areas within, and adjacent to, the park for public uses,
including ski areas. 82 Stat. 926, 930, 16 U.S.C. §§ 90, 90d-3. A
1970 study conducted by the Forest Service pursuant to this
congressional directive identified Sandy Butte as having the
highest potential of any site in the State of Washington for
development as a major downhill ski resort. [
Footnote 3] App. to Pet. for Cert. 23a.
Page 490 U. S. 338
In 1978, Methow Recreation, Inc. (MRI), applied for a special
use permit to develop and operate its proposed "Early Winters Ski
Resort" on Sandy Butte and a 1,165-acre parcel of land it had
acquired adjacent to the National Forest. The proposed development
would make use of approximately 3,900 acres of Sandy Butte; would
entice visitors to travel long distances to stay at the resort for
several days at a time; and would stimulate extensive commercial
and residential growth in the vicinity to accommodate both
vacationers and staff.
In response to MRI's application, the Forest Service, in
cooperation with state and county officials, prepared an EIS known
as the Early Winters Alpine Winter Sports Study (Early Winters
Study or Study). The stated purpose of the EIS was "to provide the
information required to evaluate the potential for skiing at Early
Winters" and
"to assist in making a decision whether to issue a Special Use
Permit for downhill skiing on all or a portion of approximately
3900 acres of National Forest System land."
Early Winters Study 1. A draft of the Study was completed and
circulated in 1982, but release of the final EIS was delayed as
Congress considered including Sandy Butte in a proposed wilderness
area. App. to Pet. for Cert. 26a. When the Washington State
Wilderness Act of 1984 was passed, however, Sandy Butte was
excluded from the wilderness designation, [
Footnote 4] and the EIS was released.
Page 490 U. S. 339
The Early Winters Study is a printed document containing almost
150 pages of text and 12 appendices. It evaluated five alternative
levels of development of Sandy Butte that might be authorized, the
lowest being a "no action" alternative and the highest being
development of a 16-1ift ski area able to accommodate 10,500 skiers
at one time. The Study considered the effect of each level of
development on water resources, soil, wildlife, air quality,
vegetation, and visual quality, as well as land use and
transportation in the Methow Valley, probable demographic shifts,
the economic market for skiing and other summer and winter
recreational activities in the Valley, and the energy requirements
for the ski area and related developments. The Study's discussion
of possible impacts was not limited to on-site effects, but also,
as required by Council on Environmental Quality (CEQ) regulations,
see 40 CFR § 1502.16(b) (1987), addressed
"off-site impacts that each alternative might have on community
facilities, socioeconomic and other environmental conditions in the
Upper Methow Valley."
Early Winters Study 1. As to off-site effects, the Study
explained that "due to the uncertainty of where other public and
private lands may become developed," it is difficult to evaluate
off-site impacts,
id. at 76, and thus the document's
analysis is necessarily "not site-specific,"
id. at 1.
Finally, the Study outlined certain steps that might be taken to
mitigate adverse effects, both on Sandy Butte and in the
neighboring Methow Valley, but indicated that these proposed steps
are merely conceptual, and "will be made more specific as part of
the design and implementation stages of the planning process."
Id. at 14.
The effects of the proposed development on air quality and
wildlife received particular attention in the Study. In the chapter
on "Environmental Consequences," the first subject discussed is air
quality. As is true of other subjects, the discussion included an
analysis of cumulative impacts over several
Page 490 U. S. 340
years resulting from actions on other lands as well as from the
development of Sandy Butte itself. The Study concluded that,
although the construction, maintenance, and operation of the
proposed ski area "will not have a measurable effect on existing or
future air quality," the off-site development of private land under
all five alternatives -- including the "no action" alternative --
"will have a significant effect on air quality during severe
meteorological inversion periods."
Id. at 65. The burning
of wood for space heat, the Study explained, would constitute the
primary cause of diminished air quality, and the damage would
increase incrementally with each of the successive levels of
proposed development.
Ibid. The Study cautioned that.
without efforts to mitigate these effects, even under the "no
action" alternative, the increase in automobile, fireplace, and
wood stove use would reduce air quality below state standards, but
added that "[t]he numerous mitigation measures discussed" in the
Study "will greatly reduce the impacts presented by the model."
Id. at 67.
In its discussion of air quality mitigation measures, the EIS
identified actions that could be taken by the county government to
mitigate the adverse effects of development, as well as those that
the Forest Service itself could implement at the construction stage
of the project. The Study suggested that Okanogan County develop an
air quality management plan, requiring weatherization of new
buildings, limiting the number of wood stoves and fireplaces, and
adopting monitoring and enforcement measures. [
Footnote 5] In addition, the
Page 490 U. S. 341
Study suggested that the Forest Service require that the master
plan include procedures to control dust and to comply with smoke
management practices. [
Footnote
6]
In its discussion of adverse effects on area wildlife, the EIS
concluded that no endangered or threatened species would be
affected by the proposed development, and that the only impact on
sensitive species was the probable loss of a pair of spotted owls
and their progeny.
Id. at 75. With regard to other
wildlife, the Study considered the impact on 75 different
Page 490 U. S. 342
indigenous species and predicted that, within a decade after
development, vegetational change and increased human activity would
lead to a decrease in population for 31 species, while causing an
increase in population for another 24 species on Sandy Butte.
Ibid. Two species, the pine marten and nesting goshawk,
would be eliminated altogether from the area of development.
Ibid.
In a comment in response to the draft EIS, the Washington
Department of Game voiced a special concern about potential losses
to the State's largest migratory deer herd, which uses the Methow
Valley as a critical winter range and as its migration route.
Id. at Appendix D (letter of November 18, 1982). The state
agency estimated that the total population of mule deer in the area
most likely to be affected was "better than 30,000 animals," and
that "the ultimate impact on the Methow deer herd could exceed a 50
percent reduction in numbers."
Ibid. The agency asserted
that "Okanogan County residents place a great deal of importance on
the area's deer herd."
Ibid. In addition, it explained
that hunters had "harvested" 3,247 deer in the Methow Valley area
in 1981, and that, since, in 1980, hunters on average spent $1,980
for each deer killed in Washington, they had contributed over $6
million to the State's economy in 1981. Because the deer harvest is
apparently proportional to the size of the herd, the state agency
predicted that "Washington business can expect to lose over $3
million annually from reduced recreational opportunity."
Ibid. The Forest Service's own analysis of the impact on
the deer herd was more modest. It first concluded that the actual
operation of the ski hill would have only a "minor" direct impact
on the herd, [
Footnote 7] but
then recognized
Page 490 U. S. 343
that the off-site effect of the development "would noticeably
reduce numbers of deer in the Methow [Valley] with any
alternative."
Id. at 76. Although its estimate indicated a
possible 15 percent decrease in the size of the herd, it summarized
the State's contrary view in the text of the EIS, and stressed that
off-site effects are difficult to estimate due to uncertainty
concerning private development.
Ibid.
As was true of its discussion of air quality, the EIS also
described both on-site and off-site mitigation measures. Among
possible on-site mitigation possibilities, the Study recommended
locating runs, ski lifts, and roads so as to minimize interference
with wildlife, restricting access to selected roads during fawning
season, and further examination of the effect of the development on
mule deer migration routes. [
Footnote 8] Off-site options discussed in the Study
included the use of zoning and tax incentives to limit development
on deer winter range and migration routes, encouragement of
conservation easements, and acquisition and management by local
Page 490 U. S. 344
government of critical tracts of land. [
Footnote 9] As with the measures suggested for
mitigating the off-site effects on air quality, the proposed
options were primarily directed to steps that might be taken by
state and local government.
Ultimately, the Early Winters Study recommended the issuance of
a permit for development at the second highest level considered --
a 16-1ift ski area able to accommodate 8,200 skiers at one time. On
July 5, 1984, the Regional Forester decided to issue a special use
permit as recommended by the
Page 490 U. S. 345
Study. [
Footnote 10] App.
to Pet. for Cert. 63a. In his decision, the Regional Forester found
that no major adverse effects would result directly from the
federal action, but that secondary effects could include a
degradation of existing air quality and a reduction of mule deer
winter range.
Id. at 67a. He therefore directed the
supervisor of the Okanogan National Forest, both independently and
in cooperation with local officials, to identify and implement
certain mitigating measures.
Id. at 67a-70a.
Four organizations (respondents) [
Footnote 11] opposing the decision to issue a permit
appealed the Regional Forester's decision to the Chief of the
Forest Service.
See 36 CFR § 211.18 (1988). After a
hearing, he affirmed the Regional Forester's decision. Stressing
that the decision, which simply approved the general concept of
issuing a 30-year special use permit for development of Sandy
Butte, did not authorize construction of a particular ski area and,
in fact, did not even act on MRI's specific permit application, he
concluded that the EIS' discussion of mitigation was "adequate for
this stage in the review process." App. to Pet. for Cert. 59a.
Thereafter, respondents brought this action under the
Administrative Procedure Act, 5 U.S.C. §§ 701-706, to obtain
judicial review of the Forest Service's decision. Their principal
claim was that the Early Winters Study did not satisfy
Page 490 U. S. 346
the requirements of NEPA, 42 U.S.C. § 4332. [
Footnote 12] With the consent of the
parties, the case was assigned to a United States Magistrate.
See 28 U.S.C. § 636(c). After a trial, the Magistrate
filed a comprehensive written opinion and concluded that the EIS
was adequate. App. to Pet. for Cert. 20a. Specifically, he found
that the EIS had adequately disclosed the adverse impacts on the
mule deer herd and on air quality, and that there was no duty to
prepare a "worst case analysis" because the relevant information
essential to a reasoned decision was available.
Id. at
39a-44a. In concluding that the discussion of off-site, or
secondary, impacts was adequate, the Magistrate stressed that
courts apply a "rule of reason" in evaluating the adequacy of an
EIS, and
"take the uncertainty and speculation involved with secondary
impacts into account in passing on the adequacy of the discussion
of secondary impacts."
Id. at 38a. On the subject of mitigation, he explained
that "[m]ere listing . . . is generally inadequate to satisfy the
CEQ regulations," but found that "in this EIS there is more -- not
much more -- but more than a mere listing of mitigation measures."
Id. at 41a. Moreover, emphasizing the tiered nature of the
Forest Service's decisional process, the Magistrate noted that
additional mitigation strategies would be included in the master
plan, that the Forest Service continues to develop mitigation plans
as further information becomes available, and that the Regional
Forester's decision conditioned issuance of the special use permit
on execution of an agreement between the Forest Service, the State
of Washington, and Okanogan County concerning mitigation.
Id. at 41a-42a, 45a.
Concluding that the Early Winters Study was inadequate as a
matter of law, the Court of Appeals reversed.
Methow Valley
Citizens Council v. Regional Forester, 833 F.2d 810
Page 490 U. S. 347
(CA9 1987). The court held that the Forest Service could not
rely on "
the implementation of mitigation measures'" to support
its conclusion that the impact on the mule deer would be
minor,
"since not only has the effectiveness of these mitigation
measures not yet been assessed, but the mitigation measures
themselves have yet to be developed."
Id. at 817. It then added that, if the agency had
difficulty obtaining adequate information to make a reasoned
assessment of the environmental impact on the herd, it had a duty
to make a so-called "worst case analysis." Such an analysis is
"'formulated on the basis of available information, using
reasonable projections of the worst possible consequences of a
proposed action.'
Save Our Ecosystems, 747 F.2d at 1244-45
(quoting 46 Fed.Reg. 18032 (1981))."
Ibid.
The court found a similar defect in the EIS' treatment of air
quality. Since the EIS made it clear that commercial development in
the Methow Valley will result in violations of state air quality
standards unless effective mitigation measures are put in place by
the local governments and the private developer, the Court of
Appeals concluded that the Forest Service had an affirmative duty
to "develop the necessary mitigation measures
before the
permit is granted."
Id. at 819 (emphasis in original)
(footnote omitted). The court held that this duty was imposed by
both the Forest Service's own regulations and § 102 of NEPA.
Ibid. It read the statute as imposing a substantive
requirement that "
action be taken to mitigate the adverse
effects of major federal actions.'" Ibid. (quoting
Stop H-3 Assn. v. Brinegar, 389
F. Supp. 1102, 1111 (Haw.1974), rev'd on other
grounds, 533 F.2d 434 (CA9), cert. denied, 429 U.S.
999 (1976)). For this reason, it concluded that "an EIS must
include a fair discussion of measures to mitigate the adverse
environmental impacts of a proposed action." 833 F.2d at 819. The
Court of Appeals concluded by quoting this paragraph from an
opinion it had just announced:
"'The importance of the mitigation plan cannot be overestimated.
It is a determinative factor in evaluatting
Page 490 U. S. 348
the adequacy of an environmental impact statement. Without a
complete mitigation plan, the decisionmaker is unable to make an
informed judgment as to the environmental impact of the project --
one of the main purposes of an environmental impact
statement.'"
Id. at 820 (quoting
Oregon Natural Resources
Council v. Marsh, 832 F.2d 1489, 1493 (CA9 1987),
rev'd,
post, p.
490 U. S.
360).
II
Section 101 of NEPA declares a broad national commitment to
protecting and promoting environmental quality. 83 Stat. 852, 42
U.S.C. § 4331. To ensure that this commitment is
"infused into the ongoing programs and actions of the Federal
Government, the act also establishes some important
'action-forcing' procedures."
115 Cong.Rec. 40416 (remarks of Sen. Jackson).
See also
S.Rep. No. 91-296, p.19 (1969);
Andrus v. Sierra Club,
442 U. S. 347,
442 U. S. 350
(1979);
Kleppe v. Sierra Club, 427 U.
S. 390,
427 U. S. 409,
and n. 18 (1976). Section 102 thus, among other measures
"directs that, to the fullest extent possible . . . all agencies
of the Federal Government shall -- "
"
* * * *"
"(C) include in every recommendation or report on proposals for
legislation and other major Federal actions significantly affecting
the quality of the human environment, a detailed statement by the
responsible official on -- "
"(i) the environmental impact of the proposed
Page 490 U. S. 349
action,"
"(ii) any adverse environmental effects which cannot be avoided
should the proposal be implemented,"
"(iii) alternatives to the proposed action,"
"(iv) the relationship between local short-term uses of man's
environment and the maintenance and enhancement of long-term
productivity, and"
"(v) any irreversible and irretrievable commitments of resources
which would be involved in the proposed action should it be
implemented."
83 Stat. 853, 42 U.S.C. § 4332.
The statutory requirement that a federal agency contemplating a
major action prepare such an environmental impact statement serves
NEPA's "action-forcing" purpose in two important respects.
See
Baltimore Gas & Electric Co. v. Natural Resources Defense
Council, Inc., 462 U. S. 87,
462 U. S. 97
(1983);
Weinberger v. Catholic Action of Hawaii/Peace Education
Project, 454 U. S. 139,
454 U. S. 143
(1981). It ensures that the agency, in reaching its decision, will
have available, and will carefully consider, detailed information
concerning significant environmental impacts; it also guarantees
that the relevant information will be made available to the larger
audience that may also play a role in both the decisionmaking
process and the implementation of that decision.
Simply by focusing the agency's attention on the environmental
consequences of a proposed project, NEPA ensures that important
effects will not be overlooked or underestimated, only to be
discovered after resources have been committed or the die otherwise
cast.
See ibid.; Kleppe, supra, at
426 U. S. 409.
Moreover, the strong precatory language of § 101 of the Act and the
requirement that agencies prepare detailed impact statements
inevitably bring pressure to bear on agencies "to respond to the
needs of environmental quality." 115 Cong.Rec. 40425 (1969)
(remarks of Sen. Muskie).
Publication of an EIS, both in draft and final form, also serves
a larger informational role. It gives the public the assurance that
the agency "has indeed considered environmental concerns in its
decisionmaking process,"
Baltimore Gas & Electric Co.,
supra, at
462 U. S. 97,
and, perhaps more significantly, provides a springboard for public
comment,
see L. Caldwell, Science and the National
Environmental Policy Act 72 (1982). Thus, in this case the final
draft of the Early Winters Study reflects not only the work of the
Forest Service itself, but also the critical views of the
Washington State Department of Game, the Methow Valley Citizens
Council, and
Page 490 U. S. 350
Friends of the Earth, as well as many others, to whom copies of
the draft Study were circulated. [
Footnote 13]
See Early Winters Study, Appendix
D. Moreover, with respect to a development such as Sandy Butte,
where the adverse effects on air quality and the mule deer herd are
primarily attributable to predicted off-site development that will
be subject to regulation by other governmental bodies, the EIS
serves the function of offering those bodies adequate notice of the
expected consequences and the opportunity to plan and implement
corrective measures in a timely manner.
The sweeping policy goals announced in § 101 of NEPA are thus
realized through a set of "action-forcing" procedures that require
that agencies take a "
hard look' at environmental
consequences," Kleppe, 427 U.S. at 427 U. S. 410,
n. 21 (citation omitted), and that provide for broad dissemination
of relevant environmental information. Although these procedures
are almost certain to affect the agency's substantive decision, it
is now well settled that NEPA itself does not mandate particular
results, but simply prescribes the necessary process. See
Strycker's Bay Neighborhood Council, Inc. v. Karlen,
444 U. S. 223,
444 U. S.
227-228 (1980) (per curiam); Vermont Yankee Nuclear
Power Corp. v. Natural Resources Defense Council, Inc.,
435 U. S. 519,
435 U. S. 558
(1978). If the adverse environmental effects of the proposed action
are adequately identified and evaluated, the agency is not
constrained by NEPA from deciding that other values outweigh the
environmental costs. See ibid.; Strycker's Bay Neighborhood
Council, Inc., supra, at 444 U. S.
227-228; Kleppe, supra, at 472 U. S. 410,
n. 21. In this
Page 490 U. S. 351
case, for example, it would not have violated NEPA if the Forest
Service, after complying with the Act's procedural prerequisites,
had decided that the benefits to be derived from downhill skiing at
Sandy Butte justified the issuance of a special use permit,
notwithstanding the loss of 15 percent, 50 percent, or even 100
percent of the mule deer herd. Other statutes may impose
substantive environmental obligations on federal agencies,
[
Footnote 14] but NEPA
merely prohibits uninformed -- rather than unwise -- agency
action.
To be sure, one important ingredient of an EIS is the discussion
of steps that can be taken to mitigate adverse environmental
consequences. [
Footnote 15]
The requirement that an EIS contain a detailed discussion of
possible mitigation measures flows both from the language of the
Act and, more expressly, from CEQ's implementing regulations.
Implicit in NEPA's demand that an agency prepare a detailed
statement on "any adverse environmental effects which cannot be
avoided should the proposal be implemented," 42 U.S.C.
Page 490 U. S. 352
§ 4332(C)(ii), is an understanding that the EIS will discuss the
extent to which adverse effects can be avoided.
See D.
Mandelker, NEPA Law and Litigation § 10:38 (1984). More generally,
omission of a reasonably complete discussion of possible mitigation
measures would undermine the "action-forcing" function of NEPA.
Without such a discussion, neither the agency nor other interested
groups and individuals can properly evaluate the severity of the
adverse effects. An adverse effect that can be fully remedied by,
for example, an inconsequential public expenditure is certainly not
as serious as a similar effect that can only be modestly
ameliorated through the commitment of vast public and private
resources. Recognizing the importance of such a discussion in
guaranteeing that the agency has taken a "hard look" at the
environmental consequences of proposed federal action, CEQ
regulations require that the agency discuss possible mitigation
measures in defining the scope of the EIS, 40 CFR § 1508.25(b)
(1987), in discussing alternatives to the proposed action, §
1502.14(f), and consequences of that action, § 1502.16(h), and in
explaining its ultimate decision, § 1505.2(c).
There is a fundamental distinction, however, between a
requirement that mitigation be discussed in sufficient detail to
ensure that environmental consequences have been fairly evaluated,
on the one hand, and a substantive requirement that a complete
mitigation plan be actually formulated and adopted, on the other.
In this case, the off-site effects on air quality and on the mule
deer herd cannot be mitigated unless nonfederal government agencies
take appropriate action. Since it is those state and local
governmental bodies that have jurisdiction over the area in which
the adverse effects need be addressed, and since they have the
authority to mitigate them, it would be incongruous to conclude
that the Forest Service has no power to act until the local
agencies have reached a final conclusion on what mitigating
measures
Page 490 U. S. 353
they consider necessary. [
Footnote 16] Even more significantly, it would be
inconsistent with NEPA's reliance on procedural mechanisms -- as
opposed to substantive, result-based standards -- to demand the
presence of a fully developed plan that will mitigate environmental
harm before an agency can act.
Cf. Baltimore Gas & Electric
Co., 462 U.S. at
462 U. S. 100
("NEPA does not require agencies to adopt any particular internal
decisionmaking structure").
We thus conclude that the Court of Appeals erred, first, in
assuming that "NEPA requires that
action be taken to mitigate
the adverse effects of major federal actions,'" 833 F.2d at 819
(quoting Stop H-3 Assn. v. Brinegar, 389 F.Supp. at 1111),
and, second, in finding that this substantive requirement entails
the further duty to include in every EIS "a detailed explanation of
specific measures which will be employed to mitigate the
adverse impacts of a proposed action," 833 F.2d at 819 (emphasis
supplied).
Page 490 U. S. 354
III
The Court of Appeals also concluded that the Forest Service had
an obligation to make a "worst case analysis" if it could not make
a reasoned assessment of the impact of the Early Winters project on
the mule deer herd. Such a "worst case analysis" was required at
one time by CEQ regulations, but those regulations have since been
amended. Moreover, although the prior regulations may well have
expressed a permissible application of NEPA, the Act itself does
not mandate that uncertainty in predicting environmental harms be
addressed exclusively in this manner. Accordingly, we conclude that
the Court of Appeals also erred in requiring the "worst case"
study.
In 1977, President Carter directed that CEQ promulgate binding
regulations implementing the procedural provisions of NEPA.
Exec.Order No. 11991, 3 CFR 123 (1977 Comp.). Pursuant to this
presidential order, CEQ promulgated implementing regulations. Under
§ 1502.22 of these regulations -- a provision which became known as
the "worst case requirement" -- CEQ provided that, if certain
information relevant to the agency's evaluation of the proposed
action is either unavailable or too costly to obtain, the agency
must include in the EIS a "worst case analysis and an indication of
the probability or improbability of its occurrence." 40 CFR §
1502.22 (1985). In 1986, however, CEQ replaced the "worst case"
requirement with a requirement that federal agencies, in the face
of unavailable information concerning a reasonably foreseeable
significant environmental consequence, prepare "a summary of
existing credible scientific evidence which is relevant to
evaluating the . . . adverse impacts" and prepare an "evaluation of
such impacts based upon theoretical approaches or research methods
generally accepted in the scientific community." 40 CFR §
1502.22(b) (1987). The amended regulation thus
"retains the duty to describe the consequences of a remote, but
potentially severe impact, but grounds the duty in evaluation of
scientific opinion, rather
Page 490 U. S. 355
than in the framework of a conjectural 'worst case
analysis.'"
50 Fed.Reg. 32237 (1985).
The Court of Appeals recognized that the "worst case analysis"
regulation has been superseded, yet held that "[t]his rescission .
. . does not nullify the requirement, . . . since the regulation
was merely a codification of prior NEPA case law." 833 F.2d at 817,
n. 11. This conclusion, however, is erroneous in a number of
respects. Most notably, review of NEPA case law reveals that the
regulation, in fact, was not a codification of prior judicial
decisions.
See Note, 86 Mich.L.Rev. 777, 798, 800-802,
813-814 (1988). The cases cited by the Court of Appeals ultimately
rely on the Fifth Circuit's decision in
Sierra Club v.
Sigler, 695 F.2d 957 (1983).
Sigler, however, simply
recognized that the "worst case analysis" regulation codified the
"judicially created principl[e]" that an EIS must "consider the
probabilities of the occurrence of any environmental effects it
discusses."
Id. at 970-971. As CEQ recognized at the time
it superseded the regulation, case law prior to the adoption of the
"worst case analysis" provision did require agencies to describe
environmental impacts even in the face of substantial uncertainty,
but did not require that this obligation necessarily be met through
the mechanism of a "worst case analysis."
See 51 Fed.Reg.
15625 (1986). CEQ's abandonment of the "worst case analysis"
provision, therefore, is not inconsistent with any previously
established judicial interpretation of the statute.
Nor are we convinced that the new CEQ regulation is not
controlling simply because it was preceded by a rule that was in
some respects more demanding. In
Andrus v. Sierra Club,
442 U.S. at
442 U. S. 358,
we held that CEQ regulations are entitled to substantial deference.
In that case, we recognized that, although less deference may be in
order in some cases in which the "
administrative guidelines'"
conflict "`with earlier pronouncements of the agency,'"
ibid. (quoting General Electric Co. v. Gilbert,
429 U. S. 125,
429 U. S. 143
(1976)), substantial deference is nonetheless appropriate if there
appears to have
Page 490 U. S. 356
been good reason for the change, 442 U.S. at
442 U. S. 358.
Here, the amendment only came after the prior regulation had been
subjected to considerable criticism. [
Footnote 17] Moreover, the amendment was designed to
better serve the twin functions of an EIS -- requiring agencies to
take a "hard look" at the consequences of the proposed action and
providing important information to other groups and individuals.
CEQ explained that, by requiring that an EIS focus on reasonably
foreseeable impacts, the new regulation
"will generate information and discussion on those consequences
of greatest concern to the public and of greatest relevance to the
agency's decision,"
50 Fed.Reg. 32237 (1985), rather than distorting the
decisionmaking process by overemphasizing highly speculative harms,
51 Fed.Reg. 15624-15625 (1986); 50 Fed.Reg. 32236 (1985). In light
of this well considered basis for the change, the new regulation is
entitled to substantial deference. Accordingly, the Court of
Appeals erred in concluding that the Early Winters Study is
inadequate because it failed to include a "worst case analysis."
[
Footnote 18]
Page 490 U. S. 357
IV
The Court of Appeals also held that the Forest Service's failure
to develop a complete mitigation plan violated the agency's own
regulations. 833 F.2d at 814, n. 3, 819, and n. 14. Those
regulations require that an application for a special use permit
include
"measures and plans for the protection and rehabilitation of the
environment during construction, operation, maintenance, and
termination of the project,"
36 CFR § 251.54(e)(4) (1988), and that
"[e]ach special use authorization . . . contain . . . [t]erms
and conditions which will . . . minimize damage to scenic and
esthetic values and fish and wildlife habitat and otherwise protect
the environment,"
§ 251.56(a)(1)(ii). Applying those regulations, the Court of
Appeals concluded that,
"[s]ince the mitigation 'plan' here at issue is so vague and
undeveloped as to be wholly inadequate, . . . the Regional
Forester's decision to grant the special use permit could be none
other than arbitrary, capricious and an abuse of discretion."
833 F.2d at 814, n. 3. We disagree.
The Early Winters Study made clear that on-site effects of the
development will be minimal, and will be easily mitigated. For
example, the Study reported that
"[i]mpacts from construction, maintenance and operation of the
proposed 'hill' development on National Forest land will not have a
measurable effect on existing or future air quality,"
Early Winters Study 65, and that "[t]he effect development and
operation of the ski hill would have on deer migration should be
minor,"
id. at 76. Given the limited on-site effects of
the proposed
Page 490 U. S. 358
development, the recommended ameliorative steps -- which, for
example, called for "prompt revegetation of all disturbed areas,"
id. at 69, and suggested locating "new service roads away
from water resources and fawning cover,"
id. at 16 --
cannot be deemed overly vague or underdeveloped.
The Court of Appeals' conclusion that the Early Winters Study's
treatment of possible mitigation measures is inadequate apparently
turns on the court's review of the proposed off-site measures.
Although NEPA and CEQ regulations require detailed analysis of both
on-site and off-site mitigation measures,
see, e.g., 40
CFR § 1502.16(b) (1987), there is no basis for concluding that the
Forest Service's own regulations must also be read in all cases to
condition issuance of a special use permit on consideration (and
implementation) of off-site mitigation measures. The Forest Service
regulations were promulgated pursuant to a broad grant of
authority
"to permit the use and occupancy of suitable areas of land
within the national forests . . . for the purpose of constructing
or maintaining hotels, resorts, and any other structures or
facilities necessary or desirable for recreation, public
convenience, or safety,"
16 U.S.C. § 497, and were not based on the more direct
congressional concern for environmental quality embodied in NEPA.
[
Footnote 19]
See
H.R.Rep. No. 99-709, pt. 1, p. 2 (1986). As is clear from the text
of the permit issued to MRI, the Forest Service has decided to
implement its mitigation regulations by imposing appropriate
controls over MRI's actual development and operation during the
term of the permit. [
Footnote
20] It was surely not unreasonable for the Forest
Page 490 U. S. 359
Service in this case to have construed those regulations as not
extending to actions that might be taken by Okanogan County or the
State of Washington to ameliorate the off-site effects of the Early
Winters project on air quality and the mule deer herd. This
interpretation of the agency's own regulation is not "plainly
erroneous or inconsistent with the regulation," and is thus
controlling.
Bowles v. Seminole Rock & Sand Co.,
325 U. S. 410,
325 U. S. 414
(1945).
See also Lyng v. Payne, 476 U.
S. 926,
476 U. S. 939
(1986);
Udall v. Tallman, 380 U. S.
1,
380 U. S. 16-17
(1965).
V
In sum, we conclude that NEPA does not require a fully developed
plan detailing what steps will be taken to mitigate adverse
environmental impacts, and does not require a "worst case
analysis." In addition, we hold that the Forest Service has adopted
a permissible interpretation of its own regulations. The judgment
of the Court of Appeals is accordingly reversed, and the case is
remanded for further proceedings consistent with this opinion.
It is so ordered.
[
Footnote 1]
In the order granting certiorari, we consolidated this case with
Marsh v. Oregon Natural Resources Council, No. 87-1704.
See 487 U.S. 1217 (1988). Our decision in
Marsh
appears
post, p.
490 U. S. 360.
[
Footnote 2]
The developer is chosen based on: (1) "[k]ind and quality of
services to be offered"; (2) "[f]inancial capability"; (3)
"[e]xperience and qualifications in relation to the proposed use";
(4) "[a]bility to perform according to permit terms including
Federal, State, and local laws"; and (5) "[c]ontrol of private
lands necessary to develop the proposed use." U.S. Dept. of
Agriculture, Forest Service, Final EIS, Early Winters Alpine Winter
Sports Study 4 (1984).
[
Footnote 3]
The 1970 report was entitled the North Cascades Winter Sports
Study. Its conclusion that Sandy Butte is well suited for
development as an alpine ski resort was repeated in the Joint Plan
for the North Cascades area, which was issued by the Park Service
and the Forest Service in 1974.
See App. to Pet. for Cert.
23a.
[
Footnote 4]
See 98 Stat. 299. In the Senate Committee Report
explaining the decision to exclude Sandy Butte from the wilderness
designation in the bill, the Committee made this quite remarkable
comment for a legislative committee:
"The Forest Service and the Department of Agriculture are
directed to allow the evaluation process for the Sandy Butte
development to proceed without additional delay. . . ."
S.Rep. No. 98-461, p. 11 (1984).
[
Footnote 5]
The Study recommended the following action:
"1. The County will initiate the formation of an Air Quality
Control Authority or similar administrative structure pursuant to
Washington State statutes."
"2. The County will develop an airshed management plan that
incorporates strategies which will result in ambient air quality
standards for the Methow Valley that are stricter than existing
State standards. As part of the airshed management plan, the
following mitigation measures will be considered:"
"-- Development of land use codes specifically addressing site
development and project design directed at energy efficiency and
air pollution control."
"-- Requiring all new construction to be fully weatherized to
reduce the need for supplemental heating sources (
i.e.,
wood) beyond the central facilities heating needs."
"-- Restricting the number of fireplaces and wood stoves. At a
minimum, few fireplaces should be allowed in accommodations
constructed for tourist use."
"-- Encouraging the use of alternative, nonpolluting energy
sources."
"-- Establishing a certification mechanism for wood stoves and
fireplace inserts."
"-- Establishing an air pollution monitoring system specifically
designed to alert local residents to impending pollution episodes
and to record long-term changes in air quality levels. Such
long-term data will be used to evaluate the success or failure of
the mitigation and impose more stringent measures if standards are
violated."
"-- Development of enforcement measures to assure that standards
will be met."
Early Winters Study 68-69.
[
Footnote 6]
The Study recommended the following on-site, air quality
mitigation measures:
"1. The Master Plan will require prompt revegetation of all
disturbed areas and the mandatory application of dust control
measures (
e.g., rocking and oiling) on unpaved
construction roads."
"2. The construction phase will follow established Forest
Service/State of Washington smoke management practices identified
in the Washington State Smoke Management Plan. The Master Plan will
identify opportunities for utilization of waste wood, generated by
the project, thereby minimizing open burning."
Id. at 69.
[
Footnote 7]
Id. at 76. The Study predicted that development of the
ski area would diminish available summer range for the deer by
between five and ten percent, depending on the level of development
chosen. Moreover, it recognized that, although disturbance would be
greatest during fawning season, "[f]awning would not be adversely
affected with implementation of mitigation measures."
Id.
at 75-76.
[
Footnote 8]
The EIS listed the following opportunities for on-site
mitigation:
"a) Locate runs, lifts, roads, and other facilities to minimize
disturbance of blue grouse wintering areas (primarily
ridgetops)."
"b) Leave dead and defective trees standing in timbered areas
where skier safety can be protected."
"c) Restrict activities and travel on selected roads during the
fawning season (June)."
"d) Locate new service roads away from water sources and fawning
cover."
"e) Evaluate impact to mule deer migration routes in review of
Master Plan."
"f) Design and harvest nearby, off-site timber sales to retain
adequate travel corridors, foraging, roosting, and nesting sites
for spotted owls."
"g) Protect other likely migration routes between summer and
winter habitats for spotted owls."
"h) Restrict other activities within the spotted owls home
range."
"i) Springs and riparian areas in the permit area will be
protected as water sources and wildlife habitat. . . ."
Id. at 16-17. The Study further noted that additional
mitigation opportunities might result from review of the master
plan.
Id. at 77.
[
Footnote 9]
The Study listed the following steps that state and local
government might take to mitigate off-site effects:
"[1] Limit development on deer winter range and along migration
routes through rezoning options, tax incentives and other
means."
"Since loss of winter range and disruption of migration routes
are primarily concerns which will cause declines in deer numbers,
protection of vital portions will be assured prior to a ski hill
development. Rezoning is essential and will occur, to include
County rezoning options such as:"
"(a) The Methow Review District which is currently applied to
obtain certain densities, open space, and design."
"(b) Other optional zone districts such as Conservation
Districts which are available for amending existing zoning and
protecting environmentally sensitive lands."
"Other measures are probably needed, and which could occur,
include:"
"(c) Conservation Easements between private individuals and
trust agencies (
e.g., Washington Department of Game)
should be encouraged. Benefits would occur to both the landowner,
in the form of tax breaks, and the wildlife resource in the form of
undeveloped
status quo habitat."
"(d) Acquisition of certain land tracts essential to migrating
deer may be needed to insure continued passage. These lands would
be administered by a wildlife management agency (
e.g.,
Washington Department of Game)."
"[2] Minimize potential road kills of deer and other wildlife by
use of warning signs, speed limits, and roadway design where
wildlife crossings and high speed driving occur. Responsibility
rests with the appropriate agency's road department (
i.e.,
County, State, Federal) in the Methow Valley."
"[3] Protect wildlife from free-ranging dogs through County
ordinances that are enforceable."
"[4] Through zoning, discourage development in riparian
areas."
Id. at 77-78.
[
Footnote 10]
His decision did not identify a particular developer, but rather
simply authorized the taking of competitive bids. App. to Pet. for
Cert. 63a. It was not until July 21, 1986, almost one month after
the District Court affirmed the Forester's decision, that a special
use permit was issued to MRI.
[
Footnote 11]
The four organizations were Methow Valley Citizens Council,
Washington State Sportsmen's Council, Washington Environmental
Council, and the Cascade Chapter, Sierra Club. These organizations,
with the exception of Washington State Sportsmen's Council, are
respondents herein. MRI, the permittee, is also a respondent in
this Court, but, since it supports the Government's action, we
shall use the term "respondents" to refer only to the opponents of
the Early Winters proposal.
[
Footnote 12]
Respondents also alleged violations of the National Forest
Management Act of 1976, 16 U.S.C. §§ 1600-1614, and the Clean Air
Act, 42 U.S.C. §§ 7401-7626. These claims were dismissed on
petitioner's motion for summary judgment, and are no longer in
issue. App. to Pet. for Cert. 22a.
[
Footnote 13]
The CEQ regulations require that, after preparing a draft EIS,
the agency request comments from other federal agencies,
appropriate state and local agencies, affected Indian tribes, any
relevant applicant, the public generally, and, in particular,
interested or affected persons or organizations. 40 CFR § 1503.1
(1987). In preparing the final EIS, the agency must
"discuss at appropriate points . . . any responsible opposing
view which was not adequately discussed in the draft statement and
[must] indicate the agency's response to the issue raised."
§ 1502.9.
See also § 1503.4.
[
Footnote 14]
See,
e.g., the Endangered Species Act of 1973, 87 Stat.
892, 16 U.S.C. § 1536(a)(2) (requiring that every federal agency
"insure that any action authorized, funded, or carried out by such
agency . . . is not likely to jeopardize the continued existence of
any endangered species or threatened species"); the Department of
Transportation Act of 1966, 49 U.S.C. § 303 (Secretary of
Transportation may approve "use of publicly owned land of a public
park, recreation area, or wildlife and waterfowl refuge . . . or
land of an historic site . . . only if . . . there is no prudent
and feasible alternative to using that land; and . . . the program
or project includes all possible planning to minimize harm to the
[area] resulting from the use").
[
Footnote 15]
CEQ regulations define "mitigation" to include:
"(a) Avoiding the impact altogether by not taking a certain
action or parts of an action."
"(b) Minimizing impacts by limiting the degree or magnitude of
the action and its implementation."
"(c) Rectifying the impact by repairing, rehabilitating, or
restoring the affected environment."
"(d) Reducing or eliminating the impact over time by
preservation and maintenance operations during the life of the
action."
"(e) Compensating for the impact by replacing or providing
substitute resources or environments."
40 CFR § 1508.20 (1987).
[
Footnote 16]
After the Early Winters Study was completed and distributed, the
Forest Service, the Environmental Protection Agency, the State
Department of Ecology, and Okanogan County entered into a
memorandum of understanding (MOU) committing various parties to
take certain actions in mitigation. App. to Pet. for Cert. 45a-46a.
In concluding that this agreement did not satisfy the mitigation
discussion requirement, the Court of Appeals wrote:
"[T]he MOU offers no assurance whatsoever that the vague
mitigation objectives it features -- performance of almost all of
which would be the responsibility of third parties to the permit
process -- would ever in fact be achieved, or even that effective
measures would ever be designed (let alone implemented), if the
Early Winters development were to proceed.
Cf. Preservation
Coalition [v. Pierce, 667 F.2d 851, 860 (CA9 1982)] ("Since
many of the
mitigations' proposed by the agency were . . .
potential actions to be taken by [third parties], reliance on them
. . . was improper")."
Methow Valley Citizens Council v. Regional Forester,
833 F.2d 810, 819-820 (CA9 1987). Because NEPA imposes no
substantive requirement that mitigation measures actually be taken,
it should not be read to require agencies to obtain an assurance
that third parties will implement particular measures.
[
Footnote 17]
As CEQ explained:
"Many respondents to the Council's Advance Notice of Proposed
Rulemaking pointed to the limitless nature of the inquiry
established by this requirement; that is, one can always conjure up
a worse 'worst case' by adding an additional variable to a
hypothetical scenario. Experts in the field of risk analysis and
perception stated that the 'worst case analysis' lacks defensible
rationale or procedures, and that the current regulatory language
stands"
"without any discernible link to the disciplines that have
devoted so much thought and effort toward developing rational ways
to cope with problems of uncertainty. It is, therefore, not
surprising that no one knows how to do a worst case analysis. . .
."
Slovic, P., February 1, 1985, Response to ANPRM.
"Moreover, in the institutional context of litigation over
EIS(s) the 'worst case' rule has proved counterproductive, because
it has led to agencies' being required to devote substantial time
and resources to preparation of analyses which are not considered
useful to decisionmakers and divert the EIS process from its
intended purpose."
50 Fed.Reg. 32236 (1985).
[
Footnote 18]
Amicus curiae Center for Environmental Education argues
that the Court of Appeals properly applied the "worst case
analysis" provision, because the new regulation only applies to
"environmental impact statements for which a Notice of Intent (40
CFR § 1508.22) [was] published . . . on or after May 27, 1986." 40
CFR § 1502.22(c) (1987). The grandfather clause of the regulation,
however, further specifies that agencies have the option of
applying the old or new regulation to EIS's commenced prior to May
27, 1986, that are still "in progress" after that date.
Ibid. Because the Court of Appeals ordered that the Forest
Service revise the Early Winters Study, and because such a revision
is necessary even though we hold today that the Court of Appeals
erred in part, the Study remains "in progress," and thus the Forest
Service is entitled to rely on the new regulation.
[
Footnote 19]
In October, 1986, after the Forest Service issued its special
use permit to MRI, Congress substantially revised the process for
authorizing use of lands within the National Forest system for
nordic and alpine ski operations.
See National Forest Ski
Area Permit Act of 1986, 100 Stat. 3000, 16 U.S.C. § 497b (1982
ed., Supp. V). These new procedures are not in issue in this
case.
[
Footnote 20]
The special use permit provides, in part, that the permittee
"shall submit plans to reasonably restore or protect all areas
disturbed during construction," and that
"[e]ach stage of construction will be considered complete only
upon completion and acceptance of the successful seeding and
planting in the vicinity of construction,"
Special Use Authorization 17 (July 21, 1986); that the permittee
shall prevent soil erosion "by carrying out the provisions of the
erosion control plan prepared by the holder and approved by the
authorized officer,"
id. at 19; that "[p]esticides may not
be used to control undesirable woody and herbaceous vegetation,
aquatic plants, insects, rodents, etc., without the prior written
approval of the Forest Service,"
ibid., and that "[o]pen
fireplaces shall be equipped with spark screens,"
id. at
20.
JUSTICE BRENNAN, concurring.
I write separately to highlight the Court's observation that
"one important ingredient of an EIS is the discussion of steps that
can be taken to mitigate adverse environmental consequences."
Ante at
490 U. S.
351.