Case Resources
Search this Case
in Google Scholar
on the Web
Google Web Search
MSN Web Search
Yahoo! Web Search
in the News
Google News Search
Google News Archive Search
Yahoo! News Search
in the Blogs
BlawgSearch.com Search
Google Blog Search
Technorati Blog Search
in other Databases
Google Book Search
Online Research Resources
Cornell LII
Cornell Wex Dictionary & Encyclopedia
LLRX.com - Legal Research
Expert Witness Directory
Nolo Consumer & Business
US Court Forms
USA Constitution Annotated
WashLaw Directory
World LII
Online Case Law
Cornell LII
FastCase $
Lexis $
LexisOne
Loislaw $
USSCPlus.com $
VersusLaw $
Link to the Case Preview: http://supreme.justia.com/us/223/524/
Link to the Full Text of Case: http://supreme.justia.com/us/223/524/case.html
U.S. Supreme Court
United States v. Ellicott, 223 U.S. 524 (1912)
United States v. Ellicott
No. 85
Argued December 7, 8, 1911
Decided February 26, 1912
223 U.S. 524
Syllabus
The general rule governing appeals is applicable to appeal from the Court of Claims.
A judgment is not generally treated as final until a motion for new trial or rehearing, which has been entertained by the court, has been disposed of; in such a case, the time for appeal runs from the date of such disposition. Kingman v. Western Manufacturing Co., 170 U. S. 675.
When there is an irreconcilable conflict between essential provisions of a contract for building and the specifications, and the latter cannot be ignored, the contract is void for uncertainty, and unenforceable.
Where a bid has been accepted for government work after the advertisement necessary to give it validity, and the final contract contains specifications materially lessening the work and at variance with the terms of the contract as advertised, the contractor cannot recover damages because the government abrogates the contract;
if the specifications are not binding on the government, the contractor has no basis for recovery, and if they are binding, the contract varies from the one advertised for, and has no validity, and so held as to a bid for barge for the Panama Canal Commission.
44 Ct.Cl. 127 and 45 Ct.Cl. 469, reversed.
The facts, which involve the construction of a contract for dredges for the Panama Canal and the liability of the United States for damages for abrogation of the same, are stated in the opinion.