A plumbing and heating subcontractor brought suit under the
Miller Act in a Federal District Court in Georgia against a prime
contractor under contracts with the United States for construction
work at two Air Force bases in Georgia seeking (1) recovery of
amounts alleged to be due under the subcontracts, or (2) rescission
of the subcontracts on grounds of fraud and recovery on a
quantum meruit basis, or (3) recovery of the reasonable
value of the labor and materials furnished, and (4) to enjoin the
prime contractor from pursuing litigation which it had instituted
in a New York State Court seeking arbitration proceedings in New
York under provisions of the subcontracts, which the subcontractor
claimed to be fraudulent. The District Court held that (1) the
Miller Act gave the subcontractor the right to sue in the District
where the subcontracts were performed and (2) the arbitration
clause, if induced by fraud, would be vitiated; and it enjoined the
arbitration proceedings in New York. The Court of Appeals reversed,
holding that the subcontractor must arbitrate in New York under New
York law.
Held: The issue of fraud must first be determined by
the District Court, since a determination that the subcontracts or
their arbitration provisions were fraudulent would eliminate any
conflict between them, the United States Arbitration Act and the
Miller Act. Pp.
374 U. S.
168-172.
306 F.2d 554 reversed.
Page 374 U. S. 168
MR. JUSTICE CLARK delivered the opinion of the Court.
The primary issue in this case is whether a claim under the
Miller Act, 40 U.S.C. §§ 270a-270d, as amended, based upon
arbitration clauses in two subcontracts providing for arbitration
of any dispute arising thereunder, is enforceable under the
provisions of the United States Arbitration Act. 9 U.S.C. §§ 1, 2
and 3. The institution of this suit was directed toward the
recovery of compensation alleged to be due under two subcontracts
between the petitioner, a plumbing and heating contractor, and the
respondent Electronic & Missile Facilities, Inc., who was the
prime contractor under a contract with the United States Corps of
Engineers, Savannah District, covering certain Nike Hercules
missile installations at Robins Air Force Base Defense Area and
Turner Air Force Base Defense Area, both of which are located in
the State of Georgia. The subcontracts provided for arbitration in
New York, and, disputes having arisen thereunder, the respondent
filed suit in the Supreme Court of New York seeking an order
directing arbitration in accordance with the arbitration
provisions. Petitioner then filed this suit in the Middle District
of Georgia, where the work under the subcontracts was performed,
seeking (1) recovery of the amounts alleged to be due under the
subcontracts; (2) rescission of the subcontracts -- on grounds of
fraud -- and recovery on a
quantum meruit basis; (3) in
the alternative, failing in both of these claims, recovery of the
reasonable value of the labor and materials furnished; and (4) an
injunction enjoining the respondent from proceeding with its
arbitration efforts in New York. Neither party sought to compel
specific performance of the arbitration agreement. The District
Court, holding (1) that the Miller Act gave petitioner the right to
sue in the District Court where
Page 374 U. S. 169
the subcontracts were performed and (2) that the arbitration
clause, if induced by fraud on the part of respondent, would be
vitiated, made permanent its prior restraining order directed at
the arbitration proceedings in New York. The Court of Appeals
reversed, holding that petitioner must arbitrate in New York under
New York law. 306 F.2d 554. We granted certiorari. 371 U.S. 919.
Petitioner attacks the subcontracts, as well as the arbitration
agreement, as being fraudulent, and this issue, we conclude, must
be first determined by the District Court. We therefore reverse the
judgment and remand the case to the Court of Appeals with
directions to remand to the District Court for further proceedings
not inconsistent with this opinion.
I
We need not elaborate at length on the involved factual
situation, since it is detailed in the opinions of the Court of
Appeals and the District Court. As we have said, petitioner filed
suit in the United States District Court for the Middle District of
Georgia, the district in which the subcontracts were performed,
alleging breach of contract for refusal to pay and seeking recovery
for work which had been performed and, alternatively, rescission of
the subcontracts on grounds of fraud. The suit was brought under
the provisions of the Miller Act, which provides in pertinent
part:
"Every suit instituted under this section shall be brought in
the name of the United States for the use of the person suing, in
the United States District Court for any district in which the
contract was to be performed and executed and not elsewhere,
irrespective of the amount in controversy. . . ."
40 U.S.C. § 270b(b).
Page 374 U. S. 170
It further provides that parties included within the Act "shall
have the right to sue . . . and to prosecute said action to final
execution and judgment. . . ."
Id. at § 270b(a).
Respondent moved to dismiss the suit or stay the same so that the
New York arbitration suit might proceed under the terms of both
subcontracts, each of which provided that "[a]ny controversy or
claim arising out of or relating to" the subcontracts or their
breach would be submitted to arbitration in New York City under New
York law. In denying these motions, the District Court held that
the Arbitration Act did not apply here, since any other holding
would nullify the provisions of the Miller Act. It also concluded
that the allegations of fraud, if sustained, would, under Georgia
law, rescind the subcontracts, including the agreement for
arbitration.
The Court of Appeals, with one judge dissenting, reversed on the
theory that the Miller Act was not enacted for the benefit of
plaintiffs in the selection of a forum, but rather for the
convenience of the defendant, and that this is the type of dispute
that is and should be subject to arbitration. As to the issue of
fraud, it held that federal law controls in determining whether an
allegation of fraud precludes arbitration of a dispute arising
under the subcontracts, and concluded that, in order to bar
arbitration under federal law, the allegation of fraud must be
specifically directed to the arbitration clause, rather than to the
entire contract. Thus, it reversed the District Court on both
points.
II
At the outset we note, as we have indicated, that no request has
been made here for the enforcement of the arbitration agreement
included within the subcontracts. Indeed, the petitioner has
attacked not only the subcontracts, but also the arbitration
clauses contained therein,
Page 374 U. S. 171
as having been procured through fraud. With the pleadings in
this posture, we are obliged to pass upon the priority in
determination of that issue in the trial of the case. In essence,
petitioner alleges that the subcontracts with him, as well as other
subcontractors, were a fraudulent scheme to obtain a great amount
of work and material from petitioner and the other subcontractors
without making payment therefor, and to "browbeat" petitioner and
his fellow subcontractors into accepting much less than the value
of their claims. One of the means used to effect such scheme was
alleged to be the insertion in the subcontracts of an arbitration
clause requiring arbitration of disputes in New York. Under either
the Miller Act or the Arbitration Act, it seems clear that the
issue of fraud should first be adjudicated before the rights of the
parties under the subcontracts can be determined. It appears
necessary, therefore, that the District Court proceed first to
trial of this issue. In considering the question of the sufficiency
of the pleadings with reference to the allegation of fraud, we
believe that, as alleged here, the issue goes to the arbitration
clause itself, since it is contended that it was to be used to
effect the fraudulent scheme. If this issue is determined favorably
to the petitioner, there can be no arbitration under the
subcontracts.
In view of our holding here, it is not necessary to reach the
issues relating to arbitrability of disputes arising under these
subcontracts. In fact, disposition of the fraud issue may dispose
of the entire suit. In the event the fraud issue is decided
favorably to the respondent, and the United States District Court
for the Middle District of Georgia should be called upon to decide
the question of arbitrability of such disputes and related problems
in Miller Act cases, its decision on that point would then, of
course, be subject to review.
Page 374 U. S. 172
We therefore reverse the judgment of the Court of Appeals and
remand the case to it with instructions that it remand the same to
the District Court for further proceedings not inconsistent with
this opinion.
It is so ordered.
MR. JUSTICE STEWART would affirm the judgment substantially for
the reasons stated in Chief Judge Tuttle's opinion for the Court of
Appeals. 306 F.2d 554.
THE CHIEF JUSTICE and MR. JUSTICE BLACK, concurring.
We agree with the Court that fraud in the procurement of an
arbitration contract, like fraud in the procurement of any
contract, makes it void and unenforceable, and that this question
of fraud is a judicial one which must be determined by a court. To
allow this question to be decided by arbitrators would be, to that
extent, to enforce the arbitration agreement even though steeped in
the grossest kind of fraud.
Compare Robert Lawrence Co. v.
Devonshire Fabrics, 271 F.2d 402 (C.A.2d Cir. 1959). For this
reason, we acquiesce in the Court's present disposition of the case
on this single issue. But we point out that this disposition leaves
open questions of great importance to laborers and materialmen who,
under the Miller Act, are entitled to have their controversies
settled in independent courts of law:
(1) Can a member of the special class of laborers and
materialmen which Congress, in the public interest, has protected
by fixing the venue for their claims under the Miller Act in a
particular federal court deprive himself of that kind of remedy as
a condition of his obtaining the employment or the purchase of his
materials?
(2) Can any person, before any dispute has arisen, agree to
arbitrate all future disputes he may have, and
Page 374 U. S. 173
thereby lose his right to go into court to try his claim
according to due process of law?
(3) Can the Arbitration Act, in light of its language and
legislative history, be applied to laborers and materialmen or to
construction projects subject to the Miller Act?
(4) Is a construction project, like the one in this case, one
"involving commerce" so as to come within the restricted scope of
the Arbitration Act?