Case Resources
Search this Case
in Google Scholar
on the Web
Google Web Search
MSN Web Search
Yahoo! Web Search
in the News
Google News Search
Google News Archive Search
Yahoo! News Search
in the Blogs
BlawgSearch.com Search
Google Blog Search
Technorati Blog Search
in other Databases
Google Book Search
Online Research Resources
Cornell LII
Cornell Wex Dictionary & Encyclopedia
LLRX.com - Legal Research
Expert Witness Directory
Nolo Consumer & Business
US Court Forms
USA Constitution Annotated
WashLaw Directory
World LII
Online Case Law
Cornell LII
FastCase $
Lexis $
LexisOne
Loislaw $
USSCPlus.com $
VersusLaw $
Link to the Case Preview: http://supreme.justia.com/us/258/120/
Link to the Full Text of Case: http://supreme.justia.com/us/258/120/case.html
U.S. Supreme Court
Wood v. United States, 258 U.S. 120 (1922)
Wood v. United States
No. 100
Argued January 20, 1922
Decided February 27, 1922
258 U.S. 120
Syllabus
Where a public building contract provides that no claim shall be made or allowed for damages which may arise out of any delay caused by the government, damages due to delays caused by the government's suspension of the work cannot be recovered even though suspensions were not expressly authorized by the contract. So held where the contractor acquiesced in the first suspension and thereafter made no protest, nor any claim, until the suit was brought. P. 258 U. S. 121.
55 Ct.Clms. 533 affirmed.
Appeal from a judgment of the Court of Claims rejecting a claim for damages arising from suspension of work under claimants' contract.