Case Resources
Search this Case
in Google Scholar
on the Web
Google Web Search
MSN Web Search
Yahoo! Web Search
in the News
Google News Search
Google News Archive Search
Yahoo! News Search
in the Blogs
BlawgSearch.com Search
Google Blog Search
Technorati Blog Search
in other Databases
Google Book Search
Online Research Resources
Cornell LII
Cornell Wex Dictionary & Encyclopedia
LLRX.com - Legal Research
Expert Witness Directory
Nolo Consumer & Business
US Court Forms
USA Constitution Annotated
WashLaw Directory
World LII
Online Case Law
Cornell LII
FastCase $
Lexis $
LexisOne
Loislaw $
USSCPlus.com $
VersusLaw $
Link to the Case Preview: http://supreme.justia.com/us/322/96/
Link to the Full Text of Case: http://supreme.justia.com/us/322/96/case.html
U.S. Supreme Court
United States v. American Surety Co., 322 U.S. 96 (1944)
United States v. American Surety Co.
No. 381
Argued March 27, 28, 1944
Decided April 24, 1944
322 U.S. 96
Syllabus
1. Under the Government construction contract here involved, the Government was not entitled to recover liquidated damages for delay in completion where, though subsequently to the specified completion date, the Government terminated the contractor's right to proceed. P. 322 U. S. 100.
2. A Government construction contract may validly provide for liquidated damages in limited situations only. Act of June 6, 1902, § 21. P. 322 U. S. 101.
136 F.2d 437 affirmed.
Certiorari, 320 U.S. 729, to review a judgment which reversed in part a Judgment for the United States in a suit upon a construction contract, 44 F.Supp. 871.