Hobbs v. Head & Dowst Co.
231 U.S. 692 (1914)

Annotate this Case

U.S. Supreme Court

Hobbs v. Head & Dowst Co., 231 U.S. 692 (1914)

Hobbs v. Head & Dowst Company

No. 148

Argued December 18, 19, 1913

Decided January 5, 1914

231 U.S. 692

Syllabus

Even though contractors may not be entitled to a mechanics' lien under the statute unless the contract be completed, they may be entitled thereto if absolute completion is waived, and in this case, this Court will not go behind the finding of the master followed by the court below that there was a waiver and the contractor was justified in stopping work.

Where the state trial court had upheld a mechanics' lien before the petition and the trustee in bankruptcy seeks in the federal court to prevent the enforcement of the lien, this Court will not go behind the state judgment because exceptions thereto had not been passed upon owing to the action of those representing the estate.

In this case, this Court is satisfied that substantial justice has been

Page 231 U. S. 693

done in enforcing a lien for over $45,000 admittedly due to the contractor but contested because about $1,000 of work remained uncompleted on a contract of $187,000, the contractors having ceased work after the owner of the building had failed in its payments and was hopelessly insolvent.

175 F. 501 affirmed.

The facts, which involve the validity of lien for labor and materials on property of a bankrupt, and the necessity for completion of the contract in order to maintain the lien, are stated in the opinion.

Page 231 U. S. 699

Official Supreme Court case law is only found in the print version of the United States Reports. Justia case law is provided for general informational purposes only, and may not reflect current legal developments, verdicts or settlements. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or information linked to from this site. Please check official sources.