Horowitz v. United States - 267 U.S. 458 (1925)
- Syllabus
- Case
U.S. Supreme Court
Horowitz v. United States, 267 U.S. 458 (1925)
Horowitz v. United States
No. 74
Argued October 15, 1924
Decided March 9, 1925
267 U.S. 458
Syllabus
1. The United States, when sued as a contractor, cannot be held liable for an obstruction to the performance of the particular contract resulting from its public and general acts as a sovereign. P. 267 U. S. 460.
2. So held where the government, having sold silk to the claimant, did not ship it promptly, owing to an embargo placed on freight shipments of silk by the United States Railroad Administration, so that the claimant lost his opportunity to resell at a profit.
58 Ct.Cls. 189 affirmed.
Appeal from a judgment of the Court of Claims dismissing the petition upon demurrer.
Official Supreme Court caselaw is only found in the print version of the United States Reports. Justia caselaw is provided for general informational purposes only, and may not reflect current legal developments, verdicts or settlements. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or information linked to from this site. Please check official sources.