Case Resources
Search this Case
in Google Scholar
on the Web
Google Web Search
MSN Web Search
Yahoo! Web Search
in the News
Google News Search
Google News Archive Search
Yahoo! News Search
in the Blogs
BlawgSearch.com Search
Google Blog Search
Technorati Blog Search
in other Databases
Google Book Search
Online Research Resources
Cornell LII
Cornell Wex Dictionary & Encyclopedia
LLRX.com - Legal Research
Expert Witness Directory
Nolo Consumer & Business
US Court Forms
USA Constitution Annotated
WashLaw Directory
World LII
Online Case Law
Cornell LII
FastCase $
Lexis $
LexisOne
Loislaw $
USSCPlus.com $
VersusLaw $
Link to the Case Preview: http://supreme.justia.com/us/165/340/
Link to the Full Text of Case: http://supreme.justia.com/us/165/340/case.html
U.S. Supreme Court
District of Columbia v. Hall, 165 U.S. 340 (1897)
District of Columbia v. Hall
No. 619
Submitted January 4, 1897
Decided February 16, 1897
165 U.S. 340
APPEAL FROM THE COURT OF APPEALS
Syllabus
District of Columbia v. Johnson, 165 U. S. 330, approved and followed.
The case is stated in the opinion.
MR. JUSTICE PECKHAM delivered the opinion of the Court.
This is another of the same character of actions as those above disposed of. Hall was one of the contractors for doing work of the same nature, and filed his petition under the act of 1880 in December of that year. In that petition, he alleged that he had done certain work, and that he was paid for his work, under his contract, by certain certificates, which were worth only fifty percent of their face value, and which he consented to receive only at that rate, and he asked for judgment for the other fifty percent of his contract price. He failed in the primary object of that suit, but he did recover on some other ground a small judgment of about $1,000, which was entered June 1, 1885. Subsequently, and in pursuance of the act of 1895, he applied for a new trial for the purpose of claiming the "board rates" compensation for the work done by him at contract prices, under circumstances mentioned in the foregoing cases. The Court of Claims gave judgment in his favor for that difference between the two rates, and found that, under the true intent and meaning of the acts of 1895 and 1880 the sum for which it gave judgment "became due and payable on the 1st of January, 1877," which was the date when the plaintiff had completed his work under the contract. 31 Ct.Cl. 376.
For the reasons mentioned in the foregoing cases, the judgment of the Court of Claims in this case must also be
Reversed, and the cause remanded for further proceedings not inconsistent with that opinion.