UNITED STATES V. MUELLER, 113 U. S. 153 (1885)

Subscribe to Cases that cite 113 U. S. 153 RSS feed for this section

Link to the Case Preview: http://supreme.justia.com/us/113/153/

Link to the Full Text of Case: http://supreme.justia.com/us/113/153/case.html

U.S. Supreme Court

United States v. Mueller, 113 U.S. 153 (1885)

United States v. Mueller

Submitted December 22, 1884

Decided January 19, 1885

113 U.S. 153

Syllabus

Under contracts to furnish stone to the United States for a building, and to saw it, and cut and dress it, all as "required," the contractor may recover damages for enforced suspensions of, and delays in, the work by the United States arising from doubts as to the desirability of completing the building with the stone and on the site, which involved the examination of the foundation and the stone by several commissions.

A contract to furnish "all of the dimension stone that may be required in the construction" of a building does not include dimension stone used in "the approaches or steps leading up into the building."

The facts in this case are stated in the opinion of the Court.